
| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
| Ginger Popplewell | Department Assistant III | 661-336-5093 | ginger.popplewell@kccd.edu |
|
BC Agriculture Building
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $61,987,192 | Costs to Date: $60,761,928 | Balance: $1,225,264 |
| Weekly Update: 6/17/2026: Construction 87% complete. Working on interior and exterior finishes. Furniture has been ordered. Anticipated completion August 2026. | ||
|
BC Bakersfield College and Delano Center Solar
|
||
| Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
| Weekly Update: 6/17/2026: BC 99% complete. Awaiting redesign from PG&E. Updated completion date is Oct 2026. | ||
|
BC Baseball Dugout Replacement
|
||
| Design Start: Sep 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $800,000 | Costs to Date: $799,312 | Balance: $688 |
| Weekly Update: 6/4/2026: Closeout in progress. | ||
|
BC Campus Wide ADA Projects
|
||
| Design Start: Mar 2026 | Project Status: In Design |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $794,000 | Costs to Date: $0 | Balance: $794,000 |
| Weekly Update: 6/15/2026: Architect working on project plans to submit to DSA. | ||
|
BC Campus Wide Security Cameras
|
||
| Design Start: Sep 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,498,000 | Costs to Date: $1,453,814 | Balance: $44,186 |
| Weekly Update: 6/17/2026: Notice of Completion filed. Retention payment in progress for closeout. | ||
|
BC Campuswide Elevator Upgrades & Rehabilitation
|
||
| Design Start: Jun 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $6,250,000 | Costs to Date: $0 | Balance: $6,250,000 |
| Weekly Update: | ||
|
BC Center For Student Success
|
||
| Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. BC |
| Budget/PPR: $27,993,000 | Costs to Date: $1,442,878 | Balance: $26,550,122 |
| Weekly Update: 6/4/2026: Design and budget meeting complete. Final layout approved. Moving into construction documents. Project approved by State Chancellor Office. Meeting with architect to finalize mechanical and electrical systems complete. Final design for furniture and office space in progress. 3D design and color review complete. DSA submission August 2026. | ||
|
BC Center for Student Success Swing Space
|
||
| Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $2,000,000 | Costs to Date: $27,617 | Balance: $1,972,383 |
| Weekly Update: 6/4/2026: Planning in progress for counseling to move into library over summer of 2026. Furniture and office space floorplan complete. Communication and electrical in progress. Furniture and office spaces to be installed July 2026. | ||
|
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $10,000,000 | Costs to Date: $1,733,999 | Balance: $8,266,001 |
| Weekly Update: 6/4/2026: Final concept and floor plan approved. Construction documents in progress. Meeting for security complete in progress. Landscape design meeting June 8, 2026. | ||
|
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $6,150,000 | Costs to Date: $5,763,320 | Balance: $386,681 |
| Weekly Update: 6/17/2026: Construction 35% complete. Backfilling in progress. | ||
|
BC Combined Gym and Fieldhouse Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $361,000 | Costs to Date: $18,000 | Balance: $343,000 |
| Weekly Update: 6/15/2026: Architect working on project drawings to submit to DSA. | ||
|
BC Culinary Arts Lab Renovation
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $4,500,000 | Costs to Date: $440,100 | Balance: $4,059,900 |
| Weekly Update: 6/17/2026: Project is in preliminary design phase. Floor plan design completed. Awaiting stakeholder approval. | ||
|
BC DC Randolph Center Maintenance Repairs
|
||
| Design Start: Apr 2026 | Project Status: In Design |
Funding Source: Local C.O. DO |
| Budget/PPR: $600,000 | Costs to Date: $487,203 | Balance: $112,798 |
| Weekly Update: 6/17/2026: Construction has begun. Electrical work in progress. | ||
|
BC Delano Center Agrivoltaics Farm
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $500,000 | Costs to Date: $66,961 | Balance: $433,039 |
| Weekly Update: 6/17/2026: Project in design phase. DSA appointment is scheduled for July 1st. | ||
|
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $3,900,000 | Costs to Date: $3,706,984 | Balance: $193,016 |
| Weekly Update: 6/17/2026: Phase II construction 80% complete. Roadwork and flatwork is complete. Striping forthcoming. | ||
|
BC Delano Center Welding Lab Expansion
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,000,000 | Costs to Date: $482,376 | Balance: $517,624 |
| Weekly Update: 6/17/2026: Contractor to begin mobilizing on 6/17/2026. | ||
|
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,686,455 | Costs to Date: $1,110,175 | Balance: $576,280 |
| Weekly Update: 6/17/2026: Construction 95% complete. Testing scheduled in the upcoming weeks. Punchwalk with engineer completed. | ||
|
BC Fine Arts Replacement
|
||
| Design Start: Oct 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $13,618,000 | Costs to Date: $0 | Balance: $13,618,000 |
| Weekly Update: 6/17/2026: Project in preliminary design phase. Meetings to select in architect forthcoming. | ||
|
BC Infrastructure
|
||
| Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $15,000,000 | Costs to Date: $8,470,462 | Balance: $6,529,538 |
| Weekly Update: 6/8/2026: PG&E has approved design and switchgear. Switchgear is to be shipped in October 2026. Working with Electrical Engineer to put together bid documents. | ||
|
BC Infrastructure Campus Wide Rekeying
|
||
| Design Start: Sep 2024 | Project Status: Close-out |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $825,000 | Costs to Date: $709,057 | Balance: $115,943 |
| Weekly Update: 6/17/2026: Received all closeout documents. NOC has been filed. | ||
|
BC Infrastructure Solar Inverter Repairs
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $800,000 | Costs to Date: $42,179 | Balance: $757,821 |
| Weekly Update: 6/4/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards arrived unprogrammed and work not completed. Boards were returned and awaiting shipment from vendor for installation. | ||
|
BC Mass Communication
|
||
| Design Start: Aug 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $550,000 | Costs to Date: $195,498 | Balance: $354,502 |
| Weekly Update: 6/17/2026: Construction complete. Electrical Engineer drafting specs for additional scope of work. Additional scope of work consists of adding speakers above the library and stadium and adding two interrupters for the PA system at baseball and football stadium. | ||
|
BC Math Science Allied Health- Room 14 Remodel
|
||
| Design Start: May 2026 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $450,000 | Costs to Date: $47,250 | Balance: $402,750 |
| Weekly Update: 6/17/2026: Project in preliminary design phase. Preliminary plans are 80% complete. | ||
|
BC Safety Lighting Phase II
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $350,000 | Costs to Date: $316,730 | Balance: $33,270 |
| Weekly Update: 6/15/2026: Construction 50% complete. | ||
|
BC Security Gates and Bollards
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $300,000 | Costs to Date: $283,811 | Balance: $16,189 |
| Weekly Update: 6/17/2026: Contract awarded. Contractor to begin mobilizing 6-15-2026. | ||
|
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $460,000 | Costs to Date: $415,207 | Balance: $44,793 |
| Weekly Update: 6/17/2026: Construction 95% complete. Air balance complete, contractor to complete corrections. Punch walk tentatively scheduled with the mechanical engineer first week of July. | ||
|
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $480,000 | Costs to Date: $440,851 | Balance: $39,149 |
| Weekly Update: 6/17/2026: Construction 95% complete. Air balance complete, contractor to complete corrections. Punch walk tentatively scheduled with the mechanical engineer first week of July. | ||
|
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
| Design Start: Jan 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $190,796 | Balance: $9,204 |
| Weekly Update: 6/17/2026: Closeout in progress. | ||
|
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,150,000 | Costs to Date: $841,787 | Balance: $308,213 |
| Weekly Update: 6/17/2026: Construction 25% complete. | ||
|
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
| Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,503,280 | Costs to Date: $1,228,575 | Balance: $274,705 |
| Weekly Update: 6/4/2026: Child Development Center and Maintenance Operations buildings to be painted summer of 2026. Bidding complete and project awarded. Pre-construction meeting June 8, 2026. | ||
|
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
| Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
| Budget/PPR: $1,000,000 | Costs to Date: $145,450 | Balance: $854,550 |
| Weekly Update: 6/17/2026:Contract awarded. Preconstruction meeting forthcoming. | ||
|
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
| Design Start: Feb 2025 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
| Budget/PPR: $1,741,267 | Costs to Date: $1,330,071 | Balance: $411,196 |
| Weekly Update: 6/17/2026: Construction 15% completed. Demolition of east wing completed. MEP to be installed. | ||
|
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,665,601 | Costs to Date: $1,403,481 | Balance: $262,120 |
| Weekly Update: 6/4/2026: Preconstruction meeting complete. Submittals under review. Project schedule in progress. | ||
|
BC Soccer Field
|
||
| Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $12,000,000 | Costs to Date: $682,000 | Balance: $11,318,000 |
| Weekly Update: 6/17/2026: Design in progress. Meeting to be scheduled with campus to review working drawings and updated cost estimate. | ||
|
BC Student Housing
|
||
| Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
| Budget/PPR: $63,445,000 | Costs to Date: $58,338,243 | Balance: $5,106,757 |
| Weekly Update: 6/17/2026: Construction 82% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion October 2026. | ||
|
BC Swing Space (Measure J)
|
||
| Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $5,550,000 | Costs to Date: $5,384,201 | Balance: $165,799 |
| Weekly Update: 6/22/2026: Payment on remaining lease balance in progress. | ||
|
BC Swing Space Modular Purchase
|
||
| Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,200,000 | Costs to Date: $993,872 | Balance: $206,128 |
| Weekly Update: 6/17/2026: Campus has decided to closeout this project and not continue. Legal notice sent, awaiting vendor response. | ||