Facilities and Construction Report
Date: July 11, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,626,644 Balance: $1,860,548
Weekly Update: 7/6/2025: Construction 45% complete. Structural steel, concrete, framing, plumbing and electrical in progress. Anticipated completion August 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 7/6/2025: Audit complete and closeout in progress.


BC Arvin Educational Center
Design Start: Jun 2020 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $29,698,305 Balance: $120,033
Weekly Update: 7/6/2025: Waiting on signage, and monument sign. Working on closeout documents, and DSA closeout.



Projects Summaries

BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 7/6/2025: BC 99% complete. Battery backup equipment installation in progress. Interconnection scheduled for August 2025. Anticipated completion August 2025.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $154,157 Balance: $645,843
Weekly Update: 6/27/2025: Project start July 7, 2025. Project completion September 2025. Pre-construction meeting complete.


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $187,906 Balance: $1,310,094
Weekly Update: 7/6/2025: Infrastructure work in progress. Anticipated completion August 2025



Projects Summaries

BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 6/27/2025: Project approved.


BC Combined Gym & Fieldhouse (Modular Swing Space)
Design Start: Oct 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $150,000 Costs to Date: $73,644 Balance: $76,356
Weekly Update: 7/6/2025: Campus is going to purchase modulars.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 6/27/2025: Designs on hold pending future funding.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,000,000 Costs to Date: $2,246,976 Balance: $3,753,024
Weekly Update: 6/27/2025: DSA approval for demolition of north and south buildings complete. Awaiting approval for equipment building.


BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $63,843,904 Balance: $3,856,096
Weekly Update: 7/6/2025: Pending DSA closeout.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $1,876,081 Balance: $1,123,919
Weekly Update: 6/9/2025: Construction 60% complete. RFP issued to de-scope the project and move the work to phase II due to SCE.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $127,293 Balance: $872,708
Weekly Update: 7/2/2025: Plans anticipated to be sent to DSA July for approval 2025.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $600,000 Costs to Date: $70,000 Balance: $530,000
Weekly Update: 6/9/2025: Preparing bid documents


BC Industrial Tech Electrical Lab Remodel
Design Start: Oct 2023 Project Status: Close-out Funding Source: Other
Budget/PPR: $1,200,000 Costs to Date: $0 Balance: $1,200,000
Weekly Update: 7/6/2025: Closeout in progress. Requesting final construction cost audit.



Projects Summaries

BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $7,833,652 Balance: $7,166,348
Weekly Update: 7/6/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Design Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $667,337 Balance: $157,663
Weekly Update: 6/9/2025: Construction tentative start date 6/23/2025.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 7/6/2025: Materials have been ordered. Pending delivery date.



Projects Summaries

BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $2,316,261 Balance: $295,739
Weekly Update: 7/6/2025: Closeout in progress.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $24,200 Balance: $525,800
Weekly Update: 7/6/2025: RFP for re-bidding forthcoming.


BC Science and Engineering Phase II
Design Start: Jan 2024 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $2,150,000 Costs to Date: $2,013,397 Balance: $136,603
Weekly Update: 7/6/2025 Project closeout in progress.



Projects Summaries

BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $27,500 Balance: $232,500
Weekly Update: 6/9/2025: This program will be revised to include the bollards.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $46,189 Balance: $413,811
Weekly Update: 6/9/2025: Award of contract going to Board for approval June 2025.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $55,987 Balance: $424,013
Weekly Update: 6/9/2025: Award of contract going to Board for approval June 2025.



Projects Summaries

BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 6/9/2025: Final bid scope established by campus. Preparing bid documents.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $385,313 Balance: $764,687
Weekly Update: 6/9/2025: Construction 40% complete.


BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,500,000 Costs to Date: $397,429 Balance: $1,102,571
Weekly Update: 6/9/2025: Additional server work added to the project. Work to begin in June 2025.



Projects Summaries

BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,938,882 Costs to Date: $1,145,663 Balance: $793,219
Weekly Update: 6/27/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium in progress.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 7/6/2025: Awaiting DSA plan approval.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $188,332 Balance: $1,552,935
Weekly Update: 6/9/2025: Construction 20% complete.



Projects Summaries

BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,230,000 Costs to Date: $96,172 Balance: $1,133,828
Weekly Update: 7/7/2025: Project start date June 23, 2025.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 6/9/2025: Design in progress. Meeting to be scheduled with new BC staff for review.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $55,730,111 Balance: $7,714,889
Weekly Update: 7/6/2025: Construction 40% complete. Site utilities, structural concrete, framing in progress. Anticipated completion Aug 2026.



Projects Summaries

BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,475,430 Balance: $74,570
Weekly Update: 7/6/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing.


BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $975,372 Balance: $224,628
Weekly Update: 6/6/2025: Purchase contracts going to Board for approval June 2026.


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: Close-out Funding Source: Meas. J
Other
Budget/PPR: $292,358 Costs to Date: $234,888 Balance: $57,470
Weekly Update: 6/9/2025: Contract awarded for additional work being completed in the fireside room.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse