| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
|
CC Baseball Batter's Eye Replacement
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $578,182 | Costs to Date: $324,750 | Balance: $253,432 |
| Weekly Update: 3/13/2026: Batters eye installation 90% complete. Fence slat color approved. Fencing installation to be scheduled for May 2026. | ||
|
CC Bishop Roofing Mechanical Utilities Exterior Security Upgrades
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $250,000 | Costs to Date: $0 | Balance: $250,000 |
| Weekly Update: 3/13/2026: PPR approved. | ||
|
CC Bishop Water Purification & Emergency Utilities Upgrades
|
||
| Design Start: Jan 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $2,499,999 | Costs to Date: $0 | Balance: $2,499,999 |
| Weekly Update: 3/13/2026: Program approved. Selection of engineering firm complete. Work Authorization approved. | ||
|
CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR Local C.O. CC |
| Budget/PPR: $110,599 | Costs to Date: $65,479 | Balance: $45,120 |
| Weekly Update: 3/13/2026: Scheduling remaining work to take place during spring recess 2026. | ||
|
CC Mammoth Parking Mechanical Exterior Utilities & Security Upgrades
|
||
| Design Start: Mar 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $750,000 | Costs to Date: $0 | Balance: $750,000 |
| Weekly Update: 3/13/2026: PPR approved. | ||
|
CC Mechanical MCC/ Transformer PSPS Generator Utilities System Exterior Repair & Replacement
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $4,500,000 | Costs to Date: $0 | Balance: $4,500,000 |
| Weekly Update: 3/13/2026: Program approved. Solar building HVAC parts ordered. | ||
|
CC Physical Education Outdoor Complex Renovation
|
||
| Design Start: May 2019 | Project Status: Close-out |
Funding Source: Meas. J |
| Budget/PPR: $20,847,924 | Costs to Date: $20,478,553 | Balance: $369,371 |
| Weekly Update: 3/13/2026: Closeout in progress. | ||
|
CC Physical Education Outdoor Complex Renovation Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $562,497 | Costs to Date: $329,669 | Balance: $232,828 |
| Weekly Update: 3/13/2026: Turf installation complete. Erosion control and overflow parking area grading complete. | ||
|
CC Portable Classroom Relocation
|
||
| Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $258,000 | Costs to Date: $73,800 | Balance: $184,200 |
| Weekly Update: 3/13/2026: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. | ||
|
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $176,775 | Balance: $23,225 |
| Weekly Update: 3/13/2026: Remaining landscape materials to be purchased April 2026. | ||
|
CC Solar Canopy
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $120,000 | Costs to Date: $109,008 | Balance: $10,992 |
| Weekly Update: 3/13/2026: Awaiting final plans and specs from local utility provider to complete transformer upgrade. Construction to start April 2026. | ||
|
CC Student Housing Planning
|
||
| Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $314,000 | Costs to Date: $209,108 | Balance: $104,892 |
| Weekly Update: 3/13/2026: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options. | ||
|
CC Tehachapi Campus Center
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. CC Meas. G |
| Budget/PPR: $4,100,000 | Costs to Date: $3,168,723 | Balance: $931,277 |
| Weekly Update: 3/13/2026: Re-zone of property approved. Construction of portable classrooms in progress. Project currently out to bid. Bid opening March 25, 2026. | ||