Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
BC Agriculture Building
|
||
Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $60,487,192 | Costs to Date: $58,626,644 | Balance: $1,860,548 |
Weekly Update: 7/6/2025: Construction 45% complete. Structural steel, concrete, framing, plumbing and electrical in progress. Anticipated completion August 2026. |
BC Allied Health Math Science Remodel
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
Weekly Update: 7/6/2025: Audit complete and closeout in progress. |
BC Arvin Educational Center
|
||
Design Start: Jun 2020 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $29,818,338 | Costs to Date: $29,698,305 | Balance: $120,033 |
Weekly Update: 7/6/2025: Waiting on signage, and monument sign. Working on closeout documents, and DSA closeout. |
BC Bakersfield College and Delano Center Solar
|
||
Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
Weekly Update: 7/6/2025: BC 99% complete. Battery backup equipment installation in progress. Interconnection scheduled for August 2025. Anticipated completion August 2025. |
BC Baseball Dugout Replacement
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $800,000 | Costs to Date: $154,157 | Balance: $645,843 |
Weekly Update: 6/27/2025: Project start July 7, 2025. Project completion September 2025. Pre-construction meeting complete. |
BC Campus Wide Security Cameras
|
||
Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
Budget/PPR: $1,498,000 | Costs to Date: $187,906 | Balance: $1,310,094 |
Weekly Update: 7/6/2025: Infrastructure work in progress. Anticipated completion August 2025 |
BC Center for Student Success Swing Space
|
||
Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
Weekly Update: 6/27/2025: Project approved. |
BC Combined Gym & Fieldhouse (Modular Swing Space)
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $150,000 | Costs to Date: $73,644 | Balance: $76,356 |
Weekly Update: 7/6/2025: Campus is going to purchase modulars. |
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
Weekly Update: 6/27/2025: Designs on hold pending future funding. |
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $6,000,000 | Costs to Date: $2,246,976 | Balance: $3,753,024 |
Weekly Update: 6/27/2025: DSA approval for demolition of north and south buildings complete. Awaiting approval for equipment building. |
BC Combined Gym and Fieldhouse
|
||
Design Start: Jan 2019 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $67,700,000 | Costs to Date: $63,843,904 | Balance: $3,856,096 |
Weekly Update: 7/6/2025: Pending DSA closeout. |
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $3,000,000 | Costs to Date: $1,876,081 | Balance: $1,123,919 |
Weekly Update: 6/9/2025: Construction 60% complete. RFP issued to de-scope the project and move the work to phase II due to SCE. |
BC Delano Center Welding Lab Expansion
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,000,000 | Costs to Date: $127,293 | Balance: $872,708 |
Weekly Update: 7/2/2025: Plans anticipated to be sent to DSA July for approval 2025. |
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $600,000 | Costs to Date: $70,000 | Balance: $530,000 |
Weekly Update: 6/9/2025: Preparing bid documents |
BC Industrial Tech Electrical Lab Remodel
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $1,200,000 | Costs to Date: $0 | Balance: $1,200,000 |
Weekly Update: 7/6/2025: Closeout in progress. Requesting final construction cost audit. |
BC Infrastructure
|
||
Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $15,000,000 | Costs to Date: $7,833,652 | Balance: $7,166,348 |
Weekly Update: 7/6/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages. |
BC Infrastructure Campus Wide Rekeying
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Meas. J Meas. G |
Budget/PPR: $825,000 | Costs to Date: $667,337 | Balance: $157,663 |
Weekly Update: 6/9/2025: Construction tentative start date 6/23/2025. |
BC Infrastructure Solar Inverter Repairs
|
||
Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 7/6/2025: Materials have been ordered. Pending delivery date. |
BC Lab Tech Bachelors Program
|
||
Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
Budget/PPR: $2,612,000 | Costs to Date: $2,316,261 | Balance: $295,739 |
Weekly Update: 7/6/2025: Closeout in progress. |
BC Mass Communication
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $550,000 | Costs to Date: $24,200 | Balance: $525,800 |
Weekly Update: 7/6/2025: RFP for re-bidding forthcoming. |
BC Science and Engineering Phase II
|
||
Design Start: Jan 2024 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $2,150,000 | Costs to Date: $2,013,397 | Balance: $136,603 |
Weekly Update: 7/6/2025 Project closeout in progress. |
BC Security Gates and Bollards
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $260,000 | Costs to Date: $27,500 | Balance: $232,500 |
Weekly Update: 6/9/2025: This program will be revised to include the bollards. |
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $460,000 | Costs to Date: $46,189 | Balance: $413,811 |
Weekly Update: 6/9/2025: Award of contract going to Board for approval June 2025. |
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $480,000 | Costs to Date: $55,987 | Balance: $424,013 |
Weekly Update: 6/9/2025: Award of contract going to Board for approval June 2025. |
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
Weekly Update: 6/9/2025: Final bid scope established by campus. Preparing bid documents. |
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,150,000 | Costs to Date: $385,313 | Balance: $764,687 |
Weekly Update: 6/9/2025: Construction 40% complete. |
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,500,000 | Costs to Date: $397,429 | Balance: $1,102,571 |
Weekly Update: 6/9/2025: Additional server work added to the project. Work to begin in June 2025. |
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,938,882 | Costs to Date: $1,145,663 | Balance: $793,219 |
Weekly Update: 6/27/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium in progress. |
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,000,000 | Costs to Date: $143,770 | Balance: $856,230 |
Weekly Update: 7/6/2025: Awaiting DSA plan approval. |
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
Budget/PPR: $1,741,267 | Costs to Date: $188,332 | Balance: $1,552,935 |
Weekly Update: 6/9/2025: Construction 20% complete. |
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,230,000 | Costs to Date: $96,172 | Balance: $1,133,828 |
Weekly Update: 7/7/2025: Project start date June 23, 2025. |
BC Soccer Field
|
||
Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
Weekly Update: 6/9/2025: Design in progress. Meeting to be scheduled with new BC staff for review. |
BC Student Housing
|
||
Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
Budget/PPR: $63,445,000 | Costs to Date: $55,730,111 | Balance: $7,714,889 |
Weekly Update: 7/6/2025: Construction 40% complete. Site utilities, structural concrete, framing in progress. Anticipated completion Aug 2026. |
BC Swing Space (Measure J)
|
||
Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $5,550,000 | Costs to Date: $5,475,430 | Balance: $74,570 |
Weekly Update: 7/6/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing. |
BC Swing Space Modular Purchase
|
||
Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,200,000 | Costs to Date: $975,372 | Balance: $224,628 |
Weekly Update: 6/6/2025: Purchase contracts going to Board for approval June 2026. |
BC Welcome Center Interior & Exterior Improvements
|
||
Design Start: Sep 2023 | Project Status: Close-out |
Funding Source: Meas. J Other |
Budget/PPR: $292,358 | Costs to Date: $234,888 | Balance: $57,470 |
Weekly Update: 6/9/2025: Contract awarded for additional work being completed in the fireside room. |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | |