| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
|
BC Agriculture Building
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $60,487,192 | Costs to Date: $59,152,750 | Balance: $1,334,442 |
| Weekly Update: 3/6/2026: Construction 73% complete. Working on interior and exterior finishes. Furniture has been ordered. Anticipated completion Mid-July 2026. | ||
|
BC Allied Health Math Science Remodel
|
||
| Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
| Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
| Weekly Update: 3/6/2026: Closeout in progress. | ||
|
BC Bakersfield College and Delano Center Solar
|
||
| Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
| Weekly Update: 3/6/2026: BC 99% complete. Awaiting redesign from PG&E. Updated completion date is May 2026 | ||
|
BC Baseball Dugout Replacement
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $800,000 | Costs to Date: $796,188 | Balance: $3,812 |
| Weekly Update: 2/17/2026: Construction 100% complete. Punch list items in progress. | ||
|
BC Campus Wide ADA Projects
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $294,000 | Costs to Date: $0 | Balance: $294,000 |
| Weekly Update: 3/12/2026: Meeting has been scheduled with the campus for 3-9-2026 to review and scope the project prior to moving forward. | ||
|
BC Campus Wide Security Cameras
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,498,000 | Costs to Date: $1,453,814 | Balance: $44,186 |
| Weekly Update: 2/27/2026: Construction 98% complete. Cameras have been installed. Contractor is completing testing on the equipment. | ||
|
BC Center For Student Success
|
||
| Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. BC |
| Budget/PPR: $27,993,000 | Costs to Date: $1,309,778 | Balance: $26,683,222 |
| Weekly Update: 2/17/2026: Basic requirement overview complete and briefed to BC staff. Design and budget meeting complete. Final layout approved, moving into construction documents. | ||
|
BC Center for Student Success Swing Space
|
||
| Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
| Weekly Update: 2/17/2026: Initial planning to start January or February 2026. | ||
|
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $10,000,000 | Costs to Date: $1,670,499 | Balance: $8,329,501 |
| Weekly Update: 2/17/2026: Final concept and floor plan approved. Moving into construction documents phase. | ||
|
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $6,150,000 | Costs to Date: $5,762,095 | Balance: $387,906 |
| Weekly Update: 2/27/2026: Pools have been drained. Demolition of northern building set to begin on 3/2/26 | ||
|
BC Combined Gym and Fieldhouse Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $361,000 | Costs to Date: $0 | Balance: $361,000 |
| Weekly Update: 3/12/26: Architect estimates have been sent to the campus. | ||
|
BC Culinary Arts Lab Renovation
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $4,500,000 | Costs to Date: $0 | Balance: $4,500,000 |
| Weekly Update: 2/27/2026: Architect has been selected. Proposal forthcoming. | ||
|
BC Delano Center Agrivoltaics Farm
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $500,000 | Costs to Date: $25,500 | Balance: $474,500 |
| Weekly Update: 2/27/2026: Project in design phase. | ||
|
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $3,900,000 | Costs to Date: $3,699,785 | Balance: $200,215 |
| Weekly Update: 2/27/2026: Ground is being excavated to extend the sump. | ||
|
BC Delano Center Welding Lab Expansion
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,000,000 | Costs to Date: $277,187 | Balance: $722,813 |
| Weekly Update: 2/27/2026: Project is currently out to bid. Bid opening 3-10-2026. | ||
|
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,686,455 | Costs to Date: $1,109,175 | Balance: $577,280 |
| Weekly Update: 2/27/2026: Construction is 60% complete. The remaining work will be completed during spring break 2026. | ||
|
BC Fine Arts Replacement
|
||
| Design Start: Oct 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $13,618,000 | Costs to Date: $0 | Balance: $13,618,000 |
| Weekly Update: 2/27/2026: Project is in preliminary design phase. | ||
|
BC Infrastructure
|
||
| Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $15,000,000 | Costs to Date: $8,470,017 | Balance: $6,529,983 |
| Weekly Update: 2/27/2026: PG&E has approved design and switchgear. Switchgear is to be shipped in October 2026. | ||
|
BC Infrastructure Campus Wide Rekeying
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $825,000 | Costs to Date: $672,113 | Balance: $152,887 |
| Weekly Update: 2/27/2026: Construction 99% complete. Final job walk has been scheduled | ||
|
BC Infrastructure Solar Inverter Repairs
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $800,000 | Costs to Date: $42,179 | Balance: $757,821 |
| Weekly Update: 2/17/2026: Construction 100% complete for initial contract. Additional repairs to inverters complete and start up conducted. Approval of repairs to circuit boards complete. Scheduling remaining work. | ||
|
BC Mass Communication
|
||
| Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $550,000 | Costs to Date: $195,498 | Balance: $354,502 |
| Weekly Update: 2/27/2026: Construction is 95% complete. Equipment has been installed. Testing is scheduled on 2-27-2026 | ||
|
BC Safety Lighting Phase II
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $350,000 | Costs to Date: $0 | Balance: $350,000 |
| Weekly Update: 3/12/26: Contract award going to March Board meeting for approval. | ||
|
BC Security Gates and Bollards
|
||
| Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $260,000 | Costs to Date: $29,722 | Balance: $230,278 |
| Weekly Update: 2/27/2026: Project is in bidding phase. Bid opening 3-5-2026. | ||
|
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $460,000 | Costs to Date: $415,207 | Balance: $44,793 |
| Weekly Update: 2/27/2026: Construction is 95% complete. Air balance is scheduled for 3/16. | ||
|
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
| Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $480,000 | Costs to Date: $440,851 | Balance: $39,149 |
| Weekly Update: 2/27/2026: Construction is 95% complete. Air Balance is scheduled 3/19 | ||
|
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $200,000 | Costs to Date: $190,796 | Balance: $9,204 |
| Weekly Update: 2/27/2026: Received recorded NOC. Preparing project closeout. | ||
|
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,150,000 | Costs to Date: $611,532 | Balance: $538,468 |
| Weekly Update: 2/27/2026: Currently out to bid. Bid opening scheduled 3-10-2026. | ||
|
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
| Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $397,430 | Costs to Date: $397,429 | Balance: $1 |
| Weekly Update: 2/27/2026: Construction is 100% complete. NOC has been filed. | ||
|
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
| Design Start: Apr 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $1,503,280 | Costs to Date: $1,144,575 | Balance: $358,705 |
| Weekly Update: 2/17/2026: Child Development Center and Maintenance Operations buildings to be painted summer of 2026. | ||
|
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
| Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
| Budget/PPR: $1,000,000 | Costs to Date: $144,970 | Balance: $855,030 |
| Weekly Update: 2/27/2026: Awaiting DSA plan approval. | ||
|
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
| Design Start: Feb 2025 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
| Budget/PPR: $1,741,267 | Costs to Date: $633,120 | Balance: $1,108,147 |
| Weekly Update: 2/27/2026: Bids under review. Construction to start May 2026. | ||
|
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,665,601 | Costs to Date: $1,067,097 | Balance: $598,504 |
| Weekly Update: 2/17/2026: Phase II first floor design in progress. Project to bid March 2026 for completion in May 2026. Preliminary floor layout and paint colors under review. | ||
|
BC Soccer Field
|
||
| Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
| Weekly Update: 2/27/2026: Design in progress. Site plan approved by the campus on 1-13-2026. | ||
|
BC Student Housing
|
||
| Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
| Budget/PPR: $63,445,000 | Costs to Date: $56,156,934 | Balance: $7,288,066 |
| Weekly Update: 3/6/2026: Construction 71% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Anticipated completion October 2026. | ||
|
BC Swing Space (Measure J)
|
||
| Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $5,550,000 | Costs to Date: $5,472,100 | Balance: $77,900 |
| Weekly Update: 3/6/2026: Payment on remaining lease balance in progress. | ||
|
BC Swing Space Modular Purchase
|
||
| Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,200,000 | Costs to Date: $993,872 | Balance: $206,128 |
| Weekly Update: 2/27/2026: Campus has decided to closeout this project and not continue. | ||