Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Omar Flores | Project Manager | 661-336-5132 | omar.flores@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
BC Agriculture Building
|
||
Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $60,487,192 | Costs to Date: $58,637,444 | Balance: $1,849,748 |
Weekly Update: 8/22/2025: Construction 47% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion August 2026. |
BC Allied Health Math Science Remodel
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
Weekly Update: 8/22/2025: Closeout in progress. |
BC Arvin 4th and Walnut Grant Project
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $5,355,748 | Costs to Date: $0 | Balance: $5,355,748 |
Weekly Update: 9/5/2025: Design Build Contract sent to vendor for signature. |
BC Arvin Educational Center
|
||
Design Start: Jun 2020 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $29,818,338 | Costs to Date: $29,718,743 | Balance: $99,595 |
Weekly Update: 8/22/2025: Waiting on signage, and monument sign. Closeout documents and DSA closeout in progress. |
BC Bakersfield College and Delano Center Solar
|
||
Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
Weekly Update: 8/22/2025: BC 99% complete. PG&E has determined that the design is inadequate and will need to be redesigned. Update on design and construction is 6-8 months out. |
BC Baseball Dugout Replacement
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $800,000 | Costs to Date: $676,753 | Balance: $123,247 |
Weekly Update: 9/5/2025: Construction 25% complete. Existing dugouts removed. Earthwork in progress. First and third base dugout compaction complete. Concrete foundation complete. Vertical construction to start September 8, 2025. Project completion September 2025. |
BC Campus Wide ADA Projects
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
Budget/PPR: $294,000 | Costs to Date: $0 | Balance: $294,000 |
Weekly Update: |
BC Campus Wide Security Cameras
|
||
Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
Budget/PPR: $1,498,000 | Costs to Date: $1,441,152 | Balance: $56,848 |
Weekly Update: 9/5/2025: Construction 75% complete. Pending 5 cameras at the solar canopy. Anticipated completion December 2025. |
BC Center For Student Success
|
||
Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J State C.O. PC |
Budget/PPR: $27,993,000 | Costs to Date: $1,274,000 | Balance: $26,719,000 |
Weekly Update: 9/5/2025: PPR Approved. Architect selection complete. Initial design planning interviews completed. Next interview session September 17, 2025. |
BC Center for Student Success Swing Space
|
||
Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
Weekly Update: 9/5/2025: Project approved. Initial planning to start January 2026. |
BC Combined Gym & Fieldhouse (Modular Swing Space)
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $150,000 | Costs to Date: $73,644 | Balance: $76,356 |
Weekly Update: 9/5/2025: Closeout in progress. |
BC Combined Gym & Fieldhouse Pool Administration Building
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $10,000,000 | Costs to Date: $1,670,499 | Balance: $8,329,501 |
Weekly Update: 9/5/2025: Revised PPR in progress to start final designs and approval for working drawings and DSA submission. |
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $6,000,000 | Costs to Date: $720,477 | Balance: $5,279,523 |
Weekly Update: 9/5/2025: Project is out to bid. Job-Walk scheduled 9-18-25. |
BC Combined Gym and Fieldhouse
|
||
Design Start: Jan 2019 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $67,700,000 | Costs to Date: $63,948,238 | Balance: $3,751,762 |
Weekly Update: 8/22/2025: DSA closeout in progress. |
BC Combined Gym and Fieldhouse Phase II
|
||
Design Start: Oct 2025 | Project Status: In Design |
Funding Source: Meas. G |
Budget/PPR: $361,000 | Costs to Date: $0 | Balance: $361,000 |
Weekly Update: |
BC Delano Center Agrivoltaics Farm
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Other |
Budget/PPR: $500,000 | Costs to Date: $0 | Balance: $500,000 |
Weekly Update: 9/5/2025:Project is in the preliminary plan phase. |
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $3,000,000 | Costs to Date: $2,529,117 | Balance: $470,883 |
Weekly Update: 9/5/2025: Phase 1 construction 66% complete. Closeout on phase I in progress. Phase II approved by DSA. Bidding documents forthcoming. |
BC Delano Center Welding Lab Expansion
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,000,000 | Costs to Date: $275,237 | Balance: $724,763 |
Weekly Update: 9/5/2025: Plans in DSA for review and approval. |
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,686,455 | Costs to Date: $71,004 | Balance: $1,615,451 |
Weekly Update: 9/5/2025: Award of contract going to the Board for approval September 11, 2025. |
BC Infrastructure
|
||
Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $15,000,000 | Costs to Date: $7,833,652 | Balance: $7,166,348 |
Weekly Update: 8/22/2025: Water scope on hold. Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study complete. High Voltage is high priority due to power outages. PG&E approved Engineer design. |
BC Infrastructure Campus Wide Rekeying
|
||
Design Start: Sep 2024 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $825,000 | Costs to Date: $667,337 | Balance: $157,663 |
Weekly Update: 9/5/2025: Construction 95% complete. Work in progress. |
BC Infrastructure Solar Inverter Repairs
|
||
Design Start: Nov 2024 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 9/5/2025: Construction 60% complete. Phase I to be completed September 2025. |
BC Lab Tech Bachelors Program
|
||
Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
Budget/PPR: $2,612,000 | Costs to Date: $2,318,439 | Balance: $293,561 |
Weekly Update: 8/22/2025: Closeout in progress. |
BC Mass Communication
|
||
Design Start: Aug 2024 | Project Status: In Const |
Funding Source: Local C.O. BC |
Budget/PPR: $550,000 | Costs to Date: $195,498 | Balance: $354,502 |
Weekly Update: 9/5/2025: Contract awarded. Submittals are in progress and review. |
BC Safety Lighting Phase II
|
||
Design Start: Sep 2025 | Project Status: In Design |
Funding Source: Meas. G |
Budget/PPR: $120,000 | Costs to Date: $0 | Balance: $120,000 |
Weekly Update: |
BC Security Gates and Bollards
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $260,000 | Costs to Date: $28,522 | Balance: $231,478 |
Weekly Update: 9/5/2025: Project is out to bid. Job walk is scheduled on 9-5-25. Bid opening 9-18-25. |
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $460,000 | Costs to Date: $415,207 | Balance: $44,793 |
Weekly Update: 9/5/2025:Submittals are in progress and review. Construction to start tentatively October 2025. |
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
Design Start: Feb 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $480,000 | Costs to Date: $440,851 | Balance: $39,149 |
Weekly Update: 9/5/2025:Submittals are in progress and review. Construction to start tentatively October 2025. |
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
Weekly Update: 9/5/2025: Bid documents have been drafted. BC staff to review. |
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,150,000 | Costs to Date: $425,172 | Balance: $724,828 |
Weekly Update: 9/5/2025: Establishing new project area for remaining funds. |
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $397,430 | Costs to Date: $397,429 | Balance: $1 |
Weekly Update: 9/5/2025: Additional server work added to the project. Construction is 50% complete. |
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,938,882 | Costs to Date: $1,147,775 | Balance: $791,107 |
Weekly Update: 9/5/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch walk complete. Rework in progress. |
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,000,000 | Costs to Date: $143,770 | Balance: $856,230 |
Weekly Update: 9/5/2025: Awaiting DSA plan approval. |
BC SMSR 2022-23 Phase II Window Replacement
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $216,115 | Costs to Date: $200,000 | Balance: $16,115 |
Weekly Update: 3/21/2024: Closeout in process. |
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
Design Start: Feb 2025 | Project Status: In Const |
Funding Source: SMSR Local C.O. BC |
Budget/PPR: $1,741,267 | Costs to Date: $631,111 | Balance: $1,110,156 |
Weekly Update: 9/5/2025: Phase 1 Construction 100% complete. Phase II in DSA. |
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
Design Start: Jan 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,230,000 | Costs to Date: $1,004,902 | Balance: $225,098 |
Weekly Update: 9/5/2025: Flooring complete. Punch items complete. NOC in progress. |
BC Soccer Field
|
||
Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
Weekly Update: 9/5/2025: Design in progress. BC staff to review value engineering proposal. |
BC Student Housing
|
||
Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
Budget/PPR: $63,445,000 | Costs to Date: $58,105,856 | Balance: $5,339,144 |
Weekly Update: 8/22/2025: Construction 45% complete. Site utilities, structural concrete, framing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026. |
BC Swing Space (Measure J)
|
||
Design Start: Sep 2020 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $5,550,000 | Costs to Date: $5,475,430 | Balance: $74,570 |
Weekly Update: 8/22/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing. |
BC Swing Space Modular Purchase
|
||
Design Start: May 2025 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,200,000 | Costs to Date: $993,872 | Balance: $206,128 |
Weekly Update: 9/5/2025: Purchase of modular used for the field house complete. Remaining modular used for the restroom and showers in design. |
BC Welcome Center Interior & Exterior Improvements
|
||
Design Start: Sep 2023 | Project Status: Close-out |
Funding Source: Meas. J Other |
Budget/PPR: $292,358 | Costs to Date: $234,888 | Balance: $57,470 |
Weekly Update: 9/5/2025: Construction completed. Preparing project close out. |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | |