| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
| Ginger Popplewell | Department Assistant III | 661-336-5093 | ginger.popplewell@kccd.edu |
|
BC Agriculture Building
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $61,987,192 | Costs to Date: $61,115,985 | Balance: $871,207 |
| Weekly Update: 10/16/2026: Construction 96% complete. Working on interior and exterior finishes. Furniture and technology will be installed November 2026. Anticipated completion December 2026. | ||
|
BC Bakersfield College and Delano Center Solar
|
||
| Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
| Weekly Update: 10/16/2026: BC 99% complete. Labor to install switchgear to go out to bid October 2026. Board approval November 2026. Updated completion date to utilize 100% of solar is December 2026. | ||
|
BC Baseball Dugout Replacement
|
||
| Design Start: Sep 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $800,119 | Costs to Date: $800,119 | Balance: $0 |
| Weekly Update: 10/30/2026: All forms submitted to DSA and certification complete. Closeout in progress. | ||
|
BC BC Campus Wide HVAC Repair & Replacement
|
||
| Design Start: Aug 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $3,166,666 | Costs to Date: $428,011 | Balance: $2,738,655 |
| Weekly Update: 10/30/2026 PPR approved. | ||
|
BC Campus Wide ADA Projects
|
||
| Design Start: Mar 2026 | Project Status: In Design |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $794,000 | Costs to Date: $187,860 | Balance: $606,140 |
| Weekly Update: 10/30/2026: Architect working on project plans to submit to DSA. | ||
|
BC Campuswide Elevator Upgrades & Rehabilitation
|
||
| Design Start: Nov 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $6,250,000 | Costs to Date: $0 | Balance: $6,250,000 |
| Weekly Update: 10/16/2026: Architect work authorization scheduled for November Board approval. | ||
|
BC Center For Student Success
|
||
| Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. BC |
| Budget/PPR: $27,993,000 | Costs to Date: $3,152,603 | Balance: $24,840,397 |
| Weekly Update: 10/30/2026: Design and budget meeting complete. Final layout approved by college. Construction documents complete and resubmitted to DSA on October 13, 2026. Final design for furniture complete. 3D design and basic color review complete. Next milestone DSA approval May 2027. | ||
|
BC Center for Student Success Swing Space
|
||
| Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $2,000,000 | Costs to Date: $598,110 | Balance: $1,401,890 |
| Weekly Update: 10/30/2026: Library move complete. Remaining CSS staff move to Weill Institute 1/4/2027. Job walk scheduled for 11/5/2026. | ||
|
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $10,000,000 | Costs to Date: $1,977,500 | Balance: $8,022,500 |
| Weekly Update: 10/30/2026: Final concept and floor plan approved. Construction documents in progress. Final landscape plan and security/door access and controls meeting complete. Interior finishes, color review, and Audio-Video review complete. DSA submission 10/2/2026. New fire hydrant flow test in progress. Low water usage landscape plan approved. | ||
|
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $6,550,000 | Costs to Date: $6,226,560 | Balance: $323,440 |
| Weekly Update: 10/16/2026: Construction 45% complete. Contractor installing underground utilities and footings for foundation of the pool equipment building. | ||
|
BC Combined Gym and Fieldhouse Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $361,000 | Costs to Date: $21,887 | Balance: $339,113 |
| Weekly Update: 10/30/2026: Architect has submitted drawings to DSA. | ||
|
BC Culinary Arts Lab Renovation
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $4,500,000 | Costs to Date: $476,705 | Balance: $4,023,296 |
| Weekly Update: 10/16/2026: Drawings are in design phase. Estimate came in over budget. AOR to value engineer the project. | ||
|
BC DC Randolph Center Maintenance Repairs
|
||
| Design Start: Apr 2026 | Project Status: In Const |
Funding Source: Local C.O. DO |
| Budget/PPR: $600,000 | Costs to Date: $600,064 | Balance: ($64) |
| Weekly Update: 10/16/2026: Construction 97% complete. Awaiting additional funds to begin roof repairs. | ||
|
BC Delano Center Agrivoltaics Farm
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $500,000 | Costs to Date: $74,581 | Balance: $425,419 |
| Weekly Update: 10/16/2026: Plans resubmitted to DSA for backcheck comments. Awaiting DSA review. | ||
|
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $3,900,000 | Costs to Date: $3,703,684 | Balance: $196,316 |
| Weekly Update: 10/16/2026: Phase II construction 95% complete. Punch work and change order work in progress. | ||
|
BC Delano Center Welding Lab Expansion
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,000,000 | Costs to Date: $504,992 | Balance: $495,008 |
| Weekly Update: 10/16/2026: Construction 95% complete. Punchlist items work in progress. | ||
|
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
| Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $1,686,455 | Costs to Date: $1,166,823 | Balance: $519,632 |
| Weekly Update: 10/16/2026: NOC filed. Project in closeout phase. | ||
|
BC Emergency Management Indoor Speakers
|
||
| Design Start: Sep 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,070,000 | Costs to Date: $0 | Balance: $1,070,000 |
| Weekly Update: 10/16/2026: In design phase. | ||
|
BC Fine Arts Replacement
|
||
| Design Start: Oct 2026 | Project Status: In Design |
Funding Source: State C.O. BC Local C.O. BC |
| Budget/PPR: $14,546,000 | Costs to Date: $23,360 | Balance: $14,522,640 |
| Weekly Update: 10/16/2026: Architect selected, Work Authorization approved. Project in preliminary design phase. | ||
|
BC Infrastructure
|
||
| Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $9,000,000 | Costs to Date: $8,408,834 | Balance: $591,166 |
| Weekly Update: 10/16/2026: Switchgear received. Proposal going to the board for approval in Nov. 2026. Upgraded water service should be completed | ||
|
BC Infrastructure Solar Inverter Repairs
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $800,000 | Costs to Date: $79,671 | Balance: $720,329 |
| Weekly Update: 10/30/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards completed. Inverters shutdown due to over temperature. Additional work required. Proposal received for new power supplies, cable sensors, and filters. Additional proposals received. Remaining work to be completed. | ||
|
BC Mass Communication
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $550,000 | Costs to Date: $197,098 | Balance: $352,902 |
| Weekly Update: 10/16/2026: Project in bidding phase for additional scope of work. Bid opening scheduled on 10/29/2026. | ||
|
BC Math Science Allied Health- Room 14 Remodel
|
||
| Design Start: May 2026 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $450,000 | Costs to Date: $147,060 | Balance: $302,940 |
| Weekly Update: 10/16/2026: Contract on the November Board for approval. | ||
|
BC Safety Lighting Phase II
|
||
| Design Start: Sep 2025 | Project Status: Close-out |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $350,000 | Costs to Date: $316,730 | Balance: $33,270 |
| Weekly Update: 10/30/2026: Closeout in progress. | ||
|
BC Security Gates and Bollards
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $300,000 | Costs to Date: $297,411 | Balance: $2,589 |
| Weekly Update: 10/16/2026: Construction 95% complete. Punch list work in progress. | ||
|
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
| Design Start: Feb 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $415,207 | Costs to Date: $415,207 | Balance: $0 |
| Weekly Update: 10/16/2026: Construction 100% complete. NOC has been filed. Closeout in progress. | ||
|
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
| Design Start: Feb 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $440,852 | Costs to Date: $440,851 | Balance: $1 |
| Weekly Update: 10/16/2026: Construction 100% complete. NOC filed. Closeout in progress. | ||
|
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,150,000 | Costs to Date: $860,923 | Balance: $289,077 |
| Weekly Update: 10/16/2026: Construction 99% complete. Awaiting minor punch list items to be completed. | ||
|
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
| Design Start: Apr 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $1,503,280 | Costs to Date: $1,206,137 | Balance: $297,143 |
| Weekly Update: 10/30/2026: Child Development Center complete. Punch items complete. M&O building complete. Punch walk complete. NOC complete. Closeout in progress. | ||
|
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,000,000 | Costs to Date: $655,109 | Balance: $344,891 |
| Weekly Update: 10/16/2026: Construction 45% complete. MEP installation work in progress. | ||
|
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,434,413 | Costs to Date: $1,372,007 | Balance: $62,406 |
| Weekly Update: 10/16/2026: Construction 50% complete. Drywall work in progress in the eastern wing. Framing work in progress in the western wing. | ||
|
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,665,601 | Costs to Date: $1,476,204 | Balance: $189,397 |
| Weekly Update: 10/30/2026: Construction 100% complete. Project started June 29, 2026. Mold abatement complete. Wall repair, texture, and paint complete. Flooring complete. Punch walk complete. Final walk to be scheduled after punch items complete. Remaining crash rail and corner guards to be replaced end of November. | ||
|
BC Soccer Field
|
||
| Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $12,000,000 | Costs to Date: $784,401 | Balance: $11,215,600 |
| Weekly Update: 10/16/2026: Plans submitted to DSA. | ||
|
BC Softball Fieldhouse Title 9
|
||
| Design Start: Jan 2027 | Project Status: In Design |
Funding Source: Local C.O. BC Local C.O. DO |
| Budget/PPR: $3,450,000 | Costs to Date: $0 | Balance: $3,450,000 |
| Weekly Update: 10/16/2026 Design Build contract on December board for approval. | ||
|
BC Student Housing
|
||
| Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
| Budget/PPR: $63,445,000 | Costs to Date: $61,487,385 | Balance: $1,957,615 |
| Weekly Update: 10/1/2026: Construction 91% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion December 2026. | ||
|
BC Swing Space Modular Purchase
|
||
| Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,200,000 | Costs to Date: $1,199,919 | Balance: $81 |
| Weekly Update: 10/16/2026: Settlement has been reached. Coordinating with vendor for transfer of title. | ||