| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
|
PC Allied Health Phase II
|
||
| Design Start: Dec 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $200,000 | Costs to Date: $148,934 | Balance: $51,066 |
| Weekly Update: 11/6/2025: Construction is complete. Meeting to take place with the Contractor and the Engineer for project sign off. | ||
|
PC Asphalt Repairs Parking Lot A & B
|
||
| Design Start: Apr 2025 | Project Status: Close-out |
Funding Source: Local C.O. PC |
| Budget/PPR: $1,500,000 | Costs to Date: $357,455 | Balance: $1,142,545 |
| Weekly Update: 11/6/25: Punch list 100% complete. Closeout in progress. | ||
|
PC Baseball/Softball Fields
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $8,273,400 | Costs to Date: $8,250,377 | Balance: $23,023 |
| Weekly Update: 11/6/2025: Construction 98% complete. Contractor completing civil, architectural and landscaping punch list. Owner punch list 11/10/25. | ||
|
PC Basic Needs Remodel
|
||
| Design Start: Aug 2024 | Project Status: Close-out |
Funding Source: Other |
| Budget/PPR: $592,835 | Costs to Date: $0 | Balance: $592,835 |
| Weekly Update: 11/14/2025: Construction 100% complete. Furniture punch list items in progress. Closeout in progress. | ||
|
PC Campus Wide Building Upgrades
|
||
| Design Start: Apr 2025 | Project Status: Close-out |
Funding Source: Meas. G |
| Budget/PPR: $600,000 | Costs to Date: $0 | Balance: $600,000 |
| Weekly Update: 11/6/2025: Safety repairs completed in the Art and Speech rooms. District to set up meeting with campus to discuss upcoming project. | ||
|
PC Classroom Modernization (FF&E & Flooring)
|
||
| Design Start: Jul 2019 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $700,000 | Costs to Date: $573,547 | Balance: $126,453 |
| Weekly Update: 11/6/2025: Campus working on next phase. | ||
|
PC College Avenue Realignment
|
||
| Design Start: Aug 2021 | Project Status: Close-out |
Funding Source: Meas. J |
| Budget/PPR: $7,164,800 | Costs to Date: $7,030,974 | Balance: $133,826 |
| Weekly Update: 11/6/2025: Closeout in progress. | ||
|
PC Fine Arts Darkroom & Career Remodel
|
||
| Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: Local C.O. PC Local C.O. PC |
| Budget/PPR: $1,479,683 | Costs to Date: $1,479,682 | Balance: $1 |
| Weekly Update: 11/6/25: Closeout in progress. | ||
|
PC Fitness Center Remodel Title 9
|
||
| Design Start: Feb 2025 | Project Status: In Design |
Funding Source: Local C.O. PC |
| Budget/PPR: $6,252,000 | Costs to Date: $518,625 | Balance: $5,733,375 |
| Weekly Update: 11/6/25: Campus to meet with architect on 11/10/25 to make final selection on what plan they would like to move forward with. Plans in progress to submit to DSA. | ||
|
PC HVAC Upgrades
|
||
| Design Start: Jul 2019 | Project Status: In Const |
Funding Source: Meas. J Other Other |
| Budget/PPR: $1,443,849 | Costs to Date: $722,365 | Balance: $721,484 |
| Weekly Update: 11/6/25: Small projects ongoing. Working on pricing for remaining equipment. District to meet with the campus to determine the next step. | ||
|
PC Land Acquisition Phase II
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $400,000 | Costs to Date: $0 | Balance: $400,000 |
| Weekly Update: 11/14/25 Working with campus to finalize agreement. | ||
|
PC Lighting Retrofit Fine Arts Gallery and Room #3 Remodel
|
||
| Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Other |
| Budget/PPR: $47,271 | Costs to Date: $0 | Balance: $47,271 |
| Weekly Update: 11/6/2025: Closeout PPR in progress. Requested campus to do an audit on construction costs. District to follow up. | ||
|
PC Measure G Future Allocation
|
||
| Design Start: Nov 2021 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $0 | Costs to Date: $0 | Balance: $0 |
| Weekly Update: Complete audit of Measure G in progress. | ||
|
PC Multicultural & Interactive Garden
|
||
| Design Start: Jan 2023 | Project Status: In Design |
Funding Source: Local C.O. PC Local C.O. PC |
| Budget/PPR: $3,699,041 | Costs to Date: $448,581 | Balance: $3,250,460 |
| Weekly Update: 11/6/2025: Plans are in review with DSA and City of Porterville. DSA plan approval anticipated by December 2025. Bidding anticipated mid-January 2025. Construction to start early 2026. | ||
|
PC SMSR 2021-2022 Exterior Lighting Safety Retrofit
|
||
| Design Start: Mar 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $274,142 | Costs to Date: $238,636 | Balance: $35,506 |
| Weekly Update: 11/6/2025: Construction complete. Buying fixtures with remaining funds. | ||
|
PC SMSR 2021-22 Upgrade Fire Alarm Detection System
|
||
| Design Start: Dec 2021 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $185,000 | Costs to Date: $176,886 | Balance: $8,114 |
| Weekly Update: 11/6/2025: Project in DSA closeout. | ||
|
PC SMSR 2022-23 Campus Signage Replacement and Update
|
||
| Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR Other |
| Budget/PPR: $956,089 | Costs to Date: $71,633 | Balance: $884,456 |
| Weekly Update: 11/6/2025: Building names have been approved by the Board of Trustees. Project is out to bid as of 10/14/25. Job Walk 10/28/25. Bid opening 11/12/25. | ||
|
PC SMSR 2022-23 Lighting Retrofit Tennis Courts & Locker Rooms
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $237,013 | Costs to Date: $237,778 | Balance: ($765) |
| Weekly Update: 11/6/2025: Phase I and II complete. District and Campus to meet to discuss update of budget. | ||