Facilities and Construction Report
Date: March 13, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $59,152,750 Balance: $1,334,442
Weekly Update: 3/6/2026: Construction 73% complete. Working on interior and exterior finishes. Furniture has been ordered. Anticipated completion Mid-July 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 3/6/2026: Closeout in progress.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 3/6/2026: BC 99% complete. Awaiting redesign from PG&E. Updated completion date is May 2026



Projects Summaries

BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $796,188 Balance: $3,812
Weekly Update: 2/17/2026: Construction 100% complete. Punch list items in progress.


BC Campus Wide ADA Projects
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $294,000 Costs to Date: $0 Balance: $294,000
Weekly Update: 3/12/2026: Meeting has been scheduled with the campus for 3-9-2026 to review and scope the project prior to moving forward.


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,453,814 Balance: $44,186
Weekly Update: 2/27/2026: Construction 98% complete. Cameras have been installed. Contractor is completing testing on the equipment.



Projects Summaries

BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $1,309,778 Balance: $26,683,222
Weekly Update: 2/17/2026: Basic requirement overview complete and briefed to BC staff. Design and budget meeting complete. Final layout approved, moving into construction documents.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 2/17/2026: Initial planning to start January or February 2026.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,670,499 Balance: $8,329,501
Weekly Update: 2/17/2026: Final concept and floor plan approved. Moving into construction documents phase.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $6,150,000 Costs to Date: $5,762,095 Balance: $387,906
Weekly Update: 2/27/2026: Pools have been drained. Demolition of northern building set to begin on 3/2/26


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $0 Balance: $361,000
Weekly Update: 3/12/26: Architect estimates have been sent to the campus.


BC Culinary Arts Lab Renovation
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,500,000 Costs to Date: $0 Balance: $4,500,000
Weekly Update: 2/27/2026: Architect has been selected. Proposal forthcoming.



Projects Summaries

BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $25,500 Balance: $474,500
Weekly Update: 2/27/2026: Project in design phase.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $3,699,785 Balance: $200,215
Weekly Update: 2/27/2026: Ground is being excavated to extend the sump.


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $277,187 Balance: $722,813
Weekly Update: 2/27/2026: Project is currently out to bid. Bid opening 3-10-2026.



Projects Summaries

BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,109,175 Balance: $577,280
Weekly Update: 2/27/2026: Construction is 60% complete. The remaining work will be completed during spring break 2026.


BC Fine Arts Replacement
Design Start: Oct 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $13,618,000 Costs to Date: $0 Balance: $13,618,000
Weekly Update: 2/27/2026: Project is in preliminary design phase.


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,470,017 Balance: $6,529,983
Weekly Update: 2/27/2026: PG&E has approved design and switchgear. Switchgear is to be shipped in October 2026.



Projects Summaries

BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $672,113 Balance: $152,887
Weekly Update: 2/27/2026: Construction 99% complete. Final job walk has been scheduled


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $42,179 Balance: $757,821
Weekly Update: 2/17/2026: Construction 100% complete for initial contract. Additional repairs to inverters complete and start up conducted. Approval of repairs to circuit boards complete. Scheduling remaining work.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 2/27/2026: Construction is 95% complete. Equipment has been installed. Testing is scheduled on 2-27-2026



Projects Summaries

BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $350,000 Costs to Date: $0 Balance: $350,000
Weekly Update: 3/12/26: Contract award going to March Board meeting for approval.


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $29,722 Balance: $230,278
Weekly Update: 2/27/2026: Project is in bidding phase. Bid opening 3-5-2026.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 2/27/2026: Construction is 95% complete. Air balance is scheduled for 3/16.



Projects Summaries

BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 2/27/2026: Construction is 95% complete. Air Balance is scheduled 3/19


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $190,796 Balance: $9,204
Weekly Update: 2/27/2026: Received recorded NOC. Preparing project closeout.


BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $611,532 Balance: $538,468
Weekly Update: 2/27/2026: Currently out to bid. Bid opening scheduled 3-10-2026.



Projects Summaries

BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $397,429 Balance: $1
Weekly Update: 2/27/2026: Construction is 100% complete. NOC has been filed.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,144,575 Balance: $358,705
Weekly Update: 2/17/2026: Child Development Center and Maintenance Operations buildings to be painted summer of 2026.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $144,970 Balance: $855,030
Weekly Update: 2/27/2026: Awaiting DSA plan approval.



Projects Summaries

BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $633,120 Balance: $1,108,147
Weekly Update: 2/27/2026: Bids under review. Construction to start May 2026.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,067,097 Balance: $598,504
Weekly Update: 2/17/2026: Phase II first floor design in progress. Project to bid March 2026 for completion in May 2026. Preliminary floor layout and paint colors under review.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $680,200 Balance: $11,319,800
Weekly Update: 2/27/2026: Design in progress. Site plan approved by the campus on 1-13-2026.



Projects Summaries

BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $56,156,934 Balance: $7,288,066
Weekly Update: 3/6/2026: Construction 71% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Anticipated completion October 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,472,100 Balance: $77,900
Weekly Update: 3/6/2026: Payment on remaining lease balance in progress.


BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 2/27/2026: Campus has decided to closeout this project and not continue.