Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
CC Baseball Batter's Eye Replacement
|
||
Design Start: Nov 2024 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $206,182 | Costs to Date: $0 | Balance: $206,182 |
Weekly Update: 5/5/2025: DSA submission date pending upon completion of drawings. Geo-technical reports complete. |
CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $85,715 | Costs to Date: $65,479 | Balance: $20,236 |
Weekly Update: 5/5/2025: Closeout in progress. |
CC Physical Education Outdoor Complex Renovation
|
||
Design Start: May 2019 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $20,847,924 | Costs to Date: $20,226,663 | Balance: $621,261 |
Weekly Update: 5/5/2025: Construction 85% complete. Bleacher installation in progress. Softball press box installed, awaiting baseball press box. Certificate of Substantial Completion in progress. |
CC Physical Education Parking Renovation & New Entry Road with Turnabouts
|
||
Design Start: Sep 2021 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $2,678,681 | Costs to Date: $2,646,374 | Balance: $32,307 |
Weekly Update: 5/5/2025: Closeout in progress. |
CC Portable Classroom Relocation
|
||
Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
Budget/PPR: $258,000 | Costs to Date: $73,800 | Balance: $184,200 |
Weekly Update: 5/5/2025: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. |
CC SMSR 2021-2022 Door Repair Replacement Access Controls
|
||
Design Start: Nov 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $75,784 | Costs to Date: $0 | Balance: $75,784 |
Weekly Update: 5/5/2025: Proposal received. Contracts in progress. |
CC SMSR 2021-22 Main Building Elevator Renovation/Repairs
|
||
Design Start: Sep 2022 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $45,870 | Costs to Date: $41,620 | Balance: $4,250 |
Weekly Update: 5/5/2025: Lighting installation complete. Paint and graphics in progress. |
CC SMSR 2021-22 Signage Replacement
|
||
Design Start: Sep 2022 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $20,000 | Costs to Date: $16,577 | Balance: $3,423 |
Weekly Update: 5/5/2025: Campus Safety updating signage design revisions. |
CC SMSR 2022-23 MDF/IDF Electrical Backup Power Supply Replacement
|
||
Design Start: Dec 2022 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $101,432 | Costs to Date: $101,432 | Balance: $0 |
Weekly Update: 5/5/2025: Contract for transfer switch installation complete. Installation of equipment in progress. |
CC SMSR 2022-23 Mechanical Energy Pumping Systems Repair and Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $1,012,851 | Costs to Date: $1,009,039 | Balance: $3,812 |
Weekly Update: 5/5/2025: Closeout in progress. |
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $142,509 | Balance: $57,491 |
Weekly Update: 5/5/2025: Closeout in progress. |
CC Solar Canopy
|
||
Design Start: Oct 2023 | Project Status: In Design |
Funding Source: Local C.O. CC |
Budget/PPR: $65,500 | Costs to Date: $0 | Balance: $65,500 |
Weekly Update: 5/5/2025: Determination of exemption letter for charging stations received. Determination of rate status from power company of existing solar field and new solar canopy complete. Amendment to agreement approved. DSA submit date June 13, 2025. |
CC Student Housing Planning
|
||
Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $314,000 | Costs to Date: $192,308 | Balance: $121,692 |
Weekly Update: 5/5/2025: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Study for partnership complete. Exploring design options and other construction options. |
CC Tehachapi Campus Center
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. CC Meas. G |
Budget/PPR: $4,100,000 | Costs to Date: $599,144 | Balance: $3,500,856 |
Weekly Update: 5/5/2025: Site plan 98% complete. Classroom designs for new modulars complete. Working with city of Tehachapi for approval of site plan design. CEQA in progress. Contract complete for modular classrooms. DSA submission request in progress for June 4, 2025. |
CC Physical Education Outdoor Complex Renovation | |