Facilities and Construction Report
Date: November 05, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu
Ginger Popplewell Department Assistant III 661-336-5093 ginger.popplewell@kccd.edu

Projects Summaries

CC Baseball Batter's Eye Replacement
Design Start: Nov 2024 Project Status: Close-out Funding Source: Local C.O. CC
Budget/PPR: $578,182 Costs to Date: $377,557 Balance: $200,625
Weekly Update: 10/30/2026: Construction 100% complete. NOC complete and DSA certification complete. Closeout in progress.


CC Bishop Roofing Mechanical Utilities Exterior Security Upgrades
Design Start: Feb 2026 Project Status: In Const Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $400,000 Costs to Date: $328,975 Balance: $71,025
Weekly Update: 10/30/2026: Project awarded. Installation of chiller in progress.


CC Bishop Water Purification & Emergency Utilities Upgrades
Design Start: Jan 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $2,499,999 Costs to Date: $325,800 Balance: $2,174,199
Weekly Update: 10/30/2026: Engineering team conducted onsite review of systems. Construction documents 60%. Reverse Osmosis system procurement in progress.



Projects Summaries

CC Mammoth Parking Mechanical Exterior Utilities & Security Upgrades
Design Start: Mar 2026 Project Status: In Const Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $750,000 Costs to Date: $551,825 Balance: $198,175
Weekly Update: 10/30/2026: Inspection and assessment of fire suppression system complete. Cost and scope for repairs to system will require DSA submission. Scope development on hold. Schedule for boiler replacement and controls received from vendor. Project started on 9/28/2026 and in progress. Completion scheduled for 11/19/2026.


CC Mammoth SMSR 2022-23 Mechanical and Energy Systems Repair and Replacement Phase 1
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Local C.O. CC
Budget/PPR: $110,599 Costs to Date: $110,227 Balance: $372
Weekly Update: 10/30/2026: Programing and graphics complete. NOC in progress. Closeout in progress.


CC Mechanical MCC/ Transformer PSPS Generator Utilities System Exterior Repair & Replacement
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. CC
Local C.O. DO
Budget/PPR: $4,350,000 Costs to Date: $275,143 Balance: $4,074,857
Weekly Update: 10/30/2026: Solar building HVAC parts ordered and received. M&O Electrical upgrades complete. Work authorization complete for fire alarm upgrades. Work authorization for HVAC and electrical upgrades complete. Site walk to verify electrical and control areas and drawings complete. Fire alarm drawing review complete. Awaiting construction document review and construction estimate.



Projects Summaries

CC Physical Education Outdoor Complex Renovation Phase II
Design Start: Oct 2025 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $562,497 Costs to Date: $499,601 Balance: $62,896
Weekly Update: 10/30/2026: Turf installation complete. Erosion control and overflow parking area grading complete. Electrical upgrades complete for bleachers and site lighting. Scoreboard in production. Delays due to parts availability, scheduling delivery, and installation with installer. Revised PPR complete.


CC Portable Classroom Relocation
Design Start: Jun 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $100,000 Costs to Date: $73,800 Balance: $26,200
Weekly Update: 10/30/2026: Corrections Facility is working on site plans for final location of classrooms. Once approved through their team, classrooms will be moved to final positions.


CC SMSR 2022-23 Water Conservation/Xeriscaping
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $200,000 Balance: $0
Weekly Update: 10/30/2026: Purchase of remaining landscape materials contract complete. Closeout in progress.



Projects Summaries

CC Solar Canopy
Design Start: Oct 2023 Project Status: In Const Funding Source: Local C.O. CC
Budget/PPR: $120,000 Costs to Date: $109,008 Balance: $10,992
Weekly Update: 10/30/2026: Construction 75% complete. Confirming with local utility provider no other requirements by customer needed. Construction started April 27, 2026. Installation of columns complete. Solar panel and canopy complete. Electrical wiring and inverter installation in progress. Utilities installation 70%.


CC Student Housing Planning
Design Start: Dec 2022 Project Status: In Design Funding Source: Other
Budget/PPR: $314,000 Costs to Date: $209,108 Balance: $104,892
Weekly Update: 10/30/2026: Plans for alternate types of housing forthcoming. Confirmation study on number of beds complete. Exploring design and construction options.


CC Tehachapi Campus Center
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. CC
Meas. G
Budget/PPR: $12,400,000 Costs to Date: $9,551,912 Balance: $2,848,088
Weekly Update: 10/30/2026: Project Schedule of Values approved. Sewer study complete. Development fee approved and payment complete. Masonry wall redesigned to meet city code with architect. Construction schedule approved. Earthwork in progress.



Projects Summaries

CC Test Training Project
Design Start: Oct 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $4,300,000 Costs to Date: $0 Balance: $4,300,000
Weekly Update: