Facilities and Construction Report
Date: December 23, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,894,789 Balance: $1,592,403
Weekly Update: 12/23/2025: Construction 65% complete. Framing, plumbing, HVAC, sheetrock, roofing, exterior finishes and electrical in progress. Anticipated completion Mid-June 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 12/23/2025: Closeout in progress.


BC Arvin 4th and Walnut Grant Project
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $5,355,748 Costs to Date: $325,000 Balance: $5,030,748
Weekly Update: 12/5/2025: Contract in progress.



Projects Summaries

BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 12/23/2025: BC 99% complete. Awaiting redesign from PG&E. Construction is approx. 6-8 months out from completion.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $782,763 Balance: $17,237
Weekly Update: 12/5/2025: Construction 75% complete. ADA path of travel and roof in progress.


BC Campus Wide ADA Projects
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $294,000 Costs to Date: $0 Balance: $294,000
Weekly Update: 12/15/2025: Meeting has been scheduled with the campus for 1/21/2026 to review and scope the project prior to moving forward.



Projects Summaries

BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,441,152 Balance: $56,848
Weekly Update: 12/23/2025: Construction 95% complete. (5) cameras pending at the solar canopy. Working with FOREFRONT Power to provide power for the cameras. Anticipated completion January 2026.


BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $1,274,210 Balance: $26,718,790
Weekly Update: 12/5/2025: Basic requirement overview complete and briefed to BC staff. Design and budget meeting to be scheduled. Working on program requirements for square footage of building. Final presentation 12/9/2025.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 12/23/2025: Initial planning to start January or February 2026.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,670,499 Balance: $8,329,501
Weekly Update: 12/5/2025: Last meeting held on 11/25/2025. Small changes to floor plan and approval meeting to be scheduled.


BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,150,000 Costs to Date: $813,965 Balance: $5,336,035
Weekly Update: 12/5/2025: Award of contract going to the December 2025 Board for approval.


BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $63,935,108 Balance: $3,764,892
Weekly Update: 12/23/2025: DSA Certified. Closeout PPR in progress.



Projects Summaries

BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $0 Balance: $361,000
Weekly Update: 12/16/2025: Meeting scheduled for 1/15/2026 to discuss the details of the project.


BC Culinary Arts Lab Renovation
Design Start: Jan 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,000,000 Costs to Date: $0 Balance: $4,000,000
Weekly Update: 12/5/2025: In preliminary design phase. Collecting architect qualifications for review.


BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $25,500 Balance: $474,500
Weekly Update: 12/5/2025: Project in the preliminary design phase.



Projects Summaries

BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $1,385,945 Balance: $2,514,055
Weekly Update: 12/5/2025: Phase I construction 66% complete. Phase II award of contract going to the December 2025 Board for approval.


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $275,987 Balance: $724,013
Weekly Update: 12/5/2025: Plans in DSA for review and approval.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,109,175 Balance: $577,280
Weekly Update: 12/5/2025: Construction to start tentatively December 15, 2025.



Projects Summaries

BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,470,017 Balance: $6,529,983
Weekly Update: 12/23/2025: High voltage design in progress. PG&E has approved design. Switchgear drawings in progress.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $667,337 Balance: $157,663
Weekly Update: 12/5/2025: Construction 95% complete. Punch list and change order work in progress.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $42,179 Balance: $757,821
Weekly Update: 12/5/2025: Construction 100% complete for initial contract. Additional repairs to inverters complete and start up conducted. Inverter has internal damage and requires further repairs. Awaiting costs from vendor.



Projects Summaries

BC Mass Communication
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 12/5/2025: Construction to start tentatively December 19, 2025.


BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $120,000 Costs to Date: $0 Balance: $120,000
Weekly Update: 12/15/2025: PPR approved as of 9/11/2025. Meeting with Gonled to go over scope of work and pricing.


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $28,522 Balance: $231,478
Weekly Update: 12/5/2025: Project was rescoped to have bollards as a priority. Project in design phase.



Projects Summaries

BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 12/5/2025: Construction to start tentatively December 2025.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 12/5/2025: Construction 10% complete.


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $197,376 Balance: $2,624
Weekly Update: 12/5/2025: Construction anticipated to start on December 15, 2025.



Projects Summaries

BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $615,332 Balance: $534,668
Weekly Update: 12/5/2025: Construction to start on December 15, 2025.


BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $397,429 Balance: $1
Weekly Update: 12/5/2025: Construction is 90% complete. Additional server work added to the project.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,144,575 Balance: $358,705
Weekly Update: 12/5/2025: Closeout in progress.



Projects Summaries

BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 12/5/2025: Awaiting DSA plan approval.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $631,111 Balance: $1,110,156
Weekly Update: 12/5/2025: Phase II bidding to begin in February 2026. Construction to start May 2026.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,066,047 Balance: $599,554
Weekly Update: 12/5/2025: Phase I complete. Phase II first floor design in progress. Project to bid March 2026 for completion in May 2026.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 12/5/2025: Design in progress. Project has been rescoped.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $58,637,698 Balance: $4,807,302
Weekly Update: 12/23/2025: Construction 60% complete. Framing, roofing, electrical, HVAC and plumbing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion October 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,472,100 Balance: $77,900
Weekly Update: 12/16/2025: Funds to cover final invoicing.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 12/5/2025: Modular used for the restroom and showers in design. Floor plan approved by campus.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse