Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
BC Agriculture Building
|
||
Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $60,487,192 | Costs to Date: $58,516,795 | Balance: $1,970,397 |
Weekly Update: 3/7/2025: Construction 42% complete. Shade structure, and greenhouse are going to be turned over for use. Structural concrete, and structural steel in progress. Site utilities on main building in progress. |
BC Allied Health Math Science Remodel
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
Weekly Update: 3/7/2025: Requested project audit from campus. |
BC Arvin Educational Center
|
||
Design Start: Jun 2020 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $29,818,338 | Costs to Date: $29,781,071 | Balance: $37,267 |
Weekly Update: 3/7/2025 Waiting on signage, wrought iron fencing, and monument sign. Working on closeout document and DSA closeout |
BC Bakersfield College and Delano Center Solar
|
||
Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
Weekly Update: 3/7/2025 BC 99% complete. Battery backup equipment being installed. Anticipated completion April 2025. Interconnection scheduled for April 2025. |
BC Baseball Dugout Replacement
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 3/7/2025 Drawings have been submitted to DSA for review. |
BC Campus Wide Security Camera
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,298,000 | Costs to Date: $187,906 | Balance: $1,110,094 |
Weekly Update: 3/7/2025 Full campus design in progress. Vendors to walk site. Budget numbers forthcoming. |
BC Center for Student Success Planning
|
||
Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $36,000,000 | Costs to Date: $92,606 | Balance: $35,907,394 |
Weekly Update: 1/4/2022 The project has been temporarily suspended to allow for finalization of the Budget and Schedule adjustments. College is working to obtain matching funding with State Chancellors office. |
BC Combined Gym & Fieldhouse (Modular Swing Space)
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $150,000 | Costs to Date: $73,644 | Balance: $76,356 |
Weekly Update: 3/7/2025 DSA closeout approval pending due to solar project. |
BC Combined Gym & Fieldhouse (Pool Equipment & Admin) Building
|
||
Design Start: Mar 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,475,000 | Costs to Date: $2,246,976 | Balance: $228,024 |
Weekly Update: 3/7/2025 Design (Pool Admin Bldg.) 85% complete. Final Admin building drawings under review with campus. Project on hold. |
BC Combined Gym and Fieldhouse
|
||
Design Start: Jan 2019 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $67,700,000 | Costs to Date: $65,590,569 | Balance: $2,109,431 |
Weekly Update: 3/7/2025 Substantial completion dated February 2025. Pending Closeout and DSA Closeout |
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $3,000,000 | Costs to Date: $1,876,081 | Balance: $1,123,919 |
Weekly Update: 2/21/2025- Construction of sidewalk in progress |
BC Delano Center Welding Lab Expansion
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,000,000 | Costs to Date: $120,250 | Balance: $879,750 |
Weekly Update: 2/21/2025: Soils report and underground utility mapping in progress. Layout to be discussed with BC Staff. |
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $600,000 | Costs to Date: $0 | Balance: $600,000 |
Weekly Update: 2/7/2025: Scope of work approved. Work Authorization in progress. |
BC Industrial Tech Electrical Lab Remodel
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $1,200,000 | Costs to Date: $0 | Balance: $1,200,000 |
Weekly Update: 3/7/2025: Closeout in progress |
BC Infrastructure
|
||
Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $15,000,000 | Costs to Date: $7,705,270 | Balance: $7,294,730 |
Weekly Update: 3/7/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages. |
BC Infrastructure Campus Wide Rekeying
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $600,000 | Costs to Date: $51,110 | Balance: $548,890 |
Weekly Update: 2/21/2025- Bid rejected. Scope of work will be revised. Pending campus approval |
BC Infrastructure Solar Inverter Repairs
|
||
Design Start: Nov 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 3/7/2025 Initial review in progress. |
BC Lab Tech Bachelors Program
|
||
Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
Budget/PPR: $2,612,000 | Costs to Date: $1,903,431 | Balance: $708,569 |
Weekly Update: 3/7/2025: Closeout in progress. |
BC Mass Communication
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $750,000 | Costs to Date: $24,200 | Balance: $725,800 |
Weekly Update: 3/7/2025: Electrical engineer working with consultant on design. Vendor proposal in progress. |
BC Science and Engineering Phase II
|
||
Design Start: Jan 2024 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $2,150,000 | Costs to Date: $2,123,000 | Balance: $27,000 |
Weekly Update: 3/7/2025 Phase 1 and Phase 2 are complete Phase 3 to be done during spring break |
BC Security Gates
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $150,000 | Costs to Date: $22,500 | Balance: $127,500 |
Weekly Update: 3/7/2025: Working with campus for final design and approvals. |
BC SMSR 2021-22 Interior Lighting Retrofit
|
||
Design Start: Jan 2022 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $709,216 | Costs to Date: $709,216 | Balance: $0 |
Weekly Update: 3/7/2025 Scheduling of work in progress. Anticipated completion spring break 2025. |
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $350,000 | Costs to Date: $45,202 | Balance: $304,798 |
Weekly Update: 2/21/2025 Design complete. Awaiting campus sign-off on plans and scope of work. |
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $400,000 | Costs to Date: $55,000 | Balance: $345,000 |
Weekly Update: 2/21/2025 Design complete. Awaiting campus sign-off on plans and scope of work. |
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
Weekly Update: 2/7/2025 Establishing final scope of work with the campus. Work to bid in Spring of 2025 |
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,150,000 | Costs to Date: $135,063 | Balance: $1,014,937 |
Weekly Update: 2/21/2025 Bid documents in progress. |
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,500,000 | Costs to Date: $284,229 | Balance: $1,215,771 |
Weekly Update: 2/21/2025 Construction 90% complete. |
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $2,658,882 | Costs to Date: $500,658 | Balance: $2,158,224 |
Weekly Update: 3/7/2025 Language Arts and Forums building exterior painting complete. Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium will be painted in summer of 2025. Awaiting drawings from architect. |
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,000,000 | Costs to Date: $143,770 | Balance: $856,230 |
Weekly Update: 3/7/2025 Awaiting DSA plan approval. |
BC SMSR 2022-23 Pool Deck Replacement
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $100,000 | Costs to Date: $0 | Balance: $100,000 |
Weekly Update: 3/7/2025 Finalizing scope of work on the pool Admin building design to determine the final scope of work for pool deck. |
BC SMSR 2022-23 Recoat Deck Industrial Tech
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $100,000 | Costs to Date: $26,435 | Balance: $73,565 |
Weekly Update: 2/14/2025: Work complete. Remaining funds to be reallocated. |
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
Design Start: Mar 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,250,000 | Costs to Date: $20,000 | Balance: $1,230,000 |
Weekly Update: 2/21/2025 Design in progress. |
BC SMSR 2022-23 Roof Replacement Industrial Tech
|
||
Design Start: Nov 2023 | Project Status: Close-out |
Funding Source: SMSR Other |
Budget/PPR: $1,800,000 | Costs to Date: $1,782,298 | Balance: $17,702 |
Weekly Update: 3/7/2025: Closeout in progress. |
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $600,000 | Costs to Date: $57,650 | Balance: $542,350 |
Weekly Update: 3/7/2025: Phase 1 complete. Design of Phase II to begin. Working with Architect on final scope of work. Proposal from architect received. |
BC Soccer Field
|
||
Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
Weekly Update: 2/21/2025 Design in progress. Soils report and underground utility mapping in progress. |
BC Student Housing
|
||
Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
Budget/PPR: $63,445,000 | Costs to Date: $55,463,864 | Balance: $7,981,136 |
Weekly Update: 3/7/2025: Construction 21% complete. Contractor is waiting for DSA approval on updated drawings. Working on site utilities, structural concrete and preparing for framing. Anticipated completion May 2026. |
BC Swing Space (Measure J)
|
||
Design Start: May 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $5,250,000 | Costs to Date: $5,221,425 | Balance: $28,575 |
Weekly Update: 3/7/2025: Project on hold. Pending funding of Measure 2. |
BC Swing Space Ag
|
||
Design Start: Mar 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $1,050,000 | Costs to Date: $1,037,146 | Balance: $12,854 |
Weekly Update: 2/14/2025: Pending DSA Certification. Closeout PPR in progress |
BC Welcome Center Interior & Exterior Improvements
|
||
Design Start: Sep 2023 | Project Status: Close-out |
Funding Source: Meas. J Other |
Budget/PPR: $314,000 | Costs to Date: $157,045 | Balance: $156,955 |
Weekly Update: 3/7/2025 Closeout in progress. |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | |