Facilities and Construction Report
Date: May 08, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,636,825 Balance: $1,850,367
Weekly Update: 4/24/2025: Construction 42% complete. Shade structure, and greenhouse are turned over for use. Structural Steel, plumbing and electrical is ongoing. Tentative completion May 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 4/24/2025: Audit complete and closeout in progress.


BC Arvin Educational Center
Design Start: Jun 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $29,686,863 Balance: $131,475
Weekly Update: 4/24/2025: Waiting on signage, wrought iron fencing, and monument sign. Working on closeout documents and DSA closeout.



Projects Summaries

BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 4/24/2025: BC 99% complete. Battery backup equipment installation in progress. Anticipated completion May 2025. Interconnection scheduled for May 2025.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $103,474 Balance: $696,526
Weekly Update: 5/2/2025: Drawings approved by DSA. Project bidding May 22, 2025. Project start June 16, 2025. Project Complete August 2025.


BC Campus Wide Security Camera
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,298,000 Costs to Date: $187,906 Balance: $1,110,094
Weekly Update: 4/24/2025: Award of contract going to Board for approval May 2025.



Projects Summaries

BC Center for Student Success Planning
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $36,000,000 Costs to Date: $92,606 Balance: $35,907,394
Weekly Update: 5/2/2025: Architect work authorization in progress.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update:


BC Combined Gym & Fieldhouse (Modular Swing Space)
Design Start: Oct 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $150,000 Costs to Date: $73,644 Balance: $76,356
Weekly Update: 4/24/2025: DSA closeout approval pending due to solar project.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,000,000 Costs to Date: $2,246,976 Balance: $3,753,024
Weekly Update: 5/2/2025: DSA approval for demolition of north and south buildings complete. Awaiting approval for equipment building.


BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $64,741,297 Balance: $2,958,703
Weekly Update: 4/24/2025: Pending DSA closeout.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $1,876,081 Balance: $1,123,919
Weekly Update: 5/2/2025: Construction 60% complete. Sidewalk on eastern side complete. Possibly doing a deductive change order for the remaining work while we await for SCE to relocate a power pole.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $120,250 Balance: $879,750
Weekly Update: 5/2/2025: Revised scope of work approved. In-Design phase.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $600,000 Costs to Date: $70,000 Balance: $530,000
Weekly Update: 5/2/2025: Design in progress. Work to take place winter of 2025.


BC Industrial Tech Electrical Lab Remodel
Design Start: Oct 2023 Project Status: Close-out Funding Source: Other
Budget/PPR: $1,200,000 Costs to Date: $0 Balance: $1,200,000
Weekly Update: 4/24/2025: Closeout in progress



Projects Summaries

BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $7,705,270 Balance: $7,294,730
Weekly Update: 4/24/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $600,000 Costs to Date: $52,097 Balance: $547,903
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 4/24/2025: Contract in progress.



Projects Summaries

BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $2,316,261 Balance: $295,739
Weekly Update: 4/24/2025: Closeout in progress.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $750,000 Costs to Date: $24,200 Balance: $725,800
Weekly Update: 4/24/2025: Campus to review final design. RFP for bidding forthcoming.


BC Science and Engineering Phase II
Design Start: Jan 2024 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $2,150,000 Costs to Date: $2,123,000 Balance: $27,000
Weekly Update: 4/24/2025: Phase 3 to be done during summer break 2025.



Projects Summaries

BC Security Gates
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $150,000 Costs to Date: $22,500 Balance: $127,500
Weekly Update: 4/4/2025: Working with campus for final design and approvals.


BC SMSR 2021-22 Interior Lighting Retrofit
Design Start: Jan 2022 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $709,216 Costs to Date: $709,216 Balance: $0
Weekly Update: 5/2/2025: Construction complete. Closeout in progress.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $350,000 Costs to Date: $46,189 Balance: $303,811
Weekly Update: 5/2/2025: Award of contract going to Board for approval June 2025.



Projects Summaries

BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $400,000 Costs to Date: $55,987 Balance: $344,013
Weekly Update: 5/2/2025: Award of contract going to Board for approval June 2025.


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 5/2/2025: Final bid scope established by campus. Preparing Bid Documents.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $135,063 Balance: $1,014,937
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025.



Projects Summaries

BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,500,000 Costs to Date: $397,429 Balance: $1,102,571
Weekly Update: 5/2/2025: Additional server work added to the project. Work to begin in May 2025.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $2,658,882 Costs to Date: $501,663 Balance: $2,157,219
Weekly Update: 5/2/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium will be painted in summer of 2025. Bidding complete. Work to start May 19, 2025.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 4/24/2025: Awaiting DSA plan approval.



Projects Summaries

BC SMSR 2022-23 Pool Deck Replacement
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $100,000 Costs to Date: $0 Balance: $100,000
Weekly Update: 5/5/2025: Project being closed and funds moved to SMSR 2022-23 Wall and Floorcovering Replacement Library.


BC SMSR 2022-23 Recoat Deck Industrial Tech
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $100,000 Costs to Date: $26,435 Balance: $73,565
Weekly Update: 4/24/2025: Work complete. Remaining funds to be reallocated.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Mar 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,250,000 Costs to Date: $119,187 Balance: $1,130,813
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025.



Projects Summaries

BC SMSR 2022-23 Roof Replacement Industrial Tech
Design Start: Nov 2023 Project Status: Close-out Funding Source: SMSR
Other
Budget/PPR: $1,800,000 Costs to Date: $1,782,298 Balance: $17,702
Weekly Update: 4/24/2025: Constuction complete. Remaining funds to be reallocated.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $600,000 Costs to Date: $96,172 Balance: $503,828
Weekly Update: 5/5/2025: Project advertising to bid. Bid opening 5-14-25.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 5/2/2025: Design in progress. Meeting scheduled with BC staff on 5/14/25 for approval.



Projects Summaries

BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $55,473,729 Balance: $7,971,271
Weekly Update: 4/24/2025: Construction 24% complete. Contractor is waiting for DSA approval on updated drawings. Site utilities, structural concrete and preparing for framing in progress. Anticipated completion May 2026.


BC Swing Space (Measure J)
Design Start: May 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,250,000 Costs to Date: $5,221,425 Balance: $28,575
Weekly Update: 4/24/2025: Project on hold pending funding of Measure 2.


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: Close-out Funding Source: Meas. J
Other
Budget/PPR: $292,358 Costs to Date: $157,045 Balance: $135,313
Weekly Update: 5/2/2025: Contract awarded to Sierra Schools for additional work being completed in the fireside room.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse