| Please contact any of the following regarding questions or comments associated with this report: | |||
| Daniel Reed | Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
| Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
| Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
| Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
| Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
| Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
| Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
| Ginger Popplewell | Department Assistant III | 661-336-5093 | ginger.popplewell@kccd.edu |
|
BC Agriculture Building
|
||
| Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
| Budget/PPR: $61,987,192 | Costs to Date: $60,941,310 | Balance: $1,045,882 |
| Weekly Update: 9/1/2026: Construction 91% complete. Working on interior and exterior finishes. Furniture and technology will be installed September 2026. Anticipated completion October 2026. | ||
|
BC Bakersfield College and Delano Center Solar
|
||
| Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
| Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
| Weekly Update: 9/1/2026: BC 99% complete. Labor to install switchgear to go out to bid mid September 2026. Board approval October 2026. Updated completion date to utilize 100% of solar is November 2026. | ||
|
BC Baseball Dugout Replacement
|
||
| Design Start: Sep 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $800,000 | Costs to Date: $799,312 | Balance: $688 |
| Weekly Update: 9/10/2026: All forms submitted to DSA. Awaiting DSA certification. | ||
|
BC BC Campus Wide HVAC Repair & Replacement
|
||
| Design Start: Aug 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $3,166,666 | Costs to Date: $0 | Balance: $3,166,666 |
| Weekly Update: 9/1/206 PPR approved. | ||
|
BC Campus Wide ADA Projects
|
||
| Design Start: Mar 2026 | Project Status: In Design |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $794,000 | Costs to Date: $187,860 | Balance: $606,140 |
| Weekly Update: 9/11/2026: Architect working on project plans to submit to DSA. | ||
|
BC Campuswide Elevator Upgrades & Rehabilitation
|
||
| Design Start: Jun 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $6,250,000 | Costs to Date: $0 | Balance: $6,250,000 |
| Weekly Update: 9/11/2026: Work authorization in progress. In preliminary design phase. | ||
|
BC Center For Student Success
|
||
| Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. BC |
| Budget/PPR: $27,993,000 | Costs to Date: $3,657,603 | Balance: $24,335,397 |
| Weekly Update: 9/10/2026: Design and budget meeting complete. Final layout approved. Moving into construction documents. Project approved by State Chancellors Office. Mechanical and electrical systems design complete. Final design for furniture complete. 3D design and basic color review complete. Resubmit to DSA on October 13, 2026. | ||
|
BC Center for Student Success Swing Space
|
||
| Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $2,000,000 | Costs to Date: $598,110 | Balance: $1,401,890 |
| Weekly Update: 9/10/2026: Furniture and office space floor plan for library complete. Communication and electrical connections complete for Phase I. Data cabling installation complete. Meeting September 11, 2026, for Phase II location and coordination. | ||
|
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
| Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $10,000,000 | Costs to Date: $1,867,474 | Balance: $8,132,526 |
| Weekly Update: 9/10/2026: Final concept and floor plan approved. Construction documents in progress. Final landscape plan, interior finishes, and security/door access and controls meeting in progress. DSA submission scheduled for October 2, 2026. | ||
|
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $6,550,000 | Costs to Date: $6,012,830 | Balance: $537,170 |
| Weekly Update: 9/11/2026: Construction 40% complete. Contractor installing underground utilities and footings for foundation of the pool equipment building. | ||
|
BC Combined Gym and Fieldhouse Phase II
|
||
| Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
| Budget/PPR: $361,000 | Costs to Date: $19,787 | Balance: $341,213 |
| Weekly Update: 9/11/2026: Architect has submitted drawings to DSA. | ||
|
BC Culinary Arts Lab Renovation
|
||
| Design Start: Feb 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $4,500,000 | Costs to Date: $474,305 | Balance: $4,025,696 |
| Weekly Update: 9/11/2026: Elevation plan approved. Drawings are in design phase. | ||
|
BC DC Randolph Center Maintenance Repairs
|
||
| Design Start: Apr 2026 | Project Status: In Const |
Funding Source: Local C.O. DO |
| Budget/PPR: $600,000 | Costs to Date: $581,517 | Balance: $18,483 |
| Weekly Update: 9/11/2026: Construction 95% complete. Fire alarm upgrades in progress. | ||
|
BC Delano Center Agrivoltaics Farm
|
||
| Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $500,000 | Costs to Date: $66,961 | Balance: $433,039 |
| Weekly Update: 9/11/2026: Plans resubmitted to DSA for backcheck comments. Awaiting DSA review. | ||
|
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
| Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $3,900,000 | Costs to Date: $3,703,724 | Balance: $196,276 |
| Weekly Update: 9/11/2026: Phase II construction 95% complete. Punch work and change order work in progress. | ||
|
BC Delano Center Welding Lab Expansion
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,000,000 | Costs to Date: $504,992 | Balance: $495,008 |
| Weekly Update: 9/11/2026: Construction 85% complete. Shade structure and concrete pad completed. Fencing work in progress. | ||
|
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
| Design Start: Jan 2023 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $1,686,455 | Costs to Date: $1,166,823 | Balance: $519,632 |
| Weekly Update: 9/11/2026: Construction 100% complete. Contractor preparing closeout documents. Air balance to be readjusted per mechanical engineer's recommendation. | ||
|
BC Emergency Management Indoor Speakers
|
||
| Design Start: Sep 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,070,000 | Costs to Date: $0 | Balance: $1,070,000 |
| Weekly Update: 9/11/2026: In design phase. | ||
|
BC Fine Arts Replacement
|
||
| Design Start: Oct 2026 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $13,618,000 | Costs to Date: $0 | Balance: $13,618,000 |
| Weekly Update: 9/11/2026: Architect selected, Work Authorization approved. Project in preliminary design phase. | ||
|
BC Infrastructure
|
||
| Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $15,000,000 | Costs to Date: $8,408,834 | Balance: $6,591,166 |
| Weekly Update: 9/14/2026: Switchgear received. Proposal for installation forthcoming. | ||
|
BC Infrastructure Solar Inverter Repairs
|
||
| Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
| Budget/PPR: $800,000 | Costs to Date: $79,671 | Balance: $720,329 |
| Weekly Update: 9/10/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards completed. Inverters shutdown due to over temperature. Additional work required. Proposal received for new power supplies, cable sensors, and filters. Awaiting proposal for inverter replacement to determine options. | ||
|
BC Mass Communication
|
||
| Design Start: Aug 2024 | Project Status: Close-out |
Funding Source: Local C.O. BC |
| Budget/PPR: $550,000 | Costs to Date: $197,098 | Balance: $352,902 |
| Weekly Update: 9/11/2026: Construction complete. NOC filed for original scope of work. Preparing Bid documents for added scope of work. | ||
|
BC Math Science Allied Health- Room 14 Remodel
|
||
| Design Start: May 2026 | Project Status: In Design |
Funding Source: Other |
| Budget/PPR: $450,000 | Costs to Date: $145,060 | Balance: $304,940 |
| Weekly Update: 9/11/2026: Project in bidding phase. Job walk scheduled on 9/22/26, Bid opening scheduled 10/1/26. | ||
|
BC Safety Lighting Phase II
|
||
| Design Start: Sep 2025 | Project Status: In Const |
Funding Source: Meas. G Local C.O. BC |
| Budget/PPR: $350,000 | Costs to Date: $316,730 | Balance: $33,270 |
| Weekly Update: 9/11/2026: Closeout in progress. | ||
|
BC Security Gates and Bollards
|
||
| Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
| Budget/PPR: $300,000 | Costs to Date: $297,411 | Balance: $2,589 |
| Weekly Update: 9/11/2026: Construction 75% complete. Base for the Removable bollards installed. Awaiting sphere bollard installation. | ||
|
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
| Design Start: Feb 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $415,207 | Costs to Date: $415,207 | Balance: $0 |
| Weekly Update: 9/11/2026: Construction 100% complete. NOC has been filed. | ||
|
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
| Design Start: Feb 2024 | Project Status: Close-out |
Funding Source: SMSR |
| Budget/PPR: $440,852 | Costs to Date: $440,851 | Balance: $1 |
| Weekly Update: 9/11/2026: Construction 100% complete. NOC to be filed. | ||
|
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
| Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,150,000 | Costs to Date: $853,548 | Balance: $296,452 |
| Weekly Update: 9/11/2026: Construction 95% complete. Awaiting sack and patch work to be completed. | ||
|
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
| Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,503,280 | Costs to Date: $1,206,137 | Balance: $297,143 |
| Weekly Update: 9/10/2026: Child Development Center complete. Punch items complete. M&O building complete. Punch walk complete. NOC in progress. | ||
|
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
| Design Start: Dec 2023 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,000,000 | Costs to Date: $655,109 | Balance: $344,891 |
| Weekly Update: 9/11/2026: Construction 45% complete. MEP installation work in progress. | ||
|
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,434,413 | Costs to Date: $1,372,007 | Balance: $62,406 |
| Weekly Update: 9/11/2026: Construction 45% complete. Slab completed in the west wing. Drywall work in progress in the eastern wing. | ||
|
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
| Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
| Budget/PPR: $1,665,601 | Costs to Date: $1,462,044 | Balance: $203,557 |
| Weekly Update: 9/10/2026: Construction 100% complete. Project started June 29, 2026. Mold abatement complete. Wall repair, texture, and paint complete. Flooring complete. Punch walk complete. Final walk to be scheduled. | ||
|
BC Soccer Field
|
||
| Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
| Budget/PPR: $12,000,000 | Costs to Date: $755,075 | Balance: $11,244,925 |
| Weekly Update: 9/11/2026: Plans submitted to DSA. | ||
|
BC Softball Fieldhouse Title 9
|
||
| Design Start: Oct 2026 | Project Status: In Design |
Funding Source: Local C.O. BC Local C.O. DO |
| Budget/PPR: $2,200,000 | Costs to Date: $0 | Balance: $2,200,000 |
| Weekly Update: 9/1/2026 Reviewing proposal for Cube Building | ||
|
BC Student Housing
|
||
| Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
| Budget/PPR: $63,445,000 | Costs to Date: $61,267,891 | Balance: $2,177,109 |
| Weekly Update: 9/1/2026: Construction 88% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion November 2026. | ||
|
BC Swing Space Modular Purchase
|
||
| Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
| Budget/PPR: $1,200,000 | Costs to Date: $998,672 | Balance: $201,328 |
| Weekly Update: 9/11/2026: Settlement has been reached. Coordinating with vendor for transfer of title. | ||