Facilities and Construction Report
Date: April 15, 2026


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $60,651,827 Balance: ($164,635)
Weekly Update: 4/13/2026: Construction 81% complete. Working on interior and exterior finishes. Furniture has been ordered. Anticipated completion Mid-July 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 4/13/2026: Closeout in progress.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 4/13/2026: BC 99% complete. Awaiting redesign from PG&E. Updated completion date is Oct 2026.



Projects Summaries

BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $796,188 Balance: $3,812
Weekly Update: 4/10/2026: Construction 100% complete. Punch list items in progress. Closeout in progress.


BC Campus Wide ADA Projects
Design Start: Mar 2026 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $794,000 Costs to Date: $0 Balance: $794,000
Weekly Update: 4/13/2026: Campus approved moving forward with project. Architect to provide design cost and update construction cost for the project.


BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $1,453,814 Balance: $44,186
Weekly Update: 4/10/2026: Construction 98% complete. Cameras have been installed. Contractor is completing testing on the equipment.



Projects Summaries

BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. BC
Budget/PPR: $27,993,000 Costs to Date: $1,363,328 Balance: $26,629,672
Weekly Update: 4/10/2026: Design and budget meeting complete. Final layout approved. Moving into construction documents. Project submitted to State Chancellor for approval.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 4/10/2026: Initial planning to start. Development of scope in progress.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $1,676,999 Balance: $8,323,001
Weekly Update: 4/10/2026: Final concept and floor plan approved. Construction documents in progress.



Projects Summaries

BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $6,150,000 Costs to Date: $5,763,320 Balance: $386,681
Weekly Update: 4/10//2026: Construction 25% complete. Demolition of the pool deck in progress.


BC Combined Gym and Fieldhouse Phase II
Design Start: Oct 2025 Project Status: In Design Funding Source: Meas. G
Budget/PPR: $361,000 Costs to Date: $0 Balance: $361,000
Weekly Update: 4/13/26: Campus approved project cost. Architect Work Authorization going to May board for approval.


BC Culinary Arts Lab Renovation
Design Start: Feb 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $4,500,000 Costs to Date: $0 Balance: $4,500,000
Weekly Update: 4/10/2026: Architect Work Authorization going to April Board for approval.



Projects Summaries

BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $62,000 Balance: $438,000
Weekly Update: 4/10/2026: Project in design phase. DSA appointment will be scheduled in the following weeks.


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,900,000 Costs to Date: $3,699,785 Balance: $200,215
Weekly Update: 4/10/2026: Phase II construction 35% complete. Rough grading of project area in progress.


BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $288,876 Balance: $711,124
Weekly Update: 4/10/2026: Bids under review.



Projects Summaries

BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,686,455 Costs to Date: $1,110,175 Balance: $576,280
Weekly Update: 4/10/2026: Construction 75% complete. Installation of boiler in progress.


BC Fine Arts Replacement
Design Start: Oct 2026 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $13,618,000 Costs to Date: $0 Balance: $13,618,000
Weekly Update: 4/10/2026: Project is in preliminary design phase.


BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $8,470,017 Balance: $6,529,983
Weekly Update: 4/13/2026: PG&E has approved design and switchgear. Switchgear is to be shipped in October 2026. Working with Electrical Engineer to put together bid documents.



Projects Summaries

BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: Close-out Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $730,282 Balance: $94,718
Weekly Update: 4/10/2026: Project complete. Preparing project closeout.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $42,179 Balance: $757,821
Weekly Update: 4/10/2026: Construction 100% complete for initial contract. Additional repairs to inverters complete and start up conducted. Approval of repairs to circuit boards complete. Scheduling final inverter repairs.


BC Mass Communication
Design Start: Aug 2024 Project Status: Close-out Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $195,498 Balance: $354,502
Weekly Update: 4/10/2026: Construction complete. Electrical Engineer preparing additional scope of work.



Projects Summaries

BC Math Science Allied Health- Room 14 Remodel
Design Start: May 2026 Project Status: In Design Funding Source: Other
Budget/PPR: $450,000 Costs to Date: $0 Balance: $450,000
Weekly Update: 4/10/2026: Project in preliminary plans phase. Awaiting proposal from architect.


BC Safety Lighting Phase II
Design Start: Sep 2025 Project Status: In Design Funding Source: Meas. G
Local C.O. BC
Budget/PPR: $350,000 Costs to Date: $0 Balance: $350,000
Weekly Update: 4/13/26: Contract award going to April Board meeting for approval. Construction set to start late May 2026.


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $300,000 Costs to Date: $33,043 Balance: $266,957
Weekly Update: 4/10/2026: Contract set to be awarded on the May Board agenda.



Projects Summaries

BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $415,207 Balance: $44,793
Weekly Update: 4/10/2026: Construction 95% complete. Air balance complete.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $440,851 Balance: $39,149
Weekly Update: 4/10/2026: Construction 95% complete. Air Balance complete.


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $190,796 Balance: $9,204
Weekly Update: 4/10/2026: Closeout in progress.



Projects Summaries

BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $614,337 Balance: $535,663
Weekly Update: 4/10/2026: Contract set to be awarded on the April Board agenda.


BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: Close-out Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $397,429 Balance: $1
Weekly Update: 4/10/2026: Preparing project closeout.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,503,280 Costs to Date: $1,154,875 Balance: $348,405
Weekly Update: 4/10/2026: Child Development Center and Maintenance Operations buildings to be painted summer of 2026. Project out to bid.



Projects Summaries

BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $144,970 Balance: $855,030
Weekly Update: 4/10/2026: Project has received DSA approval. Bid schedule forthcoming.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $645,120 Balance: $1,096,147
Weekly Update: 4/10/2026: Contract set to be awarded on the May Board agenda.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,665,601 Costs to Date: $1,067,097 Balance: $598,504
Weekly Update: 4/10/2026: Phase II bids under review.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $682,000 Balance: $11,318,000
Weekly Update: 4/10/2026: Design in progress. Site plan and floor plan approved by campus.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $59,681,260 Balance: $3,763,740
Weekly Update: 4/13/2026: Construction 75% complete. Contractor has put notice of claim on a number of change orders. Submitted new design to PG&E for separate power. Contractor working on exterior finishes and interior utilities. Anticipated completion October 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,384,201 Balance: $165,799
Weekly Update: 4/13/2026: Payment on remaining lease balance in progress.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $993,872 Balance: $206,128
Weekly Update: 4/10/2026: Campus has decided to closeout this project and not continue. Legal notice sent, awaiting vendor response.