Facilities and Construction Report
Date: October 24, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $58,729,652 Balance: $1,757,540
Weekly Update: 10/6/2025: Construction 58% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion Mid-June 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $42,179 Balance: $2,807,821
Weekly Update: 10/6/2025: Closeout in progress.


BC Arvin 4th and Walnut Grant Project
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $5,355,748 Costs to Date: $0 Balance: $5,355,748
Weekly Update: 10/17/2025: Design Build Contract in progress.



Projects Summaries

BC Arvin Educational Center
Design Start: Jun 2020 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $29,158,577 Balance: $659,761
Weekly Update: 10/11/2025: Waiting on signage, and monument sign. Project is DSA Certified


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 10/11/2025: BC 99% complete. Awaiting redesign from PG&E. Construction is approx 6-8 months out.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $689,708 Balance: $110,292
Weekly Update: 10/17/2025: Construction 60% complete. Earthwork 100% complete. Concrete foundation and block walls complete. Roof in progress. Project completion November 2025. Construction stopped and awaiting proposal for const on redesign of dugout fence location.



Projects Summaries

BC Campus Wide ADA Projects
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $294,000 Costs to Date: $0 Balance: $294,000
Weekly Update: 10/16/2025: PPR approved 9/11/2025. Meeting to be scheduled with the team to review and scope the project prior to moving forward.


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,441,152 Balance: $56,848
Weekly Update: 10/17/2025: Construction 95% complete. (5) cameras pending at the solar canopy. Anticipated completion December 2025.


BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $1,274,000 Balance: $26,719,000
Weekly Update: 10/17/2025: Basic requirement overview complete and briefed to BC staff. Next design concept meeting October 22, 2025.



Projects Summaries

BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 10/17/2025: Project approved. Initial planning to start January 2026.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,670,499 Balance: $8,329,501
Weekly Update: 10/17/2025: Revised PPR complete. Meeting to be scheduled with the Architect to discuss additional updates and small design changes.


BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,000,000 Costs to Date: $812,940 Balance: $5,187,060
Weekly Update: 10/17/2025: Project is out to bid. Bid opening 10/23/2025.



Projects Summaries

BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $63,935,108 Balance: $3,764,892
Weekly Update: 10/11/2025: DSA closeout in progress.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $0 Balance: $361,000
Weekly Update: 10/16/2025: PPR approved 9/11/2025. Meeting to be scheduled with the team to review and scope the project prior to moving forward.


BC Culinary Arts Lab Renovation
Design Start: Sep 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,000,000 Costs to Date: $0 Balance: $4,000,000
Weekly Update: 10/17/2025: In preliminary design phase.



Projects Summaries

BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $25,500 Balance: $474,500
Weekly Update: 10/17/2025: Project in the preliminary design phase.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $1,877,102 Balance: $1,122,898
Weekly Update: 10/17/2025: Phase 1 construction 66% complete. Closeout on phase I in progress. Phase II bid opening scheduled for 11/06/2025


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $275,237 Balance: $724,763
Weekly Update: 10/17/2025: Plans in DSA for review and approval.



Projects Summaries

BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,109,175 Balance: $577,280
Weekly Update: 10/17/2025:Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/5/2025


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,119,114 Balance: $6,880,886
Weekly Update: 10/11/2025: Construction documents and specifications are complete for bidding purposes. High Voltage is high priority due to power outages.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $667,337 Balance: $157,663
Weekly Update: 10/17/2025: Construction 99% complete. Punch list work in progress.



Projects Summaries

BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $42,179 Balance: $757,821
Weekly Update: 10/17/2025: Construction 100% complete. Phase I to be completed September 2025. Proposal received from vendor for additional replacement of components found during inverter repairs. Amendment in progress for additional repairs.


BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $2,318,439 Balance: $293,561
Weekly Update: 10/11/2025: Project is DSA certified.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 10/17/2025: Contract awarded. Submittals in progress and under review.



Projects Summaries

BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $120,000 Costs to Date: $0 Balance: $120,000
Weekly Update: 10/16/2025: PPR approved as of 9/11/25. Meeting with the team to review and scope the project in progress.


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $28,522 Balance: $231,478
Weekly Update: 10/17/2025: Project was rescoped to have bollards as a priority. Project in design phase.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 10/17/2025: Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/3/2025



Projects Summaries

BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 10/17/2025: Construction to start tentatively December 2025. Preconstruction meeting scheduled for 11/3/2025


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 10/17/2025: Contract awarded. Construction to tentatively start in November 2025.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $433,332 Balance: $716,668
Weekly Update: 10/17/2025: Project is in bidding phase for additional areas. Bid opening scheduled 11/6/2025



Projects Summaries

BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $397,429 Balance: $1
Weekly Update: 10/17/2025: Additional server work added to the project. Construction is 90% complete.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,938,882 Costs to Date: $1,144,575 Balance: $794,307
Weekly Update: 10/17/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch list complete. NOC in progress.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $143,770 Balance: $856,230
Weekly Update: 10/17/2025: Awaiting DSA plan approval.



Projects Summaries

BC SMSR 2022-23 Phase II Window Replacement
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $216,115 Costs to Date: $216,115 Balance: $0
Weekly Update: 10/11/2025 DSA reconciliation fee in progress.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $631,111 Balance: $1,110,156
Weekly Update: 10/17/2025: Phase II of this project has now been scheduled for construction to begin in May 2026. Bidding phase to begin in February 2026.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,230,000 Costs to Date: $997,402 Balance: $232,598
Weekly Update: 10/17/2025: Flooring complete. Punch items complete. NOC in progress. First floor design in progress. Project to bid March 2026 for completion in May 2026.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 10/17/2025: Design in progress. Project has been rescoped.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $58,312,487 Balance: $5,132,513
Weekly Update: 10/11/2025: Construction 48% complete. Structural concrete, framing, roofing rough electrical and plumbing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,472,100 Balance: $77,900
Weekly Update: 9/26/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 10/17/2025: Modular used for the restroom and showers in design.


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: Close-out Funding Source: Meas. J
Other
Budget/PPR: $292,358 Costs to Date: $234,888 Balance: $57,470
Weekly Update: 10/17/2025: Closeout in progress.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse