Facilities and Construction Report
Date: September 17, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,637,444 Balance: $1,849,748
Weekly Update: 8/22/2025: Construction 47% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion August 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 8/22/2025: Closeout in progress.


BC Arvin 4th and Walnut Grant Project
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $5,355,748 Costs to Date: $0 Balance: $5,355,748
Weekly Update: 9/5/2025: Design Build Contract sent to vendor for signature.



Projects Summaries

BC Arvin Educational Center
Design Start: Jun 2020 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $29,718,743 Balance: $99,595
Weekly Update: 8/22/2025: Waiting on signage, and monument sign. Closeout documents and DSA closeout in progress.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 8/22/2025: BC 99% complete. PG&E has determined that the design is inadequate and will need to be redesigned. Update on design and construction is 6-8 months out.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $676,753 Balance: $123,247
Weekly Update: 9/5/2025: Construction 25% complete. Existing dugouts removed. Earthwork in progress. First and third base dugout compaction complete. Concrete foundation complete. Vertical construction to start September 8, 2025. Project completion September 2025.



Projects Summaries

BC Campus Wide ADA Projects
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $294,000 Costs to Date: $0 Balance: $294,000
Weekly Update:


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,441,152 Balance: $56,848
Weekly Update: 9/5/2025: Construction 75% complete. Pending 5 cameras at the solar canopy. Anticipated completion December 2025.


BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. PC
Budget/PPR: $27,993,000 Costs to Date: $1,274,000 Balance: $26,719,000
Weekly Update: 9/5/2025: PPR Approved. Architect selection complete. Initial design planning interviews completed. Next interview session September 17, 2025.



Projects Summaries

BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 9/5/2025: Project approved. Initial planning to start January 2026.


BC Combined Gym & Fieldhouse (Modular Swing Space)
Design Start: Oct 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $150,000 Costs to Date: $73,644 Balance: $76,356
Weekly Update: 9/5/2025: Closeout in progress.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,670,499 Balance: $8,329,501
Weekly Update: 9/5/2025: Revised PPR in progress to start final designs and approval for working drawings and DSA submission.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,000,000 Costs to Date: $720,477 Balance: $5,279,523
Weekly Update: 9/5/2025: Project is out to bid. Job-Walk scheduled 9-18-25.


BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $63,948,238 Balance: $3,751,762
Weekly Update: 8/22/2025: DSA closeout in progress.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $0 Balance: $361,000
Weekly Update:



Projects Summaries

BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $0 Balance: $500,000
Weekly Update: 9/5/2025:Project is in the preliminary plan phase.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $2,529,117 Balance: $470,883
Weekly Update: 9/5/2025: Phase 1 construction 66% complete. Closeout on phase I in progress. Phase II approved by DSA. Bidding documents forthcoming.


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $275,237 Balance: $724,763
Weekly Update: 9/5/2025: Plans in DSA for review and approval.



Projects Summaries

BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $71,004 Balance: $1,615,451
Weekly Update: 9/5/2025: Award of contract going to the Board for approval September 11, 2025.


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $7,833,652 Balance: $7,166,348
Weekly Update: 8/22/2025: Water scope on hold. Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study complete. High Voltage is high priority due to power outages. PG&E approved Engineer design.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $667,337 Balance: $157,663
Weekly Update: 9/5/2025: Construction 95% complete. Work in progress.



Projects Summaries

BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 9/5/2025: Construction 60% complete. Phase I to be completed September 2025.


BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $2,318,439 Balance: $293,561
Weekly Update: 8/22/2025: Closeout in progress.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 9/5/2025: Contract awarded. Submittals are in progress and review.



Projects Summaries

BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $120,000 Costs to Date: $0 Balance: $120,000
Weekly Update:


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $28,522 Balance: $231,478
Weekly Update: 9/5/2025: Project is out to bid. Job walk is scheduled on 9-5-25. Bid opening 9-18-25.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 9/5/2025:Submittals are in progress and review. Construction to start tentatively October 2025.



Projects Summaries

BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 9/5/2025:Submittals are in progress and review. Construction to start tentatively October 2025.


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 9/5/2025: Bid documents have been drafted. BC staff to review.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $425,172 Balance: $724,828
Weekly Update: 9/5/2025: Establishing new project area for remaining funds.



Projects Summaries

BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $397,429 Balance: $1
Weekly Update: 9/5/2025: Additional server work added to the project. Construction is 50% complete.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,938,882 Costs to Date: $1,147,775 Balance: $791,107
Weekly Update: 9/5/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch walk complete. Rework in progress.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 9/5/2025: Awaiting DSA plan approval.



Projects Summaries

BC SMSR 2022-23 Phase II Window Replacement
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $216,115 Costs to Date: $200,000 Balance: $16,115
Weekly Update: 3/21/2024: Closeout in process.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $631,111 Balance: $1,110,156
Weekly Update: 9/5/2025: Phase 1 Construction 100% complete. Phase II in DSA.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,230,000 Costs to Date: $1,004,902 Balance: $225,098
Weekly Update: 9/5/2025: Flooring complete. Punch items complete. NOC in progress.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 9/5/2025: Design in progress. BC staff to review value engineering proposal.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $58,105,856 Balance: $5,339,144
Weekly Update: 8/22/2025: Construction 45% complete. Site utilities, structural concrete, framing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,475,430 Balance: $74,570
Weekly Update: 8/22/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 9/5/2025: Purchase of modular used for the field house complete. Remaining modular used for the restroom and showers in design.


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: Close-out Funding Source: Meas. J
Other
Budget/PPR: $292,358 Costs to Date: $234,888 Balance: $57,470
Weekly Update: 9/5/2025: Construction completed. Preparing project close out.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse