Facilities and Construction Report
Date: July 01, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

CC Baseball Batter's Eye Replacement
Design Start: Nov 2024 Project Status: In Design Funding Source: Other
Budget/PPR: $206,182 Costs to Date: $0 Balance: $206,182
Weekly Update: 6/27/2025: DSA submission date awaiting completion of drawings. Geo-technical reports complete.


CC Electronic Door Access Controls and Hardware Upgrades
Design Start: May 2025 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $240,000 Costs to Date: $0 Balance: $240,000
Weekly Update: 6/27/2025: Pre-construction meeting complete. Vendor ordering materials. Project start date TBD.


CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $85,715 Costs to Date: $65,479 Balance: $20,236
Weekly Update: 6/27/2025: Closeout in progress.



Projects Summaries

CC Physical Education Outdoor Complex Renovation
Design Start: May 2019 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $20,847,924 Costs to Date: $20,537,971 Balance: $309,953
Weekly Update: 6/27/2025: Construction 96% complete. Bleacher installation in progress. Softball and Baseball press box installation complete. Certificate of Substantial Completion in progress. Final electrical connections and landscaping in progress.


CC Physical Education Parking Renovation & New Entry Road with Turnabouts
Design Start: Sep 2021 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $2,678,681 Costs to Date: $2,643,412 Balance: $35,269
Weekly Update: 6/27/2025: Closeout in progress.


CC Portable Classroom Relocation
Design Start: Jun 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $258,000 Costs to Date: $73,800 Balance: $184,200
Weekly Update: 6/27/2025: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions.



Projects Summaries

CC SMSR 2021-2022 Door Repair Replacement Access Controls
Design Start: Nov 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $75,784 Costs to Date: $71,506 Balance: $4,278
Weekly Update: 6/27/2025: Closeout PPR progress.


CC SMSR 2021-22 Signage Replacement
Design Start: Sep 2022 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $20,000 Costs to Date: $16,577 Balance: $3,423
Weekly Update: 6/27/2025: Closeout PPR in progress.


CC SMSR 2022-23 MDF/IDF Electrical Backup Power Supply Replacement
Design Start: Dec 2022 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $101,932 Costs to Date: $101,932 Balance: $0
Weekly Update: 6/27/2025: Closeout in progress.



Projects Summaries

CC SMSR 2022-23 Mechanical Energy Pumping Systems Repair and Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,012,351 Costs to Date: $1,009,039 Balance: $3,312
Weekly Update: 6/27/2025: Closeout in progress.


CC SMSR 2022-23 Water Conservation/Xeriscaping
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $142,509 Balance: $57,491
Weekly Update: 6/27/2025: Closeout in progress.


CC Solar Canopy
Design Start: Oct 2023 Project Status: In Design Funding Source: Local C.O. CC
Budget/PPR: $65,500 Costs to Date: $0 Balance: $65,500
Weekly Update: 6/27/2025: Determination of rate status from power company of existing solar field and new solar canopy complete. Amendment to agreement approved. Submitted to DSA June 13, 2025.



Projects Summaries

CC Student Housing Planning
Design Start: Dec 2022 Project Status: In Design Funding Source: Other
Budget/PPR: $314,000 Costs to Date: $192,308 Balance: $121,692
Weekly Update: 6/27/2025: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options.


CC Tehachapi Campus Center
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. CC
Meas. G
Budget/PPR: $4,100,000 Costs to Date: $2,995,944 Balance: $1,104,056
Weekly Update: 6/27/2025: Site plan 100% complete. Classroom designs for new modulars complete. Working with city of Tehachapi for approval of site plan design. CEQA in progress. DSA submission July 2, 2025. Final review of drawings to be scheduled.



Projects Pictures
CC Physical Education Outdoor Complex Renovation