Facilities and Construction Report
Date: August 27, 2025


Facilities and Construction Staff

Please contact any of the following regarding questions or comments associated with this report:
Daniel Reed Interim Associate Vice Chancellor of Construction & Facilities Planning 661.336.5181 dareed@kccd.edu
Christian Beltramo Project Manager 760.384.6268 Christian.Beltramo@kccd.edu
Chris Soriano Project Manager 661.336.5173 chris.soriano@kccd.edu
Omar Flores Project Manager 661-336-5132 omar.flores@kccd.edu
Kim Crews Administrative Assistant 661.336.5174 kcrews@kccd.edu
Rafaela Cisneros Budget Analyst 661.336.5180 rcisnero@kccd.edu
Isabel Melendez Accounting Coordinator 661-336-5053 Isabel.Melendez@kccd.edu

Projects Summaries

BC Agriculture Building
Design Start: Aug 2021 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $60,487,192 Costs to Date: $29,347,474 Balance: $31,139,718
Weekly Update: 8/22/2025: Construction 47% complete. Structural steel, concrete, framing, plumbing, and electrical in progress. Anticipated completion August 2026.


BC Allied Health Math Science Remodel
Design Start: Mar 2022 Project Status: Close-out Funding Source: Other
Budget/PPR: $2,850,000 Costs to Date: $0 Balance: $2,850,000
Weekly Update: 8/22/2025: Closeout in progress.


BC Arvin 4th and Walnut Grant Project
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $5,355,748 Costs to Date: $0 Balance: $5,355,748
Weekly Update: 8/25/2025: Design Build Contract draft pending architects signature.



Projects Summaries

BC Arvin Educational Center
Design Start: Jun 2020 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $29,818,338 Costs to Date: $28,013,107 Balance: $1,805,231
Weekly Update: 8/22/2025: Waiting on signage, and monument sign. Closeout documents and DSA closeout in progress.


BC Bakersfield College and Delano Center Solar
Design Start: Oct 2021 Project Status: In Const Funding Source: Other
Budget/PPR: $170,000 Costs to Date: $0 Balance: $170,000
Weekly Update: 8/22/2025: BC 99% complete. PG&E has determined that the design is inadequate and will need to be redesigned. Update on design and construction is 6-8 months out.


BC Baseball Dugout Replacement
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $800,000 Costs to Date: $88,479 Balance: $711,521
Weekly Update: 8/22/2025: Project start date July 28, 2025. Existing dugouts removed. Earthwork in progress, first base dugout compaction complete. Third base dugout compaction in progress. Project completion September 2025.



Projects Summaries

BC Campus Wide Security Cameras
Design Start: Sep 2024 Project Status: In Const Funding Source: Local C.O. BC
Budget/PPR: $1,498,000 Costs to Date: $187,444 Balance: $1,310,556
Weekly Update: 8/22/2025: Construction 75% complete. Pending 5 cameras at the Solar canopy. Anticipated completion August 2025.


BC Center For Student Success
Design Start: Jul 2025 Project Status: In Design Funding Source: Meas. J
State C.O. PC
Budget/PPR: $27,993,000 Costs to Date: $0 Balance: $27,993,000
Weekly Update: 8/22/2025: PPR Approved. Architect selection complete. Design planning interviews scheduled for September 3, 2025.


BC Center for Student Success Swing Space
Design Start: Mar 2025 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $2,000,000 Costs to Date: $0 Balance: $2,000,000
Weekly Update: 8/22/2025: Project approved. Initial planning to start December 2025.



Projects Summaries

BC Combined Gym & Fieldhouse (Modular Swing Space)
Design Start: Oct 2023 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $150,000 Costs to Date: $69,310 Balance: $80,690
Weekly Update: 8/25/2025: Closeout in progress.


BC Combined Gym & Fieldhouse Pool Administration Building
Design Start: Jan 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $10,000,000 Costs to Date: $219,038 Balance: $9,780,962
Weekly Update: 8/22/2025: Revised PPR in progress to start final designs and approval for DSA submission.


BC Combined Gym & Fieldhouse Pool Equipment Building
Design Start: Dec 2023 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $6,000,000 Costs to Date: $435,096 Balance: $5,564,904
Weekly Update: 8/22/2025: DSA approval for demolition of north and south buildings complete. DSA approval for Equipment Building complete, awaiting release of plans.



Projects Summaries

BC Combined Gym and Fieldhouse
Design Start: Jan 2019 Project Status: Close-out Funding Source: Meas. J
Budget/PPR: $67,700,000 Costs to Date: $63,796,411 Balance: $3,903,589
Weekly Update: 8/22/2025: DSA closeout in progress.


BC Delano Center Agrivoltaics Farm
Design Start: Sep 2025 Project Status: In Design Funding Source: Other
Budget/PPR: $500,000 Costs to Date: $0 Balance: $500,000
Weekly Update:


BC Delano Center Campus Monument Sign/Sidewalk and Landscape
Design Start: Oct 2023 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $3,000,000 Costs to Date: $538,490 Balance: $2,461,510
Weekly Update: 8/25/2025: Phase 1 Construction 66% complete. Closeout on phase I in progress. Phase II approved by DSA. Bidding documents forthcoming.



Projects Summaries

BC Delano Center Welding Lab Expansion
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,000,000 Costs to Date: $64,343 Balance: $935,658
Weekly Update: 8/25/2025: Plans submitted to DSA.


BC Delano SMSR 2022-23 HVAC Replacement Science and Technology
Design Start: Jan 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,702,570 Costs to Date: $63,004 Balance: $1,639,566
Weekly Update: 8/25/2025: Award of contract going to Board for approval September 11, 2025.


BC Industrial Tech Electrical Lab Remodel
Design Start: Oct 2023 Project Status: Close-out Funding Source: Other
Budget/PPR: $1,200,000 Costs to Date: $0 Balance: $1,200,000
Weekly Update: 8/22/2025 Project is closed.



Projects Summaries

BC Infrastructure
Design Start: Aug 2018 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $15,000,000 Costs to Date: $6,507,284 Balance: $8,492,716
Weekly Update: 8/22/2025: Water scope on hold. Construction documents and specifications are complete for bidding purposes. High voltage and Arc Flash study complete. High Voltage is high priority due to power outages. PG&E approved Engineer design.


BC Infrastructure Campus Wide Rekeying
Design Start: Sep 2024 Project Status: In Const Funding Source: Meas. J
Meas. G
Budget/PPR: $825,000 Costs to Date: $4,374 Balance: $820,626
Weekly Update: 8/25/2025: Construction 80% complete. Work in progress.


BC Infrastructure Solar Inverter Repairs
Design Start: Nov 2024 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $800,000 Costs to Date: $0 Balance: $800,000
Weekly Update: 8/22/2025: Construction 60% complete. Phase I of project to be completed Sept 2025.



Projects Summaries

BC Lab Tech Bachelors Program
Design Start: Apr 2023 Project Status: Close-out Funding Source: Meas. J
Local C.O. BC
Budget/PPR: $2,612,000 Costs to Date: $2,207,207 Balance: $404,793
Weekly Update: 8/22/2025: Closeout in progress.


BC Mass Communication
Design Start: Aug 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $550,000 Costs to Date: $8,800 Balance: $541,200
Weekly Update: 8/25/2025: Award of contract going to the Board for approval September 11, 2025.


BC Security Gates and Bollards
Design Start: Sep 2024 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $260,000 Costs to Date: $12,375 Balance: $247,625
Weekly Update: 8/25/2025: Design complete. Bidding documents forthcoming.



Projects Summaries

BC SMSR 2022-23 Air Handler Replacement Forums
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $460,000 Costs to Date: $46,189 Balance: $413,811
Weekly Update: 8/25/2025: Construction to start tentatively October 2025.


BC SMSR 2022-23 Allied Health Chiller Replacement
Design Start: Feb 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $480,000 Costs to Date: $48,487 Balance: $431,513
Weekly Update: 8/25/2025: Construction to start tentatively October 2025.


BC SMSR 2022-23 Artificial Turf Installation Campuswide
Design Start: Jan 2024 Project Status: In Design Funding Source: SMSR
Budget/PPR: $200,000 Costs to Date: $0 Balance: $200,000
Weekly Update: 8/25/2025: Bid documents have been drafted. BC staff to review.



Projects Summaries

BC SMSR 2022-23 Concrete Replacement Campuswide Phase II
Design Start: Jan 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,150,000 Costs to Date: $226,289 Balance: $923,711
Weekly Update: 8/25/2025: Establishing new project area for remaining funds.


BC SMSR 2022-23 HVAC Controls and Equipment Replacement Language Arts
Design Start: Nov 2023 Project Status: In Const Funding Source: SMSR
Budget/PPR: $397,430 Costs to Date: $288,429 Balance: $109,001
Weekly Update: 8/25/2025: Additional server work added to the project.


BC SMSR 2022-23 Interior and Exterior Painting Campuswide
Design Start: Apr 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,938,882 Costs to Date: $1,079,632 Balance: $859,250
Weekly Update: 8/22/2025: Performing Arts, Fine Arts, Math Sciences, Levinson Hall, Baseball, Softball Press Boxes, and Stadium in progress. Punch walk complete. Rework in progress.



Projects Summaries

BC SMSR 2022-23 Language Arts Restroom Upgrades
Design Start: Dec 2023 Project Status: In Design Funding Source: SMSR
Budget/PPR: $1,000,000 Costs to Date: $91,290 Balance: $908,710
Weekly Update: 8/25/2025: Awaiting DSA plan approval.


BC SMSR 2022-23 Restroom Upgrades FACE Building
Design Start: Feb 2025 Project Status: In Const Funding Source: SMSR
Local C.O. BC
Budget/PPR: $1,741,267 Costs to Date: $367,071 Balance: $1,374,197
Weekly Update: 8/25/2025: Phase 1 Construction 100% complete. Phase II in DSA.


BC SMSR 2022-23 Wall and Floorcovering Replacement Library
Design Start: Jan 2024 Project Status: In Const Funding Source: SMSR
Budget/PPR: $1,230,000 Costs to Date: $273,922 Balance: $956,078
Weekly Update: 8/22/2025: Project in progress. Demolition complete. Texture and priming complete. Color selection and carpet pattern approved. Painting complete. Flooring complete. Punch walk complete. Rework in progress, completion scheduled for August 23, 2025.



Projects Summaries

BC Soccer Field
Design Start: Apr 2024 Project Status: In Design Funding Source: Meas. J
Budget/PPR: $12,000,000 Costs to Date: $151,925 Balance: $11,848,075
Weekly Update: 8/25/2025: Design in progress. BC staff to review value engineering proposal.


BC Student Housing
Design Start: Nov 2021 Project Status: In Const Funding Source: Other
Other
Budget/PPR: $63,445,000 Costs to Date: $20,845,122 Balance: $42,599,878
Weekly Update: 8/22/2025: Construction 45% complete. Site utilities, structural concrete, framing in progress. Contractor has put notice of claim on a number of change orders. Submitted design to PGE. Anticipated completion August 2026.


BC Swing Space (Measure J)
Design Start: Sep 2020 Project Status: In Const Funding Source: Meas. J
Budget/PPR: $5,550,000 Costs to Date: $5,441,522 Balance: $108,478
Weekly Update: 8/22/2025: Project on hold pending funding of Measure 2. Updating funds to cover final invoicing.



Projects Summaries

BC Swing Space Modular Purchase
Design Start: May 2025 Project Status: In Design Funding Source: Local C.O. BC
Budget/PPR: $1,200,000 Costs to Date: $975,372 Balance: $224,628
Weekly Update: 8/25/2025: Purchase of modular used for the field house complete. Remaining modular used for the restroom and showers in design.


BC Welcome Center Interior & Exterior Improvements
Design Start: Sep 2023 Project Status: In Const Funding Source: Meas. J
Other
Budget/PPR: $292,358 Costs to Date: $157,045 Balance: $135,313
Weekly Update: 08/25/2025: Construction completed. Preparing project close out.



Projects Pictures
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    
BC Combined Gym and Fieldhouse     BC Combined Gym and Fieldhouse    


Projects Pictures
BC Combined Gym and Fieldhouse