

| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
| Ginger Popplewell | Department Assistant III | 661-336-5093 | ginger.popplewell@kccd.edu |
|
CC Baseball Batter's Eye Replacement
|
||
| Design Start: Nov 2024 | Project Status: Close-out |
Funding Source: Local C.O. CC |
| Budget/PPR: $578,182 | Costs to Date: $377,557 | Balance: $200,625 |
| Weekly Update: 10/30/2026: Construction 100% complete. NOC complete and DSA certification complete. Closeout in progress. | ||
|
CC Bishop Roofing Mechanical Utilities Exterior Security Upgrades
|
||
| Design Start: Feb 2026 | Project Status: In Const |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $400,000 | Costs to Date: $328,975 | Balance: $71,025 |
| Weekly Update: 10/30/2026: Project awarded. Installation of chiller in progress. | ||
|
CC Bishop Water Purification & Emergency Utilities Upgrades
|
||
| Design Start: Jan 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $2,499,999 | Costs to Date: $325,800 | Balance: $2,174,199 |
| Weekly Update: 10/30/2026: Engineering team conducted onsite review of systems. Construction documents 60%. Reverse Osmosis system procurement in progress. | ||
|
CC Mammoth Parking Mechanical Exterior Utilities & Security Upgrades
|
||
| Design Start: Mar 2026 | Project Status: In Const |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $750,000 | Costs to Date: $551,825 | Balance: $198,175 |
| Weekly Update: 10/30/2026: Inspection and assessment of fire suppression system complete. Cost and scope for repairs to system will require DSA submission. Scope development on hold. Schedule for boiler replacement and controls received from vendor. Project started on 9/28/2026 and in progress. Completion scheduled for 11/19/2026. | ||
|
CC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
| Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR Local C.O. CC |
| Budget/PPR: $110,599 | Costs to Date: $110,227 | Balance: $372 |
| Weekly Update: 10/30/2026: Programing and graphics complete. NOC in progress. Closeout in progress. | ||
|
CC Mechanical MCC/ Transformer PSPS Generator Utilities System Exterior Repair & Replacement
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $4,350,000 | Costs to Date: $275,143 | Balance: $4,074,857 |
| Weekly Update: 10/30/2026: Solar building HVAC parts ordered and received. M&O Electrical upgrades complete. Work authorization complete for fire alarm upgrades. Work authorization for HVAC and electrical upgrades complete. Site walk to verify electrical and control areas and drawings complete. Fire alarm drawing review complete. Awaiting construction document review and construction estimate. | ||
|
CC Physical Education Outdoor Complex Renovation Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $562,497 | Costs to Date: $499,601 | Balance: $62,896 |
| Weekly Update: 10/30/2026: Turf installation complete. Erosion control and overflow parking area grading complete. Electrical upgrades complete for bleachers and site lighting. Scoreboard in production. Delays due to parts availability, scheduling delivery, and installation with installer. Revised PPR complete. | ||
|
CC Portable Classroom Relocation
|
||
| Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $100,000 | Costs to Date: $73,800 | Balance: $26,200 |
| Weekly Update: 10/30/2026: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. | ||
|
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
| Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $200,000 | Balance: $0 |
| Weekly Update: 10/30/2026: Purchase of remaining landscape materials contract complete. Closeout in progress. | ||
|
CC Solar Canopy
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $120,000 | Costs to Date: $109,008 | Balance: $10,992 |
| Weekly Update: 10/30/2026: Construction 75% complete. Confirming with local utility provider no other requirements by customer needed. Construction started April 27, 2026. Installation of columns complete. Solar panel and canopy complete. Electrical wiring and inverter installation in progress. Utilities installation 70%. | ||
|
CC Student Housing Planning
|
||
| Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $314,000 | Costs to Date: $209,108 | Balance: $104,892 |
| Weekly Update: 10/30/2026: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options. | ||
|
CC Tehachapi Campus Center
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. CC Meas. G |
| Budget/PPR: $12,400,000 | Costs to Date: $9,551,912 | Balance: $2,848,088 |
| Weekly Update: 10/30/2026: Project Schedule of Values approved. Sewer study complete. Development fee approved and payment complete. Masonry wall redesigned to meet city code with architect. Construction schedule approved. Earthwork in progress. | ||
|
CC Test Training Project
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $4,300,000 | Costs to Date: $0 | Balance: $4,300,000 |
| Weekly Update: | ||