Facilities and Construction Report
Date: November 05, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu
Ginger Popplewell Department Assistant III 661-336-5093 ginger.popplewell@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $61,987,192 Costs to Date: $61,115,985 Balance: $871,207
Weekly Update: 10/16/2026: Construction 96% complete. Working on interior and exterior finishes. Furniture and technology will be installed November 2026. Anticipated completion December 2026.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 10/16/2026: BC 99% complete. Labor to install switchgear to go out to bid October 2026. Board approval November 2026. Updated completion date to utilize 100% of solar is December 2026.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $800,119 Costs to Date: $800,119 Balance: $0
Weekly Update: 10/30/2026: All forms submitted to DSA and certification complete. Closeout in progress.



Projects Summaries

BC BC Campus Wide HVAC Repair & Replacement
Design Start: Aug 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $3,166,666 Costs to Date: $428,011 Balance: $2,738,655
Weekly Update: 10/30/2026 PPR approved.


BC Campus Wide ADA Projects
Design Start: Mar 2026 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $794,000 Costs to Date: $187,860 Balance: $606,140
Weekly Update: 10/30/2026: Architect working on project plans to submit to DSA.


BC Campuswide Elevator Upgrades & Rehabilitation
Design Start: Nov 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $6,250,000 Costs to Date: $0 Balance: $6,250,000
Weekly Update: 10/16/2026: Architect work authorization scheduled for November Board approval.



Projects Summaries

BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $3,152,603 Balance: $24,840,397
Weekly Update: 10/30/2026: Design and budget meeting complete. Final layout approved by college. Construction documents complete and resubmitted to DSA on October 13, 2026. Final design for furniture complete. 3D design and basic color review complete. Next milestone DSA approval May 2027.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $598,110 Balance: $1,401,890
Weekly Update: 10/30/2026: Library move complete. Remaining CSS staff move to Weill Institute 1/4/2027. Job walk scheduled for 11/5/2026.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,977,500 Balance: $8,022,500
Weekly Update: 10/30/2026: Final concept and floor plan approved. Construction documents in progress. Final landscape plan and security/door access and controls meeting complete. Interior finishes, color review, and Audio-Video review complete. DSA submission 10/2/2026. New fire hydrant flow test in progress. Low water usage landscape plan approved.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $6,550,000 Costs to Date: $6,226,560 Balance: $323,440
Weekly Update: 10/16/2026: Construction 45% complete. Contractor installing underground utilities and footings for foundation of the pool equipment building.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $21,887 Balance: $339,113
Weekly Update: 10/30/2026: Architect has submitted drawings to DSA.


BC Culinary Arts Lab Renovation
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,500,000 Costs to Date: $476,705 Balance: $4,023,296
Weekly Update: 10/16/2026: Drawings are in design phase. Estimate came in over budget. AOR to value engineer the project.



Projects Summaries

BC DC Randolph Center Maintenance Repairs
Design Start: Apr 2026 Project Status: In Const Funding Source: Local C.O. DO
Budget/PPR: $600,000 Costs to Date: $600,064 Balance: ($64)
Weekly Update: 10/16/2026: Construction 97% complete. Awaiting additional funds to begin roof repairs.


BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $74,581 Balance: $425,419
Weekly Update: 10/16/2026: Plans resubmitted to DSA for backcheck comments. Awaiting DSA review.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $3,703,684 Balance: $196,316
Weekly Update: 10/16/2026: Phase II construction 95% complete. Punch work and change order work in progress.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $504,992 Balance: $495,008
Weekly Update: 10/16/2026: Construction 95% complete. Punchlist items work in progress.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,166,823 Balance: $519,632
Weekly Update: 10/16/2026: NOC filed. Project in closeout phase.


BC Emergency Management Indoor Speakers
Design Start: Sep 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,070,000 Costs to Date: $0 Balance: $1,070,000
Weekly Update: 10/16/2026: In design phase.



Projects Summaries

BC Fine Arts Replacement
Design Start: Oct 2026 Project Status: In Design Funding Source: State C.O. BC
Local C.O. BC
Budget/PPR: $14,546,000 Costs to Date: $23,360 Balance: $14,522,640
Weekly Update: 10/16/2026: Architect selected, Work Authorization approved. Project in preliminary design phase.


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $9,000,000 Costs to Date: $8,408,834 Balance: $591,166
Weekly Update: 10/16/2026: Switchgear received. Proposal going to the board for approval in Nov. 2026. Upgraded water service should be completed


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $79,671 Balance: $720,329
Weekly Update: 10/30/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards completed. Inverters shutdown due to over temperature. Additional work required. Proposal received for new power supplies, cable sensors, and filters. Additional proposals received. Remaining work to be completed.



Projects Summaries

BC Mass Communication
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $197,098 Balance: $352,902
Weekly Update: 10/16/2026: Project in bidding phase for additional scope of work. Bid opening scheduled on 10/29/2026.


BC Math Science Allied Health- Room 14 Remodel
Design Start: May 2026 Project Status: In Const Funding Source: Other
Budget/PPR: $450,000 Costs to Date: $147,060 Balance: $302,940
Weekly Update: 10/16/2026: Contract on the November Board for approval.


BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: Close-out Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $350,000 Costs to Date: $316,730 Balance: $33,270
Weekly Update: 10/30/2026: Closeout in progress.



Projects Summaries

BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $300,000 Costs to Date: $297,411 Balance: $2,589
Weekly Update: 10/16/2026: Construction 95% complete. Punch list work in progress.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $415,207 Costs to Date: $415,207 Balance: $0
Weekly Update: 10/16/2026: Construction 100% complete. NOC has been filed. Closeout in progress.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $440,852 Costs to Date: $440,851 Balance: $1
Weekly Update: 10/16/2026: Construction 100% complete. NOC filed. Closeout in progress.



Projects Summaries

BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $860,923 Balance: $289,077
Weekly Update: 10/16/2026: Construction 99% complete. Awaiting minor punch list items to be completed.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,206,137 Balance: $297,143
Weekly Update: 10/30/2026: Child Development Center complete. Punch items complete. M&O building complete. Punch walk complete. NOC complete. Closeout in progress.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $655,109 Balance: $344,891
Weekly Update: 10/16/2026: Construction 45% complete. MEP installation work in progress.



Projects Summaries

BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,434,413 Costs to Date: $1,372,007 Balance: $62,406
Weekly Update: 10/16/2026: Construction 50% complete. Drywall work in progress in the eastern wing. Framing work in progress in the western wing.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,476,204 Balance: $189,397
Weekly Update: 10/30/2026: Construction 100% complete. Project started June 29, 2026. Mold abatement complete. Wall repair, texture, and paint complete. Flooring complete. Punch walk complete. Final walk to be scheduled after punch items complete. Remaining crash rail and corner guards to be replaced end of November.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $784,401 Balance: $11,215,600
Weekly Update: 10/16/2026: Plans submitted to DSA.



Projects Summaries

BC Softball Fieldhouse Title 9
Design Start: Jan 2027 Project Status: In Design Funding Source: Local C.O. BC
Local C.O. DO
Budget/PPR: $3,450,000 Costs to Date: $0 Balance: $3,450,000
Weekly Update: 10/16/2026 Design Build contract on December board for approval.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $61,487,385 Balance: $1,957,615
Weekly Update: 10/1/2026: Construction 91% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion December 2026.


BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $1,199,919 Balance: $81
Weekly Update: 10/16/2026: Settlement has been reached. Coordinating with vendor for transfer of title.