Please contact any of the following regarding questions or comments associated with this report: | |||
Daniel Reed | Interim Associate Vice Chancellor of Construction & Facilities Planning | 661.336.5181 | dareed@kccd.edu |
Christian Beltramo | Project Manager | 760.384.6268 | Christian.Beltramo@kccd.edu |
Chris Soriano | Project Manager | 661.336.5173 | chris.soriano@kccd.edu |
Kim Crews | Administrative Assistant | 661.336.5174 | kcrews@kccd.edu |
Rafaela Cisneros | Budget Analyst | 661.336.5180 | rcisnero@kccd.edu |
Isabel Melendez | Accounting Coordinator | 661-336-5053 | Isabel.Melendez@kccd.edu |
BC Agriculture Building
|
||
Design Start: Aug 2021 | Project Status: In Const |
Funding Source: Meas. J Meas. G |
Budget/PPR: $60,487,192 | Costs to Date: $58,636,825 | Balance: $1,850,367 |
Weekly Update: 4/24/2025: Construction 42% complete. Shade structure, and greenhouse are turned over for use. Structural Steel, plumbing and electrical is ongoing. Tentative completion May 2026. |
BC Allied Health Math Science Remodel
|
||
Design Start: Mar 2022 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $2,850,000 | Costs to Date: $0 | Balance: $2,850,000 |
Weekly Update: 4/24/2025: Audit complete and closeout in progress. |
BC Arvin Educational Center
|
||
Design Start: Jun 2020 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $29,818,338 | Costs to Date: $29,686,863 | Balance: $131,475 |
Weekly Update: 4/24/2025: Waiting on signage, wrought iron fencing, and monument sign. Working on closeout documents and DSA closeout. |
BC Bakersfield College and Delano Center Solar
|
||
Design Start: Oct 2021 | Project Status: In Const |
Funding Source: Other |
Budget/PPR: $170,000 | Costs to Date: $0 | Balance: $170,000 |
Weekly Update: 4/24/2025: BC 99% complete. Battery backup equipment installation in progress. Anticipated completion May 2025. Interconnection scheduled for May 2025. |
BC Baseball Dugout Replacement
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $800,000 | Costs to Date: $103,474 | Balance: $696,526 |
Weekly Update: 5/2/2025: Drawings approved by DSA. Project bidding May 22, 2025. Project start June 16, 2025. Project Complete August 2025. |
BC Campus Wide Security Camera
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,298,000 | Costs to Date: $187,906 | Balance: $1,110,094 |
Weekly Update: 4/24/2025: Award of contract going to Board for approval May 2025. |
BC Center for Student Success Planning
|
||
Design Start: Jul 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $36,000,000 | Costs to Date: $92,606 | Balance: $35,907,394 |
Weekly Update: 5/2/2025: Architect work authorization in progress. |
BC Center for Student Success Swing Space
|
||
Design Start: Mar 2025 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $2,000,000 | Costs to Date: $0 | Balance: $2,000,000 |
Weekly Update: |
BC Combined Gym & Fieldhouse (Modular Swing Space)
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $150,000 | Costs to Date: $73,644 | Balance: $76,356 |
Weekly Update: 4/24/2025: DSA closeout approval pending due to solar project. |
BC Combined Gym & Fieldhouse Pool Equipment Building
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $6,000,000 | Costs to Date: $2,246,976 | Balance: $3,753,024 |
Weekly Update: 5/2/2025: DSA approval for demolition of north and south buildings complete. Awaiting approval for equipment building. |
BC Combined Gym and Fieldhouse
|
||
Design Start: Jan 2019 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $67,700,000 | Costs to Date: $64,741,297 | Balance: $2,958,703 |
Weekly Update: 4/24/2025: Pending DSA closeout. |
BC Delano Center Campus Monument Sign/Sidewalk and Landscape
|
||
Design Start: Oct 2023 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $3,000,000 | Costs to Date: $1,876,081 | Balance: $1,123,919 |
Weekly Update: 5/2/2025: Construction 60% complete. Sidewalk on eastern side complete. Possibly doing a deductive change order for the remaining work while we await for SCE to relocate a power pole. |
BC Delano Center Welding Lab Expansion
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $1,000,000 | Costs to Date: $120,250 | Balance: $879,750 |
Weekly Update: 5/2/2025: Revised scope of work approved. In-Design phase. |
BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $600,000 | Costs to Date: $70,000 | Balance: $530,000 |
Weekly Update: 5/2/2025: Design in progress. Work to take place winter of 2025. |
BC Industrial Tech Electrical Lab Remodel
|
||
Design Start: Oct 2023 | Project Status: Close-out |
Funding Source: Other |
Budget/PPR: $1,200,000 | Costs to Date: $0 | Balance: $1,200,000 |
Weekly Update: 4/24/2025: Closeout in progress |
BC Infrastructure
|
||
Design Start: Aug 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $15,000,000 | Costs to Date: $7,705,270 | Balance: $7,294,730 |
Weekly Update: 4/24/2025: Water project: Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study in progress with Engineer. High Voltage is high priority due to power outages. |
BC Infrastructure Campus Wide Rekeying
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $600,000 | Costs to Date: $52,097 | Balance: $547,903 |
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025. |
BC Infrastructure Solar Inverter Repairs
|
||
Design Start: Nov 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $800,000 | Costs to Date: $0 | Balance: $800,000 |
Weekly Update: 4/24/2025: Contract in progress. |
BC Lab Tech Bachelors Program
|
||
Design Start: Apr 2023 | Project Status: Close-out |
Funding Source: Meas. J Local C.O. BC |
Budget/PPR: $2,612,000 | Costs to Date: $2,316,261 | Balance: $295,739 |
Weekly Update: 4/24/2025: Closeout in progress. |
BC Mass Communication
|
||
Design Start: Aug 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $750,000 | Costs to Date: $24,200 | Balance: $725,800 |
Weekly Update: 4/24/2025: Campus to review final design. RFP for bidding forthcoming. |
BC Science and Engineering Phase II
|
||
Design Start: Jan 2024 | Project Status: Close-out |
Funding Source: Meas. J |
Budget/PPR: $2,150,000 | Costs to Date: $2,123,000 | Balance: $27,000 |
Weekly Update: 4/24/2025: Phase 3 to be done during summer break 2025. |
BC Security Gates
|
||
Design Start: Sep 2024 | Project Status: In Design |
Funding Source: Local C.O. BC |
Budget/PPR: $150,000 | Costs to Date: $22,500 | Balance: $127,500 |
Weekly Update: 4/4/2025: Working with campus for final design and approvals. |
BC SMSR 2021-22 Interior Lighting Retrofit
|
||
Design Start: Jan 2022 | Project Status: Close-out |
Funding Source: SMSR |
Budget/PPR: $709,216 | Costs to Date: $709,216 | Balance: $0 |
Weekly Update: 5/2/2025: Construction complete. Closeout in progress. |
BC SMSR 2022-23 Air Handler Replacement Forums
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $350,000 | Costs to Date: $46,189 | Balance: $303,811 |
Weekly Update: 5/2/2025: Award of contract going to Board for approval June 2025. |
BC SMSR 2022-23 Allied Health Chiller Replacement
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $400,000 | Costs to Date: $55,987 | Balance: $344,013 |
Weekly Update: 5/2/2025: Award of contract going to Board for approval June 2025. |
BC SMSR 2022-23 Artificial Turf Installation Campuswide
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $200,000 | Costs to Date: $0 | Balance: $200,000 |
Weekly Update: 5/2/2025: Final bid scope established by campus. Preparing Bid Documents. |
BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
|
||
Design Start: Jan 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,150,000 | Costs to Date: $135,063 | Balance: $1,014,937 |
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025. |
BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
|
||
Design Start: Nov 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $1,500,000 | Costs to Date: $397,429 | Balance: $1,102,571 |
Weekly Update: 5/2/2025: Additional server work added to the project. Work to begin in May 2025. |
BC SMSR 2022-23 Interior and Exterior Painting Campuswide
|
||
Design Start: Apr 2024 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $2,658,882 | Costs to Date: $501,663 | Balance: $2,157,219 |
Weekly Update: 5/2/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, and Softball press boxes, and Stadium will be painted in summer of 2025. Bidding complete. Work to start May 19, 2025. |
BC SMSR 2022-23 Language Arts Restroom Upgrades
|
||
Design Start: Dec 2023 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,000,000 | Costs to Date: $143,770 | Balance: $856,230 |
Weekly Update: 4/24/2025: Awaiting DSA plan approval. |
BC SMSR 2022-23 Pool Deck Replacement
|
||
Design Start: Feb 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $100,000 | Costs to Date: $0 | Balance: $100,000 |
Weekly Update: 5/5/2025: Project being closed and funds moved to SMSR 2022-23 Wall and Floorcovering Replacement Library. |
BC SMSR 2022-23 Recoat Deck Industrial Tech
|
||
Design Start: Jan 2023 | Project Status: In Const |
Funding Source: SMSR |
Budget/PPR: $100,000 | Costs to Date: $26,435 | Balance: $73,565 |
Weekly Update: 4/24/2025: Work complete. Remaining funds to be reallocated. |
BC SMSR 2022-23 Restroom Upgrades FACE Building
|
||
Design Start: Mar 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $1,250,000 | Costs to Date: $119,187 | Balance: $1,130,813 |
Weekly Update: 5/2/2025: Award of contract going to Board for approval May 2025. |
BC SMSR 2022-23 Roof Replacement Industrial Tech
|
||
Design Start: Nov 2023 | Project Status: Close-out |
Funding Source: SMSR Other |
Budget/PPR: $1,800,000 | Costs to Date: $1,782,298 | Balance: $17,702 |
Weekly Update: 4/24/2025: Constuction complete. Remaining funds to be reallocated. |
BC SMSR 2022-23 Wall and Floorcovering Replacement Library
|
||
Design Start: Jan 2024 | Project Status: In Design |
Funding Source: SMSR |
Budget/PPR: $600,000 | Costs to Date: $96,172 | Balance: $503,828 |
Weekly Update: 5/5/2025: Project advertising to bid. Bid opening 5-14-25. |
BC Soccer Field
|
||
Design Start: Apr 2024 | Project Status: In Design |
Funding Source: Meas. J |
Budget/PPR: $12,000,000 | Costs to Date: $680,200 | Balance: $11,319,800 |
Weekly Update: 5/2/2025: Design in progress. Meeting scheduled with BC staff on 5/14/25 for approval. |
BC Student Housing
|
||
Design Start: Nov 2021 | Project Status: In Const |
Funding Source: Other Other |
Budget/PPR: $63,445,000 | Costs to Date: $55,473,729 | Balance: $7,971,271 |
Weekly Update: 4/24/2025: Construction 24% complete. Contractor is waiting for DSA approval on updated drawings. Site utilities, structural concrete and preparing for framing in progress. Anticipated completion May 2026. |
BC Swing Space (Measure J)
|
||
Design Start: May 2018 | Project Status: In Const |
Funding Source: Meas. J |
Budget/PPR: $5,250,000 | Costs to Date: $5,221,425 | Balance: $28,575 |
Weekly Update: 4/24/2025: Project on hold pending funding of Measure 2. |
BC Welcome Center Interior & Exterior Improvements
|
||
Design Start: Sep 2023 | Project Status: Close-out |
Funding Source: Meas. J Other |
Budget/PPR: $292,358 | Costs to Date: $157,045 | Balance: $135,313 |
Weekly Update: 5/2/2025: Contract awarded to Sierra Schools for additional work being completed in the fireside room. |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | BC Combined Gym and Fieldhouse |
BC Combined Gym and Fieldhouse | |