Facilities and Construction Report
Date: September 20, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu
Ginger Popplewell Department Assistant III 661-336-5093 ginger.popplewell@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $61,987,192 Costs to Date: $60,941,310 Balance: $1,045,882
Weekly Update: 9/1/2026: Construction 91% complete. Working on interior and exterior finishes. Furniture and technology will be installed September 2026. Anticipated completion October 2026.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 9/1/2026: BC 99% complete. Labor to install switchgear to go out to bid mid September 2026. Board approval October 2026. Updated completion date to utilize 100% of solar is November 2026.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $799,312 Balance: $688
Weekly Update: 9/10/2026: All forms submitted to DSA. Awaiting DSA certification.



Projects Summaries

BC BC Campus Wide HVAC Repair & Replacement
Design Start: Aug 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $3,166,666 Costs to Date: $0 Balance: $3,166,666
Weekly Update: 9/1/206 PPR approved.


BC Campus Wide ADA Projects
Design Start: Mar 2026 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $794,000 Costs to Date: $187,860 Balance: $606,140
Weekly Update: 9/11/2026: Architect working on project plans to submit to DSA.


BC Campuswide Elevator Upgrades & Rehabilitation
Design Start: Jun 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $6,250,000 Costs to Date: $0 Balance: $6,250,000
Weekly Update: 9/11/2026: Work authorization in progress. In preliminary design phase.



Projects Summaries

BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $3,657,603 Balance: $24,335,397
Weekly Update: 9/10/2026: Design and budget meeting complete. Final layout approved. Moving into construction documents. Project approved by State Chancellors Office. Mechanical and electrical systems design complete. Final design for furniture complete. 3D design and basic color review complete. Resubmit to DSA on October 13, 2026.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $598,110 Balance: $1,401,890
Weekly Update: 9/10/2026: Furniture and office space floor plan for library complete. Communication and electrical connections complete for Phase I. Data cabling installation complete. Meeting September 11, 2026, for Phase II location and coordination.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,867,474 Balance: $8,132,526
Weekly Update: 9/10/2026: Final concept and floor plan approved. Construction documents in progress. Final landscape plan, interior finishes, and security/door access and controls meeting in progress. DSA submission scheduled for October 2, 2026.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $6,550,000 Costs to Date: $6,012,830 Balance: $537,170
Weekly Update: 9/11/2026: Construction 40% complete. Contractor installing underground utilities and footings for foundation of the pool equipment building.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $19,787 Balance: $341,213
Weekly Update: 9/11/2026: Architect has submitted drawings to DSA.


BC Culinary Arts Lab Renovation
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,500,000 Costs to Date: $474,305 Balance: $4,025,696
Weekly Update: 9/11/2026: Elevation plan approved. Drawings are in design phase.



Projects Summaries

BC DC Randolph Center Maintenance Repairs
Design Start: Apr 2026 Project Status: In Const Funding Source: Local C.O. DO
Budget/PPR: $600,000 Costs to Date: $581,517 Balance: $18,483
Weekly Update: 9/11/2026: Construction 95% complete. Fire alarm upgrades in progress.


BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $66,961 Balance: $433,039
Weekly Update: 9/11/2026: Plans resubmitted to DSA for backcheck comments. Awaiting DSA review.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $3,703,724 Balance: $196,276
Weekly Update: 9/11/2026: Phase II construction 95% complete. Punch work and change order work in progress.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $504,992 Balance: $495,008
Weekly Update: 9/11/2026: Construction 85% complete. Shade structure and concrete pad completed. Fencing work in progress.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,166,823 Balance: $519,632
Weekly Update: 9/11/2026: Construction 100% complete. Contractor preparing closeout documents. Air balance to be readjusted per mechanical engineer's recommendation.


BC Emergency Management Indoor Speakers
Design Start: Sep 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,070,000 Costs to Date: $0 Balance: $1,070,000
Weekly Update: 9/11/2026: In design phase.



Projects Summaries

BC Fine Arts Replacement
Design Start: Oct 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $13,618,000 Costs to Date: $0 Balance: $13,618,000
Weekly Update: 9/11/2026: Architect selected, Work Authorization approved. Project in preliminary design phase.


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,408,834 Balance: $6,591,166
Weekly Update: 9/14/2026: Switchgear received. Proposal for installation forthcoming.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $79,671 Balance: $720,329
Weekly Update: 9/10/2026: Construction 100% complete for initial contract. Approval of repairs to circuit boards complete. New inverter boards completed. Inverters shutdown due to over temperature. Additional work required. Proposal received for new power supplies, cable sensors, and filters. Awaiting proposal for inverter replacement to determine options.



Projects Summaries

BC Mass Communication
Design Start: Aug 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $197,098 Balance: $352,902
Weekly Update: 9/11/2026: Construction complete. NOC filed for original scope of work. Preparing Bid documents for added scope of work.


BC Math Science Allied Health- Room 14 Remodel
Design Start: May 2026 Project Status: In Design Funding Source: Other
Budget/PPR: $450,000 Costs to Date: $145,060 Balance: $304,940
Weekly Update: 9/11/2026: Project in bidding phase. Job walk scheduled on 9/22/26, Bid opening scheduled 10/1/26.


BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Const Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $350,000 Costs to Date: $316,730 Balance: $33,270
Weekly Update: 9/11/2026: Closeout in progress.



Projects Summaries

BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $300,000 Costs to Date: $297,411 Balance: $2,589
Weekly Update: 9/11/2026: Construction 75% complete. Base for the Removable bollards installed. Awaiting sphere bollard installation.


BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $415,207 Costs to Date: $415,207 Balance: $0
Weekly Update: 9/11/2026: Construction 100% complete. NOC has been filed.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $440,852 Costs to Date: $440,851 Balance: $1
Weekly Update: 9/11/2026: Construction 100% complete. NOC to be filed.



Projects Summaries

BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $853,548 Balance: $296,452
Weekly Update: 9/11/2026: Construction 95% complete. Awaiting sack and patch work to be completed.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,206,137 Balance: $297,143
Weekly Update: 9/10/2026: Child Development Center complete. Punch items complete. M&O building complete. Punch walk complete. NOC in progress.


BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $655,109 Balance: $344,891
Weekly Update: 9/11/2026: Construction 45% complete. MEP installation work in progress.



Projects Summaries

BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,434,413 Costs to Date: $1,372,007 Balance: $62,406
Weekly Update: 9/11/2026: Construction 45% complete. Slab completed in the west wing. Drywall work in progress in the eastern wing.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,462,044 Balance: $203,557
Weekly Update: 9/10/2026: Construction 100% complete. Project started June 29, 2026. Mold abatement complete. Wall repair, texture, and paint complete. Flooring complete. Punch walk complete. Final walk to be scheduled.


BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $755,075 Balance: $11,244,925
Weekly Update: 9/11/2026: Plans submitted to DSA.



Projects Summaries

BC Softball Fieldhouse Title 9
Design Start: Oct 2026 Project Status: In Design Funding Source: Local C.O. BC
Local C.O. DO
Budget/PPR: $2,200,000 Costs to Date: $0 Balance: $2,200,000
Weekly Update: 9/1/2026 Reviewing proposal for Cube Building


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $61,267,891 Balance: $2,177,109
Weekly Update: 9/1/2026: Construction 88% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion November 2026.


BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $998,672 Balance: $201,328
Weekly Update: 9/11/2026: Settlement has been reached. Coordinating with vendor for transfer of title.