Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
CC Baseball Batter's Eye Replacement
|
||
Design Start: Nov 2024 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $206,182 | Costs to Date: $0 | Balance: $206,182 |
Weekly Update: 3/7/2025 Kickoff meeting with Architect complete. Requesting DSA submission date. |
CC ESCC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $85,715 | Costs to Date: $65,479 | Balance: $20,236 |
Weekly Update: 3/71/2025 Closeout in progress. |
CC Physical Education Outdoor Complex Renovation
|
||
Design Start: May 2019 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $20,847,924 | Costs to Date: $20,226,663 | Balance: $621,261 |
Weekly Update: 3/7/2025 Construction 85% complete. Bleacher installation in progress. Certificate of Substantial Completion in progress. |
CC Physical Education Parking Renovation & New Entry Road with Turnabouts
|
||
Design Start: Sep 2021 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $2,678,681 | Costs to Date: $2,658,681 | Balance: $20,000 |
Weekly Update: 3/7/2025 Punch list items and closeout in progress. |
CC Portable Classroom Relocation
|
||
Design Start: Jun 2023 | Project Status: In Const |
Funding Source: Local C.O. CC |
Budget/PPR: $258,000 | Costs to Date: $73,800 | Balance: $184,200 |
Weekly Update: 3/7/2025 Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions. |
CC SMSR 2021-2022 Door Repair Replacement Access Controls
|
||
Design Start: Nov 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $75,784 | Costs to Date: $0 | Balance: $75,784 |
Weekly Update: 3/7/2025 PPR approved. Awaiting quote from vendor. |
CC SMSR 2021-22 Main Building Elevator Renovation/Repairs
|
||
Design Start: Sep 2022 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $45,870 | Costs to Date: $41,620 | Balance: $4,250 |
Weekly Update: 3/7/2025 Scheduling of lighting installation in progress. |
CC SMSR 2021-22 Security System Repairs/Upgrades
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $25,000 | Costs to Date: $24,999 | Balance: $1 |
Weekly Update: 3/7/2025 Construction 100% complete. New readers, and hardware installation complete. Programing complete. Closeout in progress. |
CC SMSR 2021-22 Signage Replacement
|
||
Design Start: Sep 2022 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $20,000 | Costs to Date: $16,577 | Balance: $3,423 |
Weekly Update: 3/7/2025 Campus Safety updating signage design revisions. Revised PPR complete |
CC SMSR 2022-23 MDF/IDF Electrical Backup Power Supply Replacement
|
||
Design Start: Dec 2022 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $101,432 | Costs to Date: $68,920 | Balance: $32,512 |
Weekly Update: 3/7/2025 Startup complete. Proposal for transfer switch installation recieved. Revised PPR in progress. |
CC SMSR 2022-23 Mechanical Energy Pumping Systems Repair and Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $1,012,851 | Costs to Date: $1,009,039 | Balance: $3,812 |
Weekly Update: 3/7/2025 Upgrades to controls, and HVAC complete. Closeout in progress. |
CC SMSR 2022-23 Water Conservation/Xeriscaping
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $142,509 | Balance: $57,491 |
Weekly Update: 3/7/2025 Construction 100% complete. Closeout in progress. |
CC Solar Canopy
|
||
Design Start: Oct 2023 | Project Status: In Design |
Funding Source: Local C.O. CC |
Budget/PPR: $65,500 | Costs to Date: $0 | Balance: $65,500 |
Weekly Update: 3/7/2025 Determination of exemption letter for charging stations received. Awaiting determination of rate status from power company of existing solar field and new solar canopy. |
CC Student Housing Planning
|
||
Design Start: Dec 2022 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $314,000 | Costs to Date: $184,308 | Balance: $129,692 |
Weekly Update: 3/7/2025 Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Study for partnership complete. Scheduled meeting with vendor for debrief of results. |
CC Tehachapi Campus Center
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. CC |
Budget/PPR: $3,100,000 | Costs to Date: $604,194 | Balance: $2,495,806 |
Weekly Update: 3/7/2025 Site plan 90%. Classroom designs for new modulars complete. Working with city of Tehachapi for approval of site plan design. CEQA in progress. |
CC Physical Education Outdoor Complex Renovation | |