Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
CC Baseball Batter's Eye Replacement
|
||
Design Start: Nov 2024 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $206,182 | Costs to Date: $0 | Balance: $206,182 |
Weekly Update: 9/5/2025: Plans approved by DSA. Purchase of batter's eye in progress. Project to bid November 2025. |
CC Electronic Door Access Controls and Hardware Upgrades
|
||
Design Start: May 2025 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $240,000 | Costs to Date: $234,164 | Balance: $5,836 |
Weekly Update: 9/5/2025: Hardware installation 99%. Programming and punch list in progress. Project completion September 19, 2025. |
CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $85,715 | Costs to Date: $65,479 | Balance: $20,236 |
Weekly Update: 9/5/2025: Closeout in progress. |
CC Physical Education Outdoor Complex Renovation
|
||
Design Start: May 2019 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $20,847,924 | Costs to Date: $20,526,869 | Balance: $321,055 |
Weekly Update: 9/5/2025: Construction 100% complete. NOC in progress. Closeout in progress. |
CC Portable Classroom Relocation
|
||
Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
Budget/PPR: $258,000 | Costs to Date: $73,800 | Balance: $184,200 |
Weekly Update: 9/5/2025: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. |
CC SMSR 2021-2022 MDF Back Up Battery Replacement
|
||
Design Start: Jul 2025 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $7,701 | Costs to Date: $0 | Balance: $7,701 |
Weekly Update: 9/5/2025: PPR Approved. Contract in progress. |
CC SMSR 2022-23 Mechanical Energy Pumping Systems Repair and Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $1,012,351 | Costs to Date: $1,009,039 | Balance: $3,312 |
Weekly Update: 9/5/2025: Closeout in progress. |
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $142,509 | Balance: $57,491 |
Weekly Update: 9/5/2025: Closeout in progress. |
CC Solar Canopy
|
||
Design Start: Oct 2023 | Project Status: In Design |
Funding Source: Local C.O. CC |
Budget/PPR: $120,000 | Costs to Date: $0 | Balance: $120,000 |
Weekly Update: 9/5/2025: Determination of rate status from power company of existing solar field and new solar canopy complete. Plans submitted to DSA June 13, 2025. Updated fire hydrant flow test complete. Estoppel signed and returned. Awaiting return of plans from DSA. |
CC Student Housing Planning
|
||
Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $314,000 | Costs to Date: $208,308 | Balance: $105,692 |
Weekly Update: 9/5/2025: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options. |
CC Tehachapi Campus Center
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. CC Meas. G |
Budget/PPR: $4,100,000 | Costs to Date: $2,998,128 | Balance: $1,101,872 |
Weekly Update: 9/5/2025: Working with city of Tehachapi for approval of site plan design. DSA submission July 2, 2025. First comments from DSA received. Architect making corrections for resubmission. CEQA in progress. |
CC Physical Education Outdoor Complex Renovation | |