Facilities and Construction Report
Date: June 27, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu
Ginger Popplewell Department Assistant III 661-336-5093 ginger.popplewell@kccd.edu

Projects Summaries

CC Baseball Batter's Eye Replacement
Design Start: Nov 2024 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $578,182 Costs to Date: $376,256 Balance: $201,926
Weekly Update: 6/4/2026: Batters eye and fence installation 100% complete. Punch walk to be scheduled.


CC Bishop Roofing Mechanical Utilities Exterior Security Upgrades
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $250,000 Costs to Date: $13,025 Balance: $236,975
Weekly Update: 6/4/2026: PPR approved. Project to be awarded June 11, 2026.


CC Bishop Water Purification & Emergency Utilities Upgrades
Design Start: Jan 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $2,499,999 Costs to Date: $288,400 Balance: $2,211,599
Weekly Update: 6/4/2026: Preliminary plans and scope complete. On site meeting for survey complete. Scheduling meeting with engineering team onsite.



Projects Summaries

CC Mammoth Parking Mechanical Exterior Utilities & Security Upgrades
Design Start: Mar 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $750,000 Costs to Date: $18,363 Balance: $731,637
Weekly Update: 6/4/2026: Inspection and assessment of fire suppression system complete. Proposal for repairs to system received. Cost and scope for repairs to system will require DSA submission. Scope development in progress.


CC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Local C.O. CC
Budget/PPR: $110,599 Costs to Date: $105,599 Balance: $5,000
Weekly Update: 6/4/2026: Programing and graphics in progress. Scheduling travel to site for inspection of completed work.


CC Mechanical MCC/ Transformer PSPS Generator Utilities System Exterior Repair & Replacement
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $4,500,000 Costs to Date: $19,482 Balance: $4,480,518
Weekly Update: 6/4/2026: Program approved. Solar building HVAC parts ordered and received. Meeting with vendor for job walk and proposal M&O Electrical upgrades complete, awaiting proposal. Work authorization complete for fire alarm upgrades. Work authorization for HVAC and electrical upgrades complete.



Projects Summaries

CC Physical Education Outdoor Complex Renovation
Design Start: May 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $20,847,924 Costs to Date: $20,478,553 Balance: $369,371
Weekly Update: 6/2/2026: Closeout in progress.


CC Physical Education Outdoor Complex Renovation Phase II
Design Start: Oct 2025 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $562,497 Costs to Date: $459,212 Balance: $103,285
Weekly Update: 6/4/2026: Turf installation complete. Erosion control and overflow parking area grading complete. Electrical upgrades in progress for bleachers, site lighting in progress.


CC Portable Classroom Relocation
Design Start: Jun 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $258,000 Costs to Date: $73,800 Balance: $184,200
Weekly Update: 6/4/2026: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions.



Projects Summaries

CC SMSR 2022-23 Water Conservation/Xeriscaping
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $176,775 Balance: $23,225
Weekly Update: 6/4/2026: Remaining landscape materials to be purchased September 2026.


CC Solar Canopy
Design Start: Oct 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $120,000 Costs to Date: $109,008 Balance: $10,992
Weekly Update: 6/4/2026: Final plans and specs from local utility provider complete. Confirming with local utility provider no other requirements by customer needed. Construction started April 27, 2026. Installation of columns complete. CCD denied, vendor removed coating from columns. Solar panel installation in progress.


CC Student Housing Planning
Design Start: Dec 2022 Project Status: In Design Funding Source: Other
Budget/PPR: $314,000 Costs to Date: $209,108 Balance: $104,892
Weekly Update: 6/4/2026: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options.



Projects Summaries

CC Tehachapi Campus Center
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. CC
Meas. G
Budget/PPR: $12,400,000 Costs to Date: $9,062,540 Balance: $3,337,460
Weekly Update: 6/4/2026: Re-zone of property approved. Construction of portable classrooms in progress. Project start April 27, 2026. Schedule of Values and project schedule approved. Sewer study in progress.