

| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
| Ginger Popplewell | Department Assistant III | 661-336-5093 | ginger.popplewell@kccd.edu |
|
CC Baseball Batter's Eye Replacement
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $578,182 | Costs to Date: $376,256 | Balance: $201,926 |
| Weekly Update: 6/4/2026: Batters eye and fence installation 100% complete. Punch walk to be scheduled. | ||
|
CC Bishop Roofing Mechanical Utilities Exterior Security Upgrades
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $250,000 | Costs to Date: $13,025 | Balance: $236,975 |
| Weekly Update: 6/4/2026: PPR approved. Project to be awarded June 11, 2026. | ||
|
CC Bishop Water Purification & Emergency Utilities Upgrades
|
||
| Design Start: Jan 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $2,499,999 | Costs to Date: $288,400 | Balance: $2,211,599 |
| Weekly Update: 6/4/2026: Preliminary plans and scope complete. On site meeting for survey complete. Scheduling meeting with engineering team onsite. | ||
|
CC Mammoth Parking Mechanical Exterior Utilities & Security Upgrades
|
||
| Design Start: Mar 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $750,000 | Costs to Date: $18,363 | Balance: $731,637 |
| Weekly Update: 6/4/2026: Inspection and assessment of fire suppression system complete. Proposal for repairs to system received. Cost and scope for repairs to system will require DSA submission. Scope development in progress. | ||
|
CC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR Local C.O. CC |
| Budget/PPR: $110,599 | Costs to Date: $105,599 | Balance: $5,000 |
| Weekly Update: 6/4/2026: Programing and graphics in progress. Scheduling travel to site for inspection of completed work. | ||
|
CC Mechanical MCC/ Transformer PSPS Generator Utilities System Exterior Repair & Replacement
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. CC Local C.O. DO |
| Budget/PPR: $4,500,000 | Costs to Date: $19,482 | Balance: $4,480,518 |
| Weekly Update: 6/4/2026: Program approved. Solar building HVAC parts ordered and received. Meeting with vendor for job walk and proposal M&O Electrical upgrades complete, awaiting proposal. Work authorization complete for fire alarm upgrades. Work authorization for HVAC and electrical upgrades complete. | ||
|
CC Physical Education Outdoor Complex Renovation
|
||
| Design Start: May 2019 | Project Status: Close-out |
Funding Source: Meas. J |
| Budget/PPR: $20,847,924 | Costs to Date: $20,478,553 | Balance: $369,371 |
| Weekly Update: 6/2/2026: Closeout in progress. | ||
|
CC Physical Education Outdoor Complex Renovation Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $562,497 | Costs to Date: $459,212 | Balance: $103,285 |
| Weekly Update: 6/4/2026: Turf installation complete. Erosion control and overflow parking area grading complete. Electrical upgrades in progress for bleachers, site lighting in progress. | ||
|
CC Portable Classroom Relocation
|
||
| Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $258,000 | Costs to Date: $73,800 | Balance: $184,200 |
| Weekly Update: 6/4/2026: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. | ||
|
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $176,775 | Balance: $23,225 |
| Weekly Update: 6/4/2026: Remaining landscape materials to be purchased September 2026. | ||
|
CC Solar Canopy
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
| Budget/PPR: $120,000 | Costs to Date: $109,008 | Balance: $10,992 |
| Weekly Update: 6/4/2026: Final plans and specs from local utility provider complete. Confirming with local utility provider no other requirements by customer needed. Construction started April 27, 2026. Installation of columns complete. CCD denied, vendor removed coating from columns. Solar panel installation in progress. | ||
|
CC Student Housing Planning
|
||
| Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $314,000 | Costs to Date: $209,108 | Balance: $104,892 |
| Weekly Update: 6/4/2026: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options. | ||
|
CC Tehachapi Campus Center
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. CC Meas. G |
| Budget/PPR: $12,400,000 | Costs to Date: $9,062,540 | Balance: $3,337,460 |
| Weekly Update: 6/4/2026: Re-zone of property approved. Construction of portable classrooms in progress. Project start April 27, 2026. Schedule of Values and project schedule approved. Sewer study in progress. | ||