Facilities and Construction Report
Date: March 17, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,516,795 Balance: $1,970,397
Weekly Update: 3/7/2025: Construction 42% complete. Shade structure, and greenhouse are going to be turned over for use. Structural concrete, and structural steel in progress. Site utilities on main building in progress.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 3/7/2025: Requested project audit from campus.


BC Arvin Educational Center
Design Start: Jun 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $29,781,071 Balance: $37,267
Weekly Update: 3/7/2025 Waiting on signage, wrought iron fencing, and monument sign. Working on closeout document and DSA closeout



Projects Summaries

BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 3/7/2025 BC 99% complete. Battery backup equipment being installed. Anticipated completion April 2025. Interconnection scheduled for April 2025.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 3/7/2025 Drawings have been submitted to DSA for review.


BC Campus Wide Security Camera
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,298,000 Costs to Date: $187,906 Balance: $1,110,094
Weekly Update: 3/7/2025 Full campus design in progress. Vendors to walk site. Budget numbers forthcoming.



Projects Summaries

BC Center for Student Success Planning
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $36,000,000 Costs to Date: $92,606 Balance: $35,907,394
Weekly Update: 1/4/2022 The project has been temporarily suspended to allow for finalization of the Budget and Schedule adjustments. College is working to obtain matching funding with State Chancellors office.


BC Combined Gym & Fieldhouse (Modular Swing Space)
Design Start: Oct 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $150,000 Costs to Date: $73,644 Balance: $76,356
Weekly Update: 3/7/2025 DSA closeout approval pending due to solar project.


BC Combined Gym & Fieldhouse (Pool Equipment & Admin) Building
Design Start: Mar 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,475,000 Costs to Date: $2,246,976 Balance: $228,024
Weekly Update: 3/7/2025 Design (Pool Admin Bldg.) 85% complete. Final Admin building drawings under review with campus. Project on hold.



Projects Summaries

BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $65,590,569 Balance: $2,109,431
Weekly Update: 3/7/2025 Substantial completion dated February 2025. Pending Closeout and DSA Closeout


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $1,876,081 Balance: $1,123,919
Weekly Update: 2/21/2025- Construction of sidewalk in progress


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $120,250 Balance: $879,750
Weekly Update: 2/21/2025: Soils report and underground utility mapping in progress. Layout to be discussed with BC Staff.



Projects Summaries

BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $600,000 Costs to Date: $0 Balance: $600,000
Weekly Update: 2/7/2025: Scope of work approved. Work Authorization in progress.


BC Industrial Tech Electrical Lab Remodel
Design Start: Oct 2023 Project Status: Close-out Funding Source: Other
Budget/PPR: $1,200,000 Costs to Date: $0 Balance: $1,200,000
Weekly Update: 3/7/2025: Closeout in progress


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $7,705,270 Balance: $7,294,730
Weekly Update: 3/7/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages.



Projects Summaries

BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $600,000 Costs to Date: $51,110 Balance: $548,890
Weekly Update: 2/21/2025- Bid rejected. Scope of work will be revised. Pending campus approval


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 3/7/2025 Initial review in progress.


BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $1,903,431 Balance: $708,569
Weekly Update: 3/7/2025: Closeout in progress.



Projects Summaries

BC Mass Communication
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $750,000 Costs to Date: $24,200 Balance: $725,800
Weekly Update: 3/7/2025: Electrical engineer working with consultant on design. Vendor proposal in progress.


BC Science and Engineering Phase II
Design Start: Jan 2024 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $2,150,000 Costs to Date: $2,123,000 Balance: $27,000
Weekly Update: 3/7/2025 Phase 1 and Phase 2 are complete Phase 3 to be done during spring break


BC Security Gates
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $150,000 Costs to Date: $22,500 Balance: $127,500
Weekly Update: 3/7/2025: Working with campus for final design and approvals.



Projects Summaries

BC SMSR 2021-22 Interior Lighting Retrofit
Design Start: Jan 2022 Project Status: In Const Funding Source: SMSR
Budget/PPR: $709,216 Costs to Date: $709,216 Balance: $0
Weekly Update: 3/7/2025 Scheduling of work in progress. Anticipated completion spring break 2025.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $350,000 Costs to Date: $45,202 Balance: $304,798
Weekly Update: 2/21/2025 Design complete. Awaiting campus sign-off on plans and scope of work.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $400,000 Costs to Date: $55,000 Balance: $345,000
Weekly Update: 2/21/2025 Design complete. Awaiting campus sign-off on plans and scope of work.



Projects Summaries

BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 2/7/2025 Establishing final scope of work with the campus. Work to bid in Spring of 2025


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $135,063 Balance: $1,014,937
Weekly Update: 2/21/2025 Bid documents in progress.


BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,500,000 Costs to Date: $284,229 Balance: $1,215,771
Weekly Update: 2/21/2025 Construction 90% complete.



Projects Summaries

BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $2,658,882 Costs to Date: $500,658 Balance: $2,158,224
Weekly Update: 3/7/2025 Language Arts and Forums building exterior painting complete. Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium will be painted in summer of 2025. Awaiting drawings from architect.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 3/7/2025 Awaiting DSA plan approval.


BC SMSR 2022-23 Pool Deck Replacement
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $100,000 Costs to Date: $0 Balance: $100,000
Weekly Update: 3/7/2025 Finalizing scope of work on the pool Admin building design to determine the final scope of work for pool deck.



Projects Summaries

BC SMSR 2022-23 Recoat Deck Industrial Tech
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $100,000 Costs to Date: $26,435 Balance: $73,565
Weekly Update: 2/14/2025: Work complete. Remaining funds to be reallocated.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Mar 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,250,000 Costs to Date: $20,000 Balance: $1,230,000
Weekly Update: 2/21/2025 Design in progress.


BC SMSR 2022-23 Roof Replacement Industrial Tech
Design Start: Nov 2023 Project Status: Close-out Funding Source: SMSR
Other
Budget/PPR: $1,800,000 Costs to Date: $1,782,298 Balance: $17,702
Weekly Update: 3/7/2025: Closeout in progress.



Projects Summaries

BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $600,000 Costs to Date: $57,650 Balance: $542,350
Weekly Update: 3/7/2025: Phase 1 complete. Design of Phase II to begin. Working with Architect on final scope of work. Proposal from architect received.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 2/21/2025 Design in progress. Soils report and underground utility mapping in progress.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $55,463,864 Balance: $7,981,136
Weekly Update: 3/7/2025: Construction 21% complete. Contractor is waiting for DSA approval on updated drawings. Working on site utilities, structural concrete and preparing for framing. Anticipated completion May 2026.



Projects Summaries

BC Swing Space (Measure J)
Design Start: May 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,250,000 Costs to Date: $5,221,425 Balance: $28,575
Weekly Update: 3/7/2025: Project on hold. Pending funding of Measure 2.


BC Swing Space Ag
Design Start: Mar 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $1,050,000 Costs to Date: $1,037,146 Balance: $12,854
Weekly Update: 2/14/2025: Pending DSA Certification. Closeout PPR in progress


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: Close-out Funding Source: Meas. J
Other
Budget/PPR: $314,000 Costs to Date: $157,045 Balance: $156,955
Weekly Update: 3/7/2025 Closeout in progress.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse