Facilities and Construction Report
Date: June 27, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu
Ginger Popplewell Department Assistant III 661-336-5093 ginger.popplewell@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $61,987,192 Costs to Date: $60,761,928 Balance: $1,225,264
Weekly Update: 6/17/2026: Construction 87% complete. Working on interior and exterior finishes. Furniture has been ordered. Anticipated completion August 2026.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 6/17/2026: BC 99% complete. Awaiting redesign from PG&E. Updated completion date is Oct 2026.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $799,312 Balance: $688
Weekly Update: 6/4/2026: Closeout in progress.



Projects Summaries

BC Campus Wide ADA Projects
Design Start: Mar 2026 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $794,000 Costs to Date: $0 Balance: $794,000
Weekly Update: 6/15/2026: Architect working on project plans to submit to DSA.


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,453,814 Balance: $44,186
Weekly Update: 6/17/2026: Notice of Completion filed. Retention payment in progress for closeout.


BC Campuswide Elevator Upgrades & Rehabilitation
Design Start: Jun 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $6,250,000 Costs to Date: $0 Balance: $6,250,000
Weekly Update:



Projects Summaries

BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $1,442,878 Balance: $26,550,122
Weekly Update: 6/4/2026: Design and budget meeting complete. Final layout approved. Moving into construction documents. Project approved by State Chancellor Office. Meeting with architect to finalize mechanical and electrical systems complete. Final design for furniture and office space in progress. 3D design and color review complete. DSA submission August 2026.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $27,617 Balance: $1,972,383
Weekly Update: 6/4/2026: Planning in progress for counseling to move into library over summer of 2026. Furniture and office space floorplan complete. Communication and electrical in progress. Furniture and office spaces to be installed July 2026.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,733,999 Balance: $8,266,001
Weekly Update: 6/4/2026: Final concept and floor plan approved. Construction documents in progress. Meeting for security complete in progress. Landscape design meeting June 8, 2026.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $6,150,000 Costs to Date: $5,763,320 Balance: $386,681
Weekly Update: 6/17/2026: Construction 35% complete. Backfilling in progress.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $18,000 Balance: $343,000
Weekly Update: 6/15/2026: Architect working on project drawings to submit to DSA.


BC Culinary Arts Lab Renovation
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,500,000 Costs to Date: $440,100 Balance: $4,059,900
Weekly Update: 6/17/2026: Project is in preliminary design phase. Floor plan design completed. Awaiting stakeholder approval.



Projects Summaries

BC DC Randolph Center Maintenance Repairs
Design Start: Apr 2026 Project Status: In Design Funding Source: Local C.O. DO
Budget/PPR: $600,000 Costs to Date: $487,203 Balance: $112,798
Weekly Update: 6/17/2026: Construction has begun. Electrical work in progress.


BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $66,961 Balance: $433,039
Weekly Update: 6/17/2026: Project in design phase. DSA appointment is scheduled for July 1st.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $3,706,984 Balance: $193,016
Weekly Update: 6/17/2026: Phase II construction 80% complete. Roadwork and flatwork is complete. Striping forthcoming.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $482,376 Balance: $517,624
Weekly Update: 6/17/2026: Contractor to begin mobilizing on 6/17/2026.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,110,175 Balance: $576,280
Weekly Update: 6/17/2026: Construction 95% complete. Testing scheduled in the upcoming weeks. Punchwalk with engineer completed.


BC Fine Arts Replacement
Design Start: Oct 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $13,618,000 Costs to Date: $0 Balance: $13,618,000
Weekly Update: 6/17/2026: Project in preliminary design phase. Meetings to select in architect forthcoming.



Projects Summaries

BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,470,462 Balance: $6,529,538
Weekly Update: 6/8/2026: PG&E has approved design and switchgear. Switchgear is to be shipped in October 2026. Working with Electrical Engineer to put together bid documents.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: Close-out Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $709,057 Balance: $115,943
Weekly Update: 6/17/2026: Received all closeout documents. NOC has been filed.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $42,179 Balance: $757,821
Weekly Update: 6/4/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards arrived unprogrammed and work not completed. Boards were returned and awaiting shipment from vendor for installation.



Projects Summaries

BC Mass Communication
Design Start: Aug 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 6/17/2026: Construction complete. Electrical Engineer drafting specs for additional scope of work. Additional scope of work consists of adding speakers above the library and stadium and adding two interrupters for the PA system at baseball and football stadium.


BC Math Science Allied Health- Room 14 Remodel
Design Start: May 2026 Project Status: In Design Funding Source: Other
Budget/PPR: $450,000 Costs to Date: $47,250 Balance: $402,750
Weekly Update: 6/17/2026: Project in preliminary design phase. Preliminary plans are 80% complete.


BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $350,000 Costs to Date: $316,730 Balance: $33,270
Weekly Update: 6/15/2026: Construction 50% complete.



Projects Summaries

BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $300,000 Costs to Date: $283,811 Balance: $16,189
Weekly Update: 6/17/2026: Contract awarded. Contractor to begin mobilizing 6-15-2026.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 6/17/2026: Construction 95% complete. Air balance complete, contractor to complete corrections. Punch walk tentatively scheduled with the mechanical engineer first week of July.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 6/17/2026: Construction 95% complete. Air balance complete, contractor to complete corrections. Punch walk tentatively scheduled with the mechanical engineer first week of July.



Projects Summaries

BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $190,796 Balance: $9,204
Weekly Update: 6/17/2026: Closeout in progress.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $841,787 Balance: $308,213
Weekly Update: 6/17/2026: Construction 25% complete.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,228,575 Balance: $274,705
Weekly Update: 6/4/2026: Child Development Center and Maintenance Operations buildings to be painted summer of 2026. Bidding complete and project awarded. Pre-construction meeting June 8, 2026.



Projects Summaries

BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $145,450 Balance: $854,550
Weekly Update: 6/17/2026:Contract awarded. Preconstruction meeting forthcoming.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $1,330,071 Balance: $411,196
Weekly Update: 6/17/2026: Construction 15% completed. Demolition of east wing completed. MEP to be installed.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,403,481 Balance: $262,120
Weekly Update: 6/4/2026: Preconstruction meeting complete. Submittals under review. Project schedule in progress.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $682,000 Balance: $11,318,000
Weekly Update: 6/17/2026: Design in progress. Meeting to be scheduled with campus to review working drawings and updated cost estimate.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $58,338,243 Balance: $5,106,757
Weekly Update: 6/17/2026: Construction 82% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion October 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,384,201 Balance: $165,799
Weekly Update: 6/22/2026: Payment on remaining lease balance in progress.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 6/17/2026: Campus has decided to closeout this project and not continue. Legal notice sent, awaiting vendor response.