Facilities and Construction Report
Date: September 16, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

CC Baseball Batter's Eye Replacement
Design Start: Nov 2024 Project Status: In Design Funding Source: Other
Budget/PPR: $206,182 Costs to Date: $0 Balance: $206,182
Weekly Update: 9/5/2025: Plans approved by DSA. Purchase of batter's eye in progress. Project to bid November 2025.


CC Electronic Door Access Controls and Hardware Upgrades
Design Start: May 2025 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $240,000 Costs to Date: $234,164 Balance: $5,836
Weekly Update: 9/5/2025: Hardware installation 99%. Programming and punch list in progress. Project completion September 19, 2025.


CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $85,715 Costs to Date: $65,479 Balance: $20,236
Weekly Update: 9/5/2025: Closeout in progress.



Projects Summaries

CC Physical Education Outdoor Complex Renovation
Design Start: May 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $20,847,924 Costs to Date: $20,526,869 Balance: $321,055
Weekly Update: 9/5/2025: Construction 100% complete. NOC in progress. Closeout in progress.


CC Portable Classroom Relocation
Design Start: Jun 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $258,000 Costs to Date: $73,800 Balance: $184,200
Weekly Update: 9/5/2025: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions.


CC SMSR 2021-2022 MDF Back Up Battery Replacement
Design Start: Jul 2025 Project Status: In Design Funding Source: SMSR
Budget/PPR: $7,701 Costs to Date: $0 Balance: $7,701
Weekly Update: 9/5/2025: PPR Approved. Contract in progress.



Projects Summaries

CC SMSR 2022-23 Mechanical Energy Pumping Systems Repair and Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,012,351 Costs to Date: $1,009,039 Balance: $3,312
Weekly Update: 9/5/2025: Closeout in progress.


CC SMSR 2022-23 Water Conservation/Xeriscaping
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $142,509 Balance: $57,491
Weekly Update: 9/5/2025: Closeout in progress.


CC Solar Canopy
Design Start: Oct 2023 Project Status: In Design Funding Source: Local C.O. CC
Budget/PPR: $120,000 Costs to Date: $0 Balance: $120,000
Weekly Update: 9/5/2025: Determination of rate status from power company of existing solar field and new solar canopy complete. Plans submitted to DSA June 13, 2025. Updated fire hydrant flow test complete. Estoppel signed and returned. Awaiting return of plans from DSA.



Projects Summaries

CC Student Housing Planning
Design Start: Dec 2022 Project Status: In Design Funding Source: Other
Budget/PPR: $314,000 Costs to Date: $208,308 Balance: $105,692
Weekly Update: 9/5/2025: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options.


CC Tehachapi Campus Center
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. CC
Meas. G
Budget/PPR: $4,100,000 Costs to Date: $2,998,128 Balance: $1,101,872
Weekly Update: 9/5/2025: Working with city of Tehachapi for approval of site plan design. DSA submission July 2, 2025. First comments from DSA received. Architect making corrections for resubmission. CEQA in progress.



Projects Pictures
CC Physical Education Outdoor Complex Renovation