Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
BC Agriculture Building
|
||
Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $60,487,192 | Costs to Date: $29,347,474 | Balance: $31,139,718 |
Weekly Update: 8/22/2025: Construction 47% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion August 2026. |
BC Allied Health Math Science Remodel
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
Weekly Update: 8/22/2025: Closeout in progress. |
BC Arvin 4th and Walnut Grant Project
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $5,355,748 | Costs to Date: $0 | Balance: $5,355,748 |
Weekly Update: 8/25/2025: Design Build Contract draft pending architects signature. |
BC Arvin Educational Center
|
||
Design Start: Jun 2020 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $29,818,338 | Costs to Date: $28,013,107 | Balance: $1,805,231 |
Weekly Update: 8/22/2025: Waiting on signage, and monument sign. Closeout documents and DSA closeout in progress. |
BC Bakersfield College and Delano Center Solar
|
||
Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
Weekly Update: 8/22/2025: BC 99% complete. PG&E has determined that the design is inadequate and will need to be redesigned. Update on design and construction is 6-8 months out. |
BC Baseball Dugout Replacement
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $800,000 | Costs to Date: $88,479 | Balance: $711,521 |
Weekly Update: 8/22/2025: Project start date July 28, 2025. Existing dugouts removed. Earthwork in progress, first base dugout compaction complete. Third base dugout compaction in progress. Project completion September 2025. |
BC Campus Wide Security Cameras
|
||
Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
Budget/PPR: $1,498,000 | Costs to Date: $187,444 | Balance: $1,310,556 |
Weekly Update: 8/22/2025: Construction 75% complete. Pending 5 cameras at the Solar canopy. Anticipated completion August 2025. |
BC Center For Student Success
|
||
Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. PC |
Budget/PPR: $27,993,000 | Costs to Date: $0 | Balance: $27,993,000 |
Weekly Update: 8/22/2025: PPR Approved. Architect selection complete. Design planning interviews scheduled for September 3, 2025. |
BC Center for Student Success Swing Space
|
||
Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
Weekly Update: 8/22/2025: Project approved. Initial planning to start December 2025. |
BC Combined Gym & Fieldhouse (Modular Swing Space)
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $150,000 | Costs to Date: $69,310 | Balance: $80,690 |
Weekly Update: 8/25/2025: Closeout in progress. |
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $10,000,000 | Costs to Date: $219,038 | Balance: $9,780,962 |
Weekly Update: 8/22/2025: Revised PPR in progress to start final designs and approval for DSA submission. |
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $6,000,000 | Costs to Date: $435,096 | Balance: $5,564,904 |
Weekly Update: 8/22/2025: DSA approval for demolition of north and south buildings complete. DSA approval for Equipment Building complete, awaiting release of plans. |
BC Combined Gym and Fieldhouse
|
||
Design Start: Jan 2019 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $67,700,000 | Costs to Date: $63,796,411 | Balance: $3,903,589 |
Weekly Update: 8/22/2025: DSA closeout in progress. |
BC Delano Center Agrivoltaics Farm
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $500,000 | Costs to Date: $0 | Balance: $500,000 |
Weekly Update: |
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $3,000,000 | Costs to Date: $538,490 | Balance: $2,461,510 |
Weekly Update: 8/25/2025: Phase 1 Construction 66% complete. Closeout on phase I in progress. Phase II approved by DSA. Bidding documents forthcoming. |
BC Delano Center Welding Lab Expansion
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,000,000 | Costs to Date: $64,343 | Balance: $935,658 |
Weekly Update: 8/25/2025: Plans submitted to DSA. |
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,702,570 | Costs to Date: $63,004 | Balance: $1,639,566 |
Weekly Update: 8/25/2025: Award of contract going to Board for approval September 11, 2025. |
BC Industrial Tech Electrical Lab Remodel
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $1,200,000 | Costs to Date: $0 | Balance: $1,200,000 |
Weekly Update: 8/22/2025 Project is closed. |
BC Infrastructure
|
||
Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $15,000,000 | Costs to Date: $6,507,284 | Balance: $8,492,716 |
Weekly Update: 8/22/2025: Water scope on hold. Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study complete. High Voltage is high priority due to power outages. PG&E approved Engineer design. |
BC Infrastructure Campus Wide Rekeying
|
||
Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $825,000 | Costs to Date: $4,374 | Balance: $820,626 |
Weekly Update: 8/25/2025: Construction 80% complete. Work in progress. |
BC Infrastructure Solar Inverter Repairs
|
||
Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 8/22/2025: Construction 60% complete. Phase I of project to be completed Sept 2025. |
BC Lab Tech Bachelors Program
|
||
Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
Budget/PPR: $2,612,000 | Costs to Date: $2,207,207 | Balance: $404,793 |
Weekly Update: 8/22/2025: Closeout in progress. |
BC Mass Communication
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $550,000 | Costs to Date: $8,800 | Balance: $541,200 |
Weekly Update: 8/25/2025: Award of contract going to the Board for approval September 11, 2025. |
BC Security Gates and Bollards
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $260,000 | Costs to Date: $12,375 | Balance: $247,625 |
Weekly Update: 8/25/2025: Design complete. Bidding documents forthcoming. |
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $460,000 | Costs to Date: $46,189 | Balance: $413,811 |
Weekly Update: 8/25/2025: Construction to start tentatively October 2025. |
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $480,000 | Costs to Date: $48,487 | Balance: $431,513 |
Weekly Update: 8/25/2025: Construction to start tentatively October 2025. |
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
Weekly Update: 8/25/2025: Bid documents have been drafted. BC staff to review. |
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,150,000 | Costs to Date: $226,289 | Balance: $923,711 |
Weekly Update: 8/25/2025: Establishing new project area for remaining funds. |
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $397,430 | Costs to Date: $288,429 | Balance: $109,001 |
Weekly Update: 8/25/2025: Additional server work added to the project. |
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,938,882 | Costs to Date: $1,079,632 | Balance: $859,250 |
Weekly Update: 8/22/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch walk complete. Rework in progress. |
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,000,000 | Costs to Date: $91,290 | Balance: $908,710 |
Weekly Update: 8/25/2025: Awaiting DSA plan approval. |
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
Design Start: Feb 2025 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
Budget/PPR: $1,741,267 | Costs to Date: $367,071 | Balance: $1,374,197 |
Weekly Update: 8/25/2025: Phase 1 Construction 100% complete. Phase II in DSA. |
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,230,000 | Costs to Date: $273,922 | Balance: $956,078 |
Weekly Update: 8/22/2025: Project in progress. Demolition complete. Texture and priming complete. Color selection and carpet pattern approved. Painting complete. Flooring complete. Punch walk complete. Rework in progress, completion scheduled for August 23, 2025. |
BC Soccer Field
|
||
Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $12,000,000 | Costs to Date: $151,925 | Balance: $11,848,075 |
Weekly Update: 8/25/2025: Design in progress. BC staff to review value engineering proposal. |
BC Student Housing
|
||
Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
Budget/PPR: $63,445,000 | Costs to Date: $20,845,122 | Balance: $42,599,878 |
Weekly Update: 8/22/2025: Construction 45% complete. Site utilities, structural concrete, framing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026. |
BC Swing Space (Measure J)
|
||
Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $5,550,000 | Costs to Date: $5,441,522 | Balance: $108,478 |
Weekly Update: 8/22/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing. |
BC Swing Space Modular Purchase
|
||
Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,200,000 | Costs to Date: $975,372 | Balance: $224,628 |
Weekly Update: 8/25/2025: Purchase of modular used for the field house complete. Remaining modular used for the restroom and showers in design. |
BC Welcome Center Interior & Exterior Improvements
|
||
Design Start: Sep 2023 | Project Status: In Const |
Funding Source: Meas. J Other |
Budget/PPR: $292,358 | Costs to Date: $157,045 | Balance: $135,313 |
Weekly Update: 08/25/2025: Construction completed. Preparing project close out. |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | |