| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
|
BC Agriculture Building
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $60,487,192 | Costs to Date: $58,729,652 | Balance: $1,757,540 |
| Weekly Update: 10/6/2025: Construction 58% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion Mid-June 2026. | ||
|
BC Allied Health Math Science Remodel
|
||
| Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
| Budget/PPR: $2,850,000 | Costs to Date: $42,179 | Balance: $2,807,821 |
| Weekly Update: 10/6/2025: Closeout in progress. | ||
|
BC Arvin 4th and Walnut Grant Project
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $5,355,748 | Costs to Date: $0 | Balance: $5,355,748 |
| Weekly Update: 10/17/2025: Design Build Contract in progress. | ||
|
BC Arvin Educational Center
|
||
| Design Start: Jun 2020 | Project Status: Close-out |
Funding Source: Meas. J |
| Budget/PPR: $29,818,338 | Costs to Date: $29,158,577 | Balance: $659,761 |
| Weekly Update: 10/11/2025: Waiting on signage, and monument sign. Project is DSA Certified | ||
|
BC Bakersfield College and Delano Center Solar
|
||
| Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
| Weekly Update: 10/11/2025: BC 99% complete. Awaiting redesign from PG&E. Construction is approx 6-8 months out. | ||
|
BC Baseball Dugout Replacement
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $800,000 | Costs to Date: $689,708 | Balance: $110,292 |
| Weekly Update: 10/17/2025: Construction 60% complete. Earthwork 100% complete. Concrete foundation and block walls complete. Roof in progress. Project completion November 2025. Construction stopped and awaiting proposal for const on redesign of dugout fence location. | ||
|
BC Campus Wide ADA Projects
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $294,000 | Costs to Date: $0 | Balance: $294,000 |
| Weekly Update: 10/16/2025: PPR approved 9/11/2025. Meeting to be scheduled with the team to review and scope the project prior to moving forward. | ||
|
BC Campus Wide Security Cameras
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,498,000 | Costs to Date: $1,441,152 | Balance: $56,848 |
| Weekly Update: 10/17/2025: Construction 95% complete. (5) cameras pending at the solar canopy. Anticipated completion December 2025. | ||
|
BC Center For Student Success
|
||
| Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. BC |
| Budget/PPR: $27,993,000 | Costs to Date: $1,274,000 | Balance: $26,719,000 |
| Weekly Update: 10/17/2025: Basic requirement overview complete and briefed to BC staff. Next design concept meeting October 22, 2025. | ||
|
BC Center for Student Success Swing Space
|
||
| Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
| Weekly Update: 10/17/2025: Project approved. Initial planning to start January 2026. | ||
|
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $10,000,000 | Costs to Date: $1,670,499 | Balance: $8,329,501 |
| Weekly Update: 10/17/2025: Revised PPR complete. Meeting to be scheduled with the Architect to discuss additional updates and small design changes. | ||
|
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
| Design Start: Dec 2023 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $6,000,000 | Costs to Date: $812,940 | Balance: $5,187,060 |
| Weekly Update: 10/17/2025: Project is out to bid. Bid opening 10/23/2025. | ||
|
BC Combined Gym and Fieldhouse
|
||
| Design Start: Jan 2019 | Project Status: Close-out |
Funding Source: Meas. J |
| Budget/PPR: $67,700,000 | Costs to Date: $63,935,108 | Balance: $3,764,892 |
| Weekly Update: 10/11/2025: DSA closeout in progress. | ||
|
BC Combined Gym and Fieldhouse Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $361,000 | Costs to Date: $0 | Balance: $361,000 |
| Weekly Update: 10/16/2025: PPR approved 9/11/2025. Meeting to be scheduled with the team to review and scope the project prior to moving forward. | ||
|
BC Culinary Arts Lab Renovation
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $4,000,000 | Costs to Date: $0 | Balance: $4,000,000 |
| Weekly Update: 10/17/2025: In preliminary design phase. | ||
|
BC Delano Center Agrivoltaics Farm
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $500,000 | Costs to Date: $25,500 | Balance: $474,500 |
| Weekly Update: 10/17/2025: Project in the preliminary design phase. | ||
|
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $3,000,000 | Costs to Date: $1,877,102 | Balance: $1,122,898 |
| Weekly Update: 10/17/2025: Phase 1 construction 66% complete. Closeout on phase I in progress. Phase II bid opening scheduled for 11/06/2025 | ||
|
BC Delano Center Welding Lab Expansion
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,000,000 | Costs to Date: $275,237 | Balance: $724,763 |
| Weekly Update: 10/17/2025: Plans in DSA for review and approval. | ||
|
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,686,455 | Costs to Date: $1,109,175 | Balance: $577,280 |
| Weekly Update: 10/17/2025:Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/5/2025 | ||
|
BC Infrastructure
|
||
| Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $15,000,000 | Costs to Date: $8,119,114 | Balance: $6,880,886 |
| Weekly Update: 10/11/2025: Construction documents and specifications are complete for bidding purposes. High Voltage is high priority due to power outages. | ||
|
BC Infrastructure Campus Wide Rekeying
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $825,000 | Costs to Date: $667,337 | Balance: $157,663 |
| Weekly Update: 10/17/2025: Construction 99% complete. Punch list work in progress. | ||
|
BC Infrastructure Solar Inverter Repairs
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $800,000 | Costs to Date: $42,179 | Balance: $757,821 |
| Weekly Update: 10/17/2025: Construction 100% complete. Phase I to be completed September 2025. Proposal received from vendor for additional replacement of components found during inverter repairs. Amendment in progress for additional repairs. | ||
|
BC Lab Tech Bachelors Program
|
||
| Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
| Budget/PPR: $2,612,000 | Costs to Date: $2,318,439 | Balance: $293,561 |
| Weekly Update: 10/11/2025: Project is DSA certified. | ||
|
BC Mass Communication
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $550,000 | Costs to Date: $195,498 | Balance: $354,502 |
| Weekly Update: 10/17/2025: Contract awarded. Submittals in progress and under review. | ||
|
BC Safety Lighting Phase II
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $120,000 | Costs to Date: $0 | Balance: $120,000 |
| Weekly Update: 10/16/2025: PPR approved as of 9/11/25. Meeting with the team to review and scope the project in progress. | ||
|
BC Security Gates and Bollards
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $260,000 | Costs to Date: $28,522 | Balance: $231,478 |
| Weekly Update: 10/17/2025: Project was rescoped to have bollards as a priority. Project in design phase. | ||
|
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $460,000 | Costs to Date: $415,207 | Balance: $44,793 |
| Weekly Update: 10/17/2025: Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/3/2025 | ||
|
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $480,000 | Costs to Date: $440,851 | Balance: $39,149 |
| Weekly Update: 10/17/2025: Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/3/2025 | ||
|
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
| Weekly Update: 10/17/2025: Contract awarded. Construction to tentatively start in November 2025. | ||
|
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,150,000 | Costs to Date: $433,332 | Balance: $716,668 |
| Weekly Update: 10/17/2025: Project is in bidding phase for additional areas. Bid opening scheduled 11/6/2025 | ||
|
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
| Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $397,430 | Costs to Date: $397,429 | Balance: $1 |
| Weekly Update: 10/17/2025: Additional server work added to the project. Construction is 90% complete. | ||
|
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
| Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,938,882 | Costs to Date: $1,144,575 | Balance: $794,307 |
| Weekly Update: 10/17/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch list complete. NOC in progress. | ||
|
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
| Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
| Budget/PPR: $1,000,000 | Costs to Date: $143,770 | Balance: $856,230 |
| Weekly Update: 10/17/2025: Awaiting DSA plan approval. | ||
|
BC SMSR 2022-23 Phase II Window Replacement
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $216,115 | Costs to Date: $216,115 | Balance: $0 |
| Weekly Update: 10/11/2025 DSA reconciliation fee in progress. | ||
|
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
| Design Start: Feb 2025 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
| Budget/PPR: $1,741,267 | Costs to Date: $631,111 | Balance: $1,110,156 |
| Weekly Update: 10/17/2025: Phase II of this project has now been scheduled for construction to begin in May 2026. Bidding phase to begin in February 2026. | ||
|
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,230,000 | Costs to Date: $997,402 | Balance: $232,598 |
| Weekly Update: 10/17/2025: Flooring complete. Punch items complete. NOC in progress. First floor design in progress. Project to bid March 2026 for completion in May 2026. | ||
|
BC Soccer Field
|
||
| Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
| Weekly Update: 10/17/2025: Design in progress. Project has been rescoped. | ||
|
BC Student Housing
|
||
| Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
| Budget/PPR: $63,445,000 | Costs to Date: $58,312,487 | Balance: $5,132,513 |
| Weekly Update: 10/11/2025: Construction 48% complete. Structural concrete, framing, roofing rough electrical and plumbing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026. | ||
|
BC Swing Space (Measure J)
|
||
| Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $5,550,000 | Costs to Date: $5,472,100 | Balance: $77,900 |
| Weekly Update: 9/26/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing. | ||
|
BC Swing Space Modular Purchase
|
||
| Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,200,000 | Costs to Date: $993,872 | Balance: $206,128 |
| Weekly Update: 10/17/2025: Modular used for the restroom and showers in design. | ||
|
BC Welcome Center Interior & Exterior Improvements
|
||
| Design Start: Sep 2023 | Project Status: Close-out |
Funding Source: Meas. J Other |
| Budget/PPR: $292,358 | Costs to Date: $234,888 | Balance: $57,470 |
| Weekly Update: 10/17/2025: Closeout in progress. | ||
| BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
| BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
| BC Combined Gym and Fieldhouse | |